Provision of E&M System which includes, supply, Erection, Testing and Commissioning of
33 KV and 11 KV HT Power Cable network, GIS Substation, DG Sets, tunnel ventilation
system, tunnel lighting, SCADA system and Fire Fighting system etc. for :-
Tunnel T-6, T-9, T-10, T-11 & T12 between Kms 39-61 on Katra-Dharam Section of
Udhampur-Srinagar-Baramulla rail link project (Kauri)
1 T-6 3465
2 T-9 691
3 T-10 1013
4 T-11 835
5 T-12 2137
3
STATUS OF WORK (PHYSICAL)
Sl.no. Tunnel Major Achievements
1. Columns completed.
2. Brick work is completed till FFL.DPC has done.
3. Slab Casting Completed.
4 T12
1.3 ANCHOR FASTENER; M12 X 130mm Make Fischers (SS316) Nos. 13050 13050
1 Approval of GADs Nos 6.00 0.00 0.00 0.00 6.00 0.00 0.00 0.00 6.00 6.00 6.00
3696 mtr is
dispatched since
Supply of 33 kV
2 KM 24.40 1.34 1.34 0.00 23.06 1.67 0.00 1.67 1.67 3.34 0.00 3.34 5.01 02.03.2022 and to
Cable Tray
arrive site on
15.03.2022
33 Kv Cable Tray
3 with erection & KM 24.40 0.00 0.00 0.00 24.40 0.00 0.00 0.00 3.05 3.05 3.05
installation
4 33KV Cable Laying KM 30.67 0.00 0.00 0.00 30.67 0.00 0.00 0.00 2.00 2.00 2.00
Supply of 11 kV
5 KM 24.15 0.00 0.00 0.00 24.15 0.00 0.00 0.00 3.70 3.70 3.70
Cable
Supply of LT Cable
6 KM 68.77 0.00 0.00 0.00 68.77 1.44 2.00 -0.56 -0.56 2.88 0.00 2.88 2.31
Tray
TARGET VS ACHIVEMENT
Targets
Sr. Total
Item Unit
No. Scope Target Completed Feb-22 Mar-22
up to up to Jan- Shortfall Balance Cumulative Cumulative Remarks
Achieved Shortfall Achieved Shortfall
Jan'22 22 Shortfall up Shortfall up
in Feb'22 in Feb'22 in Mar'22 in Mar'22
1 2 3 4 Total to Feb'22 Total to Mar'22
LV cable tray
support of 3.5 KM
still in
LT Cable Tray with manufacturing to
7 erection & KM 68.77 0.00 0.00 0.00 68.77 1.00 0.00 1.00 1.00 2.00 0.00 2.00 3.00 arrive at site on
installation 18.03.2022 and
erection to
complete by
30.03.2022
8 Supply of LT Cable KM 97.08 0.00 0.00 0.00 97.08 0.00 0.00 0.00 4.00 4.00 4.00
Supply of Linear
10 heat detection KM 9.50 0.00 0.00 0.00 9.50 0.00 0.00 0.00 2.00 2.00 2.00
cable
Still in
Supply of 33 kV manufacturing to
11 MT 128.10 0.00 0.00 0.00 128.10 16.00 0.00 16.00 16.00 17.54 0.00 17.54 33.54
Cable support arrive at site on
28.03.2022
33 kV Cable Still in
Support with manufacturing to
12 MT 128.10 0.00 0.00 0.00 128.10 16.00 0.00 16.00 16.00 16.01 0.00 16.01 32.01
erection & arrive at site on
installation 28.03.2022
Overall Physical
Progress of E&M
13 % 100% 25.0% 25% 0% 75% 0.20% 0.10% 0.10% 0.10% 0.80% 0.00% 0.80% 0.90%
works in block
section
Status of erection of various items in tunnels (kms)
33 KV cable Tray 33 KV cable 11 KV cable Tray 11 KV cable LT cable Tray LT cable Fire hydrant pipe
Tunnel
No Scope Progress Scope Progress Scope Progress Scope Progress Scope Progress Scope Progress Scope Progress