Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 11

Progress Review Meeting

Provision of E&M System which includes, supply, Erection, Testing and Commissioning of
33 KV and 11 KV HT Power Cable network, GIS Substation, DG Sets, tunnel ventilation
system, tunnel lighting, SCADA system and Fire Fighting system etc. for :-

Tunnel T-6, T-9, T-10, T-11 & T12 between Kms 39-61 on Katra-Dharam Section of
Udhampur-Srinagar-Baramulla rail link project (Kauri)

E&M WORKS Date:- 14.03.2022


SALIENT FEATURES
E&M Package – I Agency: M/s Piscesia Savronik JV

Sr. No. Tunnel No. Tunnel Length (mtr)

1 T-6 3465

2 T-9 691

3 T-10 1013
4 T-11 835

5 T-12 2137

Contractual Completion Date:30/09/2022


Awarded Cost: Rs. 288.08 Cr.
STATUS OF WORK (PHYSICAL)
Sl.no. Tunnel Major Achievements

Portal Substation- T6 (P1)


1. Cladding Wall completed.
2. Excavation for footing in progress. 40% completed.
3. Footing column in progress. 40% completed.
1 T-6

Portal Substation- T6 (P2)


1. Retaining Wall completed.
2. Excavation for footing in progress. 40% completed.
3. Footing column in progress. 30% completed.

Portal Substation- T10 (P2)


2 T-10
1. Columns completed
2. Slab Casting Completed.

3
STATUS OF WORK (PHYSICAL)
Sl.no. Tunnel Major Achievements

Portal Substation- T11 (P2)

3 T11 1. Columns completed, Lintel beam completed


2. Cladding wall completed.
3. Slab Casting of control room building completed.

Portal Substation- T12 (P1)

1. Columns completed.
2. Brick work is completed till FFL.DPC has done.
3. Slab Casting Completed.
4 T12

Portal Substation- T12 (P2)

1. DG building footing soil excavation is in progress.


2. Excavation, levelling and PCC work is in progress.
STATUS OF WORK (PHYSICAL)

Sl.no. Tunnel Major Achievements

• LV cable tray support marking and drilling completed up to 1188 meters.


1 T6 • 33 kV cable tray support marking and drilling completed up to 500 meters.
• Firefighting Pipe support installation completed up to 1065 meter.

• 33 kV cable tray support marking and drilling completed.


2 T9
• Firefighting Pipe support installation completed up to 685 meter.

• LV cable tray support marking and drilling completed up to 100 meters.


3 T10 • 33 kV cable tray support marking and drilling completed.
• Firefighting Pipe support marking and drilling completed.

• 33 kV cable tray support marking and drilling completed up to 220 meters.


4 T11
• Firefighting Pipe support marking and drilling completed up to 516 meter.

• LV cable tray support marking and drilling completed up to 200 meters.


5 T12 • 33 kV cable tray support marking and drilling completed.
• Firefighting Pipe support installation completed up to 1708 meter.
MATERIALS RECEIVED AT SITE
Sr. No Description Unit Quantity BOQ Qty
1 MAF Fire fighting Pipe Mtr. 7600 10819
1.1 HDG Brackets for Firefighting Pipe Support Nos. 2283 4350

1.2 HDG U Clamp for Firefighting Pipe Nos. 499 4350

1.3 ANCHOR FASTENER; M12 X 130mm Make Fischers (SS316) Nos. 13050 13050

1.4 Flexible Grooved Coupling 8 Inches ( Style 12 ) Nos. 500 1800

2 Junction Box FK 9255 Nos. 558 620


3 Junction Box FK1616 Nos. 4945 5495
4 MAF Lighting System (Make: Wipro) Nos. 4775 5974
5 DWC HDPE Pipe Mtr. 5700 420
6 33 kV HT Cable Mtr. 20094 27600
7 33 kV cable Tray (Niedax & Globe) Mtr. 1344 23739
7.1 Anchor & Fastener MAF 33 KV cable tray (M12x130) Nos. 19270 48810

8 LV cable tray (Make:-Globe & Niedax) Mtr. 2001 77175


TARGET VS ACHIVEMENT
Targets
Sr. Total
Item Unit
No. Scope Target Completed
Feb-22 Mar-22
up to up to Jan- Shortfall Balance Cumulative Cumulative Remarks
Achieved Shortfall Achieved Shortfall
Jan'22 22 Shortfall up Shortfall up
in Feb'22 in Feb'22 in Mar'22 in Mar'22
1 2 3 4 Total to Feb'22 Total to Mar'22

1 Approval of GADs Nos 6.00 0.00 0.00 0.00 6.00 0.00 0.00 0.00 6.00 6.00 6.00

3696 mtr is
dispatched since
Supply of 33 kV
2 KM 24.40 1.34 1.34 0.00 23.06 1.67 0.00 1.67 1.67 3.34 0.00 3.34 5.01 02.03.2022 and to
Cable Tray
arrive site on
15.03.2022

33 Kv Cable Tray
3 with erection & KM 24.40 0.00 0.00 0.00 24.40 0.00 0.00 0.00 3.05 3.05 3.05
installation

4 33KV Cable Laying KM 30.67 0.00 0.00 0.00 30.67 0.00 0.00 0.00 2.00 2.00 2.00

Supply of 11 kV
5 KM 24.15 0.00 0.00 0.00 24.15 0.00 0.00 0.00 3.70 3.70 3.70
Cable

Supply of LT Cable
6 KM 68.77 0.00 0.00 0.00 68.77 1.44 2.00 -0.56 -0.56 2.88 0.00 2.88 2.31
Tray
TARGET VS ACHIVEMENT
Targets
Sr. Total
Item Unit
No. Scope Target Completed Feb-22 Mar-22
up to up to Jan- Shortfall Balance Cumulative Cumulative Remarks
Achieved Shortfall Achieved Shortfall
Jan'22 22 Shortfall up Shortfall up
in Feb'22 in Feb'22 in Mar'22 in Mar'22
1 2 3 4 Total to Feb'22 Total to Mar'22

LV cable tray
support of 3.5 KM
still in
LT Cable Tray with manufacturing to
7 erection & KM 68.77 0.00 0.00 0.00 68.77 1.00 0.00 1.00 1.00 2.00 0.00 2.00 3.00 arrive at site on
installation 18.03.2022 and
erection to
complete by
30.03.2022

8 Supply of LT Cable KM 97.08 0.00 0.00 0.00 97.08 0.00 0.00 0.00 4.00 4.00 4.00

U-clamp for fire


pipe support to
arrive at site on
Installation of Fire
9 KM 11.13 1.00 1.00 0.00 10.13 0.50 0.00 0.50 0.50 1.00 0.00 1.00 1.50 10.03.2022,
hydrant pipe
installation will be
completed by
20.03.2022
TARGET VS ACHIVEMENT
Targets
Sr. Total
Item Unit
No. Scope Target Completed
Feb-22 Mar-22
up to up to Jan- Shortfall Balance Cumulative Cumulative Remarks
Achieved Shortfall Achieved Shortfall
Jan'22 22 Shortfall up Shortfall up
in Feb'22 in Feb'22 in Mar'22 in Mar'22
1 2 3 4 Total to Feb'22 Total to Mar'22

Supply of Linear
10 heat detection KM 9.50 0.00 0.00 0.00 9.50 0.00 0.00 0.00 2.00 2.00 2.00
cable

Still in
Supply of 33 kV manufacturing to
11 MT 128.10 0.00 0.00 0.00 128.10 16.00 0.00 16.00 16.00 17.54 0.00 17.54 33.54
Cable support arrive at site on
28.03.2022

33 kV Cable Still in
Support with manufacturing to
12 MT 128.10 0.00 0.00 0.00 128.10 16.00 0.00 16.00 16.00 16.01 0.00 16.01 32.01
erection & arrive at site on
installation 28.03.2022

Overall Physical
Progress of E&M
13 % 100% 25.0% 25% 0% 75% 0.20% 0.10% 0.10% 0.10% 0.80% 0.00% 0.80% 0.90%
works in block
section
Status of erection of various items in tunnels (kms)
33 KV cable Tray 33 KV cable 11 KV cable Tray 11 KV cable LT cable Tray LT cable Fire hydrant pipe
Tunnel
No Scope Progress Scope Progress Scope Progress Scope Progress Scope Progress Scope Progress Scope Progress

T-6 10.395 0 10.395 0 10.395 0 10.395 0 27.72 0 141.833 0 3.465 0

T-9 2.073 0 2.073 0 0 0 0 0 4.146 0 24.4 0 0.691 0

T-10 3.03 0 3.03 0 0 0 0 0 6.06 0 34.54 0 1.01 0

T-11 2.493 0 2.493 0 2.493 0 2.493 0 4.986 0 27.87 0 0.831 0

T-12 6.411 0 6.411 0 6.411 0 6.411 0 17.096 0 83.83 0 2.137 1.222

Total 24.402 0 24.402 0 19.299 0 19.299 0 60.008 0 312.473 0 8.134 1.222


STATUS OF WORK (PHYSICAL)
Tunnel No. Activity Start Date Completion Date

Substation Building, Fire fighting pump house 28-09-2021 14-02-2022

Cable Trays & Firefighting Works 30-11-2021 25-01-2022


T-6
Ventilation System 05-01-2022 24-04-2022

SCADA, Lighting & CCTV 29-03-2022 16-04-2022


T-9 Cable Trays & Firefighting Works 20-11-2021 15-02-2022
Substation Building 06-10-2021 10-03-2022
T-10
Cable Trays & Firefighting Works 30-11-2021 25-04-2022

Substation Building 02-09-2021 04-02-2022


T-11
Cable Trays & Firefighting Works 30-11-2021 25-05-2022
Substation Building, Fire fighting pump house 28-09-2021 18-04-2022
Cable Trays & Firefighting Works 30-11-2021 25-05-2022
T12
Ventilation System 10-01-2022 24-05-2022
SCADA, Lighting & CCTV 29-03-2022 16-09-2022
Integrated System Testing 17-09-2022 30-09-2022

Completion Date – 30-09-2022

You might also like