NATIONAL HIGHWAY WING

NATIONAL HIGHWAYS IN BIHAR

Total length of NH in Bihar : 5976 Km.

🞭 Length of NH with RCD : 2792 Kms.

🞭 Length of NH with NHAI : 3184 Kms.


NATIONAL HIGHWAYS IN BIHAR UNDER RCD
S. No. Particulars Nos. Sanctioned Cost (Rs. in Cr.)

1 NH projects in which work is in progress 41 12441


2 NH projects running behind schedule 21 5208
3 NH projects sanctioned in FY 2022-23 21 7741.98
a Sanctioned Civil work 16 7482
b Sanctioned Pre-construction work 2 258
c Sanctioned DPR work 3 1.98

NH projects in which work has been awarded but appointed date


4 10 4183
yet to be given

Sanctioned NH projects in which bids have been invited but yet to


5 7 2014
be finalized

6 Sanctioned NH projects in which bids are yet to invited 7 3166


Annual Action Plan 2023-24 under NHO

S. Category Length/ Nos Cost


No. (Km) (Rs. in Cr.)

1 DPR 752 26
2 Pre-Construction 599 5235
3 4-laning 82 1180
4 2L+PS 84 480
5 Bypasses/ Realignments 25 825
6 Missing Links/ New NHs 113 960
7 Strengthening/ Raising 83 120
8 Major Bridges/ Minor Bridges 42 10042
9 STMC/PBMC/ PR/IRQP 334 396
Total 2114 19264
Name of the Project : Rehabilitation & Widening work for 2-lane/2-Lane with Paved Shoulder of Existing
NH-80 from km 70.15 to Km 121.025 of Munger – Sultanganj - Bhagalpur section on EPC Mode in the
State of Bihar
Length 50.875 km
Sanction Amount (Rs. in Cr.) Rs. 477.54
Agreement Amount(Rs. in Cr.) Rs. 349.66 Cr.
Name of Contractor M/s MG Construction Pvt. Ltd.
Date of work order 01.02.2023

Date of completion as per agreement/EPCD 31.01.2025

Actual work done (Rs. in Cr.) 5%


(1) C & G - Both Sides complete
Physical progress (2) Translocation and cutting of tree in progress.
(3) Widening of Embankment - RHS completed and LHS in progress
(a) Electrical utility shifting work is in progress.
Utility Shifting
(b) Water supply – RHS Completed and LHS is in progress.
Forest related clearance Stage-I clearance obtained.

Remarks Work is in progress

5
Name of the Project : Rehabilitation & widening work for 2-Lane with Paved Shouldering of Existing NH-80
Alignment from Km. 132.895 to Km 190.150 Bhagalpur – Kahalgaon – Mirzachowki section in the State of Bihar

Length 57.255 km
Sanction Amount (Rs. in Cr.) Rs. 566.15
Agreement Amount(Rs. in Cr.) Rs. 431.54
Name of Contractor M/s TTC Infra India - Jayzee Construction (JV)
Date of work order 04.11.2022
Date of completion as per agreement/EPCD 03.11.2024
Box Culvert - 11 Nos. complete
Scarification – 8.00 Km
E/W 1st layer of subgrade – 4.750 km
2nd layer of subgrade – 3.500 km
Physical progress
Top of subgrade – 3.200 km
Sub Base Course – 0.900 km
Surface – 2.50 Km
Fly Ash- 1.000 Km

Utility Shifting Electric pole Shifting - 3.00 Km

Stage-I clearance obtained.


Forest related clearance
Translocation and cutting of tree in progress.

Remarks Work is in progress.


6
Name of the Project :New 4-laned bridge on river Ganga parallel to existing MG Setu Bridge
Length : 14.5 km
Sanction Amount (Rs. in Cr.) : Rs. 2926.42
Agreement Amount(Rs. in Cr.) : Rs. 1794.37
Name of Contractor : S.P. Singla constructions Pvt. Ltd.
Date of work order : 04.09.2020
Appointed Date : 25.03.2021
Date of completion as per agreement : 22.09.2024

Actual work done (Rs. in Cr.) : 562.54 Cr. & 31.35%


32.37%
 33 wells in progress out of 33 wells, Aggregate length of 1553.36 m out of 1739.46 m well
foundation has been done. 4 Nos of Pier Completed.
 191 piles completed out of 202 piles in Viaduct
 43 Pile cap, 41 Nos Pier, 32 Nos Pier Cap completed out of 46 Nos in Viaduct
Physical Progress :  Girder Casted -164 Nos and Girder Erected -121 Nos out of 245 Nos
 Deck Slab Casted - 22 Nos
 20 piles completed out of 32 piles in Flyover
 4 Nos Pile cap & 4 Nos Pier completed out of 8 Nos in Flyover
 31313 sqm RE Panel Casted and 14123 sqm RE Panel Erected out of 63474 sqm
 184 Nos segment casted (439,14 m) out of 1868 Nos
Land to be acquired : 18.01 cr out of 20.1 cr disbursed
1st stage forest clearance obtained on 30.09.2019.
2nd stage forest clearance obtained on 14.06.2021.
Forest & Environment clearance : Tree cutting/translocation permission received in Patna district on 25/06/2021
Environment Clearance obtained on 25.03.2021
Tree cutting / translocation permission received in Vaishali district on 30/10/2021.
Utility Shifting : Utility shifting is in progress.
Name of the Project :Construction of parallel Bridge to the Vikramshila Setu across Ganga River
after declaration of New NH (New NH-131B)
Length : 19 km
Sanction Amount (Rs. in Cr.) : Rs. 2000
Agreement Amount(Rs. in Cr.) : Rs. 994.77
Name of Contractor : S.P. Singla Construction Pvt. Ltd.
Date of work order : -
Date of completion as per agreement : -
Actual work done (Rs. in Cr.) : -
Physical Progress : -
Forest related clearance and NPV Paid
: -
deposited

LOA issued on 07.09.2022.


Remarks : Agreement signed on 24.02.2023.
Appointed date yet to be issued.
Status of Bidding / award of Work

Sanctioned Cost (Rs in Crore)


Status of Status of Financial

Date of invitation of bid


Technical Bid bid

Bid due date if invited


Date of Original /
revised San.

Date of Finalization

Date of Finalization
Status of Forest
Name of Work Length (km) Status of LA Remarks

Date of opening

Date of opening
Clearance

Construction of
proposed 4_Lane Saran
Revelganj bypass NH- 1)Amount disbursed Rs
28.03Cr.out of Rs
19 in the State of Bihar 7.155 295.25 Awarded on 30.09.2022
50.12Cr.
-
on EPC mode 2) CALA to expedite
connecting NH 19 to 85 remaining disbursement.
origin
Name of the Project :New 4-lane Major Bridge across River Kosi at Phulaut

Sr. Description Details


No
Rs. 1478.40 cr
1 Sanctioned Cost (Sanctioned on 20.9.2018)
Rs. 996.30 cr
2 Awarded Cost ( Awarded to M/s Afcon Infrastructure Ltd. on 04.01.2021 )

3 Agreement Date 12.02.2021


4 Appointed Date 07.06.2021
5 Scheduled Completion Date 06.06.2024
6 Contractor M/s Afcons Infrastructure Ltd.
M/s TPF Engineering Pvt. Ltd in JV with
7 Authority Engineer SA Infrastructure Consultants Pvt. Ltd.

8 Physical Progress 36.72%


9 Financial Progress 35.47%%
SALIENT FEATURES
1 Design Length 28.93 km
2 Major Bridge Length:- 6.93 km
Span Arrangement:- 126 nos x 55m
Width :- 2x12.5m for 120 spans and 2x15.2m for 6 spans
Foundation:-Well Foundation - 127 nos
3 Minor Bridges 07 nos
4 Culverts Pipe :- 21 nos ; Box Culverts:- 45 nos
5 Toll Plaza 01 no. (10 Lane) at Km 133+450
6 Junctions 1 No. Major road junction + 20 Nos. Minor road junctions

7 Busbays 4 Nos.

STATUS OF PROJECT CLEARANCES


1 Forest Clearance Final (Stage–II) approval granted by MoEF&CC vide letter dated
29.12.2020
2 IWAI Approval accorded by CE (IWAI), Noida vide letter dated 12.04.2021
3 Environmental Clearance Not Applicable
4 LA Completed
STATUS OF CIVIL WORK
Sr. No. Area Unit Total Scope Completed Balance to be taken

A Major Bridge
1 Cutting Edge Fabrication Nos 127 127 0.00

2 Well Curb Casting Nos 127 125.00 2.00

3 Well Steining LM 4318 3556.10 761.9

4 Nos 127 54 73
Bottom Plug

5 Nos 127 45 82
Well Cap

6 Pier Nos 127 10 117

7 Pier cap Nos 127 - 127

8 Segment Casting Nos 2394 281 2113


Box/Pipe Culvert Works/minor
bridge works
Sr. No. Area Unit Total Scope
Completed

A Box/Pipe Culvert
1 Earthwork & Subgrade Works cum. 1107991 371650

2 GSB Works cum 70693 -

3 WMM Works cum 80703 -

4 DBM Works cum 25288 -

5 BC Works cum 12464 -

6 Minor Bridge Nos. 7 1.50

7 Pipe Culvert Nos 21 16.50

8 Box Culvert Nos 45 31.50

9 Toe Wall(LHS & RHS side) LM1 32000 245.00

10 Utility Pipe Culvert Nos 88 17.00


STATUS OF CIVIL WORK
Sr. Total Scope In Balance
No. Area Unit (Km) Completed progress to be Remarks
taken up

Highway Works
A
1 Embankment & Subgrade KM 21.79 - 13.5 8.29 Embankment work likely to resume in
Dec’22.

2 GSB/
WMM/DBM/BC KM 21.79 - - 21.79 GSB Work likely to start from Jan 23.

PROJECT MILESTONES
Sr Mile Stone Date Description Status
No.

1 Milestone-1 6th June 2022 Stage Payment Statements for an amount not less Achieved
than 10% of the Contract Price.
2 Milestone-2 19th March 2023 Stage Payment Statements for an amount not less Likely to be achieved
than 35% of the Contract Price. before time

3 Milestone-3 24th December Stage Payment Statements for an amount not less -
2023 than 70% of the Contract Price.

4 Milestone-4 6th June 2024 Schedule Project completion -


THANK YOU
NH projects in which work is in progress
Sl. TPC
NH No. Name of Stretch Length Name of Contractor Remarks
No. (Rs. in Cr.)
1 NH-333A Major Bridge at KM 178 55 M/s Rajbir Construction Pvt. Ltd. Work in progress.
2 NH-19 New MG Setu 14.5 2926.42 M/s S.P. Singla Work in progress.
3 NH-106 Koshi bridge at Phulaut & approach 28.91 1478.4 AFCONS Work in progress.
4 NH-19 ROB at km 132 1 77.38 M/s Gawar Construction Ltd. Work in progress.
5 NH-19 ROB at km 135 1 55.89 M/s Dayal Hi-tech (JV) Work in progress.
6 NH-30A Fathua – Harnaut (NH-30A) 69.51 870.73 M/s Monte Carlo Ltd. & BEL (JV) Work in progress.
7 NH-81 ROB at km 31 1 53.78 M/s. Narayan Das Const. Pvt. Ltd. Work in progress.
8 NH-81 ROB at km 48 1 49.55 Dayal Hitech Baba Hans (JV) Work in progress.
9 NH-82 4 Laning of Bihar Sharif-Gaya 92.935 2138.16 M/s Gayatri Projects Ltd. Work in progress under BSRDCL.
10 NH-101 ROB at km 1.10 & 1.11 (NH-101) 1.52 61.99 M/s Gawar Construction Ltd. Work in progress.
11 NH-103 ROB at km 12 1 146.46 M/s Gawar Construction Ltd. Work in progress.
12 NH-104 Sheohar – Sitamarhi 28.1 178.85 M/s SHEL-RCM (JV) Work in progress.
13 NH-104 Sitamarhi – Jainagar 77.1 369.77 M/s SHEL-RCM (JV) Work in progress.
Work in progress.
14 NH-104 Jainagar – Narahiya (Km156.500 to 219.9450) 63.45 553.3 M/s BSCPL, Hyderabad
M/S IL&FS Engineering &
15 NH-106 Birpur to Bihpur (NH-106) 106 780.77 Work in progress.
Construction Ltd. Hydrabad
Realty Advance structure
16 NH-110 HL Bridge at Km 38(Bandhuganj) 1 12.15 Work in progress.
Enterprised Pvt. Ltd.
3 No. HL Minor Bridge at Km 61.247, 61.65 &
17 NH-110 3 15.22 Ravindra Kumar, Danapur, Patna. Work in progress.
64
18 NH-110 Strengthening Km 68 to 89 21 35.82 Waris Buildcon Work in progress.
19 NH-110 Strengthening Km 36 to 68 26.059 32 Maa Bhagwati Work in progress.
20 NH-120 Goh to Daudnagar 25.41 115.1 M/s Ramiya Const. Pvt. Ltd. Work in progress.
21 NH-120 Nasriganj to Bikramganj 20.2 95.3 M/s Ramiya Const. Pvt. Ltd. Work in progress.
22 NH-131A ROB at km 46 (Sharifganj) 1 44.47 Dayal Hi-Tech GRD (JV) Patna. Work in progress.
Sl. TPC
NH No. Name of Stretch Length Name of Contractor Remarks
No. (Rs. in Cr.)
M/s Brijesh Agrawal, Engineers &
23 NH-131A ROB at km 49 1 61.97 Work in progress.
Constructors
24 NH-327A RoB at Km 24 1 50.59 ASC Infratech Pvt. Ltd. NOIDA Work in progress.
25 NH-327E HL RCC Minor Bridge at Km 81 12.89 Dayal Hitech Engineers Pvt. Ltd. Work in progress.
26 NH-327E ROB at km 100 1 87.86 M/s Bhartiya Infra Project Ltd. Work in progress.
M/s Brijesh Agrawal, Engineers &
27 NH-327E RoB at Km 194 1 77.07 Work in progress.
Constructors
28 NH-28B ROB at km 91 1 62.48 M/s J.K. Engicon Pvt. Ltd. Work in progress.
29 NH-28B ROB at km 94 1 93.54 M/s Brajesh Agrawal Work in progress.
W&S from km 15 to km 30 Chapra-
30 NH-101 15.5 84.98 M/s Palak Infra Pvt. Ltd. work in progress.
Mohammadpur road
Rehabilitation & widening work for 2- Lane with
31 NH-80 Paved Shoulder of Existing NH-80 from km 50.875 477.54 M/s MG Construction Pvt Ltd Work in progress
70.15 to Km 121.025
Rehabilitation & widening work for 2- Lane with
32 NH-80 Paved Shoulder of Existing NH-80 from Km. 57.255 566.15 M/s TTC-JAYZEE (JV) Work in progress
132.895 to Km 190.150
NH-98 (New
33 Additional 2L PS in AIIMS Patna-Naubatpur 10.84 88.33 M/s Adarsh Const. Work in progress
NH-139)
NH-104
Ram Kripal Singh Constructions
34 (New NH- ROB with 2L approach on Jainagar bypass 1.5 70.01 Work in progress
Pvt. Ltd.
227)
35 NH-30 4-L PS in Kayamnagar to Ara 8.6 98.54 M/s Surendra Lahari Work in progress
W&S of km 0 to km 25 of NH-28B Chapwa- M/s Baba Hans Constructions Pvt.
36 NH-28B 24.8 97.6 Work in progress
Valmikinagar road Ltd.
Sl. TPC
NH No. Name of Stretch Length Name of Contractor Remarks
No. (Rs. in Cr.)
Construction of 2 no. of new minor RCC Bridge
37 NH-110 and 3 no. of new box culvert in place of old 5 9.846 M/s Dayal Hi-Tech Work in progress
bridges and culverts on NH-110
38 NH-333A Major Bridge at KM 199 (NH-333A) 1 17 M/s Hari Construction Work in progress
39 NH-81 Km 52+380 to 53+000 on NH-81 0.62 37.56 Chanakya Techno Pvt Ltd Work in progress
40 NH-104 Km. 26 to 27 of NH-104 1.325 5.76 Banshidhar Construction Pvt Ltd Work in progress
41 85 Revealganj Bypass (NH-85) 7 295.25 M/s Adarsh Cont. Work in progress
Bikramganj -Dawath- Maleyabagh - Nawanagr -
42 120 45 178.63 Ramiya Construction Pvt. Ltd Work in progress
Dumraon of NH- 120 excluding Dawath bypass
Total 820.009 12620.11
NH projects in which work has been awarded but appointed date yet to be given

TPC
Sl. No. NH No. Name of Stretch Length Name of Contractor Remarks
(Rs. in Cr.)

1 NH-333 Minor Bridge at km 112 1 24.47 LoA issued

2 NH-122B Mohiuddin nagar – Bachhwada 72 571.71 M/s RKCPL LoA issued.

3 NH-319A Chausa-Mohania 45 427.29 M/s CIVTECT (I) Pvt. Ltd LoA issued

4 NH-527E Rosera - Baheri - Darbhanga (NH-527E) 39.5 495.16 M/s Adarsh Cont. LoA issued

5 NH-333A Major Bridge at KM 199 (NH-333A) 1 17 M/s Hari Construction LoA issued

6 131B New Vikramshila setu 19 1110.23 M/s SP Singla LoA issued

7 131A Amdabad – Manihari (NH-131A) 23.945 353.27 M/s Adarsh Cont. LoA issued

Construction of Chand & Babhua Bypass and


8 NH-219 2/4 laning of Mohania-Bhabhua-Chainpur-UP 46.757 233.38 M/s Balwant Cont. LoA issued
Border (NH-219)

NH-81 &
9 Katihar Bypass 4 203.84 ASC Infratech Pvt Ltd LOA issued
131A

Construction of Bypasses in Km 0 to 72 of
10 NH-333A 72 746.73 M/s RKIPL-HCAPL JV LOA issued
NH-333A

Total 324.202 4183.08


NH projects running behind schedule
Cumul
Scheduled Likely / ative Cumulati
Scheduled Total
Total Delay Appointed Completion Actual Length ve Name of
Sl.N Division/PIU Completion Project
ProjectName Length( in Date/Start Date (Based Construction Comple Physical Contractor/Conce
o. Name Date(Origin Cost(C
km) Years Date on Approved Completion ted Progress ssionaire
al) r)
EOT) Date (km) in %
till date
Jaynagar-Narahia Section
NH Division M/s BSCPL
1 km 156.500 to km 219.945 63.45 4.4 12-May-16 11-Nov-18 31-Mar-21 31-Mar-23 587.41 63.45 93
Sitamarhi Infrastructre Ltd.
Lot-III (New NH-227)
Sitamarhi-Jaynagar Section
NH Division
2 km 79.400 to km 156.500 77 4.3 30-Jun-16 29-Dec-18 30-Jun-21 31-Mar-23 404.1 76.96 98.25 SHEL-RCM(JV)
Sitamarhi
Lot-II (New NH-227)
Construction of ROB at km Gawar
NH Division
3 1.10 & km 1.11 of NH-101 1.5 1.1 28-Aug-19 27-Feb-22 20-Sep-23 62 1.3 57.7 Construction
Chapra
(New NH-331) Limited
Construction of ROB in km M/s Brijesh
NH Division
4 194 (LC no. 53B/T-2) of 1.58 0.9 16-May-20 15-May-22 15-Apr-23 15-Apr-23 77.07 0.4 42.41 Agrawal Engineers
Madhepura
NH 327E & Constructors
Construction of ROB in km
NH Division
5 24 (LC no. 77A) of NH 1.05 1.4 16-May-20 15-Nov-21 01-Mar-23 31-Mar-23 50.59 0.5 52.37
Madhepura
327A
Cumul
Scheduled Likely / ative Cumulati
Scheduled Total
Total Delay Appointed Completion Actual Length ve Name of
Sl.N Division/PIU Completion Project
ProjectName Length( in Date/Start Date (Based Construction Comple Physical Contractor/Conce
o. Name Date(Origin Cost(C
km) Years Date on Approved Completion ted Progress ssionaire
al) r)
EOT) Date (km) in %
till date
Sheohar-Sitamarhi Section
NH Division
6 km 40.000 to 79.400 km 28.5 5 04-May-16 03-May-18 30-Jun-21 31-Mar-23 225.06 28.4 97 SHEL-RCM(JV)
Sitamarhi
Lot-I (NH-227)
Construction of High level
New RCC Bridge at km
NH Division 81.00 of NH-327E on EPC Dayal Hi Tech
7 0.22 1.9 18-Nov-19 17-May-21 31-Mar-23 12.9 0.22 90.13
Araria Mode in the State of Bihar. Engineers (P) Ltd
(Job no. NH-327E-BR-
2018-19/4)
NH Division Construction of ROB in km Dayal hightech -
8 1.05 1.8 08-Oct-18 24-Jun-21 23-Jun-22 31-Mar-23 44 1 90.25
Purnea 46 of NH-131A GRD Jv ,patna
CONSTRUCTION OF
NH Division Bhartia Infra
9 TWO LANE ROB ON NH- 1.8 1.7 14-Aug-19 13-Aug-21 31-Jul-22 30-Apr-23 87.86 1.6 71.05
Araria Projects Ltd.
327E AT KM 100
Widening to 2 lane with
paved shoulder and
strenthening from km 45.00
NH Division M/S Brijendra
10 to 65.00 (design length- 18.99 2.1 13-Sep-19 13-Mar-21 30-Jun-22 30-Jun-23 104.91 20.14 97
Chapra Kumar Singh
18.990) of NH-101 (New
NH-331) on EPC Mode in
the State of Bihar.
Cumul
Scheduled Likely / ative Cumulati
Scheduled Total
Total Delay Appointed Completion Actual Length ve Name of
Sl.N Division/PIU Completion Project
ProjectName Length( in Date/Start Date (Based Construction Comple Physical Contractor/Conce
o. Name Date(Origin Cost(C
km) Years Date on Approved Completion ted Progress ssionaire
al) r)
EOT) Date (km) in %
till date
M/S Il&Fs
NH Division Birpur-Bihpur Section km Engineering And
11 106 3.5 03-Oct-16 02-Oct-19 02-Jan-22 31-Dec-23 780.77 89.36 96.52
Madhepura 0.0 to Km 106 NH 131 Construction
Company Limited
Gaya-Hisua-Rajgir-
CGM BSRDC Nalanda-Biharsharif section Gayatri Projects
12 93 3.5 07-Nov-16 06-Nov-19 31-Mar-22 30-Nov-23 2138.16 83 81.18
Ltd km0.00 to 92.935 NH-82 Limited
(New NH-120)
Construction of ROB on
NH Division Gawar
13 NH-19 at Km 132 (New 2 1.6 26-Aug-19 25-Aug-21 31-Mar-23 77.38 0.85 21
Gulzarbagh construction
NH-31)
Construction of ROB on
NH Division Dayal Hitech Pvt.
14 NH-19 at Km 135 (New 0 0.6 27-Aug-20 26-Aug-22 26-Aug-23 26-Aug-23 55.89 0 60
Gulzarbagh Ltd.
NH-31)
Construction of ROB on GAWAR
NH Division
15 NH-103 at Km 12 (New 2.11 1.6 26-Aug-19 25-Aug-21 25-Aug-22 31-Jul-23 146.46 1.8 83 CONSTRUCTION
Gulzarbagh
NH-322) LTD
Reconstruction of damaged Realty Advance
NH Division Bridge over river Falgu at Structure
16 0.59 3.7 26-May-18 25-Aug-19 31-Mar-22 31-Mar-23 19.76 0.59 88
Gaya km 35 near Bandhuganj on Enterprises Pvt.
NH-110 (New NH-33) Ltd.,
Cumul
Scheduled Likely / ative Cumulati
Scheduled Total
Total Delay Appointed Completion Actual Length ve Name of
Sl.N Division/PIU Completion Project
ProjectName Length( in Date/Start Date (Based Construction Comple Physical Contractor/Conce
o. Name Date(Origin Cost(C
km) Years Date on Approved Completion ted Progress ssionaire
al) r)
EOT) Date (km) in %
till date
Strengthening and widening
to 2 lane with paved
shoulder from km 181.465 M/S Ramiya
NH Division
17 to 201.665 of NH-120 (job- 20.2 0.3 03-Jul-21 02-Jan-23 30-Jun-23 95.31 15.2 72 Constructions
Gaya
120-BR-2017- Private Limited
18/922)Nasriganj -
Vikramganj
NH Division BRIJESH
18 ROB at km 49 of NH-131A 1.21 0.3 05-Jan-21 04-Jan-23 31-Oct-23 55.29 0.2 48.82
Purnea AGRAWAL
Strengthening work in km
NH Division 68.00 to 89.00 NH-110 on Waris Buildcon
19 20.65 1.3 16-Mar-21 15-Dec-21 27-Jul-22 30-Jun-23 35.82 20.65 50
Gaya EPC Mode in the state of India Pvt.Ltd
Bihar (New NH-33)
Strenthening from Km 36
NH Division
20 to 68 in the state of Bihar 23.45 0.9 25-Aug-21 24-May-22 21-Oct-22 19-Apr-23 32.56 23.4 75
Gaya
(New NH-33)
Cumul
Scheduled Likely / ative Cumulati
Scheduled Total
Total Delay Appointed Completion Actual Length ve Name of
Sl.N Division/PIU Completion Project
ProjectName Length( in Date/Start Date (Based Construction Comple Physical Contractor/Conce
o. Name Date(Origin Cost(C
km) Years Date on Approved Completion ted Progress ssionaire
al) r)
EOT) Date (km) in %
till date
M/S Ramiya
NH Division W&S in km 142.05 to
21 25 2 28-Oct-19 27-Apr-21 27-Apr-22 31-Mar-23 115.1 25 98.2 Construction
Gaya 167.465 of NH-120
Pvt.Ltd
SANCTIONED CIVIL WORKS IN FY 2022-23

S. No. Project Name NH No. Length Cost (Rs. Cr.) Status

Pre-Construction activities from km 0 to km 72+000 of NH-333A and


Construction of 3 no. of Bypasses at Sheikhpura, Jamui & Khaira alongwith
1 333A 13.472 376.64 Sanctioned on 27.05.2022
1 no. of realignment at Sikandra (total length-13.472 Km) to two lane with
paved shoulders standard in State of Bihar (Package-I)

Construction of Four-Lane of Chausa-Buxar Bypass from Km 45.000 to Km


2 319A 20.915 1060.16 Sanctioned on 21.09.2022.
69.915 (Package-2) of NH-319A in the State of Bihar on EPC Mode

Pre-Construction activities from Km 134.000 to Km 190.233 of NH-333A and


Construction of 4 no. of Bypasses at Katoria, Lakhpura, Banka & Panjwara
3 333A 14.359 479.37 Sanctioned on 10.11.2022
(total length-14.359 Km) to two lane with paved shoulders standard in
State of Bihar (Package-III)

4 Construction of 4-lane Katihar bypass 31(81) 4.7 232.831 Sanctioned on 27.01.2023.

5 Construction of Saraigarh(on NH-327A) - Lalganj - Ganpatganj upto NH-106 327AD 10.672 91.63 Sanctioned on 06.02.2023

6 4-laning of Gaya - Bodhgaya 120 6.75 63.37 Sanctioned on 06.02.2023


Construction of Raniganj Bypass and Sukela & Bhargama realignments on
7 327E 5.53 98.81 Sanctioned on 06.03.2023.
NH-327E.
8 Construction of Jandaha Bypass on NH-322 (103) 322 4.8 47.43 Sanctioned on 07.03.2023

Improvement and Up-gradation to Four Lane with paved shoulders


configuration from Existing Km 0.000 to Km 39.500 (Design km 0.00 to Km
9 40.342 & 0.50 km in UP portion bridge approach, Design length 40.842 Km) 227A 40.842 1661.25 Sanctioned on 09.03.2023
of NH-227A (near Mehrauna Ghat (UP - Bihar Border) to Siwan) in the state
of Bihar on Hybrid Annuity Model (HAM) mode
Contd......

S. No. Project Name NH No. Length Cost (Rs. Cr.) Status

Construction of 4-lane ROB at km 60 of NH-33 (km 29 of old NH-


10 110 1.93 201.08 Sanctioned on 10.03.2023.
110) at LC no. 29B at Ekangarsarai
Construction of 2 lane with paved shoulder of Daudnagar Bypass,
11 120 5.535 128.39 Sanctioned on 13.03.2023
Nasriganj Bypass & Dawath Bypass
12 Construction of Sarwan to Chakai 333C 15.9 110.39 Sanctioned on 13.03.2023.
Construction of Four lane with paved shoulder of Bhagalpur–
13 Kharhara village (Dhaka more) from Km-0+000 to KM 36+600 (Total 133E 36.6 973.46 Sanctioned on 21.03.2023
Length 36.600 km) of NH 133E on EPC mode in the State of Bihar

Pre-Construction activities from Km 72.000 to Km 134.000 of NH-


333A and Construction of 6 no. of Bypasses at Mangobandar Bypass,
14 Kendua Bypass, Tola Sono Bypass, Jhajha Bypass, Narganjo Bypass & 333A 41 746.73 Sanctioned on 23.03.2023
Bhairoganj Bypass to two lane with paved shoulders standard in
State of Bihar.

Pre-Construction activities from Km 0.000 to Km 53.133 of NH-105


(New NH-527B) and Construction of 4 Lane with Paved shoulder of
15 105 53.133 991.88 Sanctioned on 28.03.2023
Darbhanga (Dilli More) – Banwari Patti from km 0+000 to km 14+950
(Package-1) in State of Bihar

L.A/Preconstruction of Manuapul-Patzirwa-Paknaha-Pipraghat-UP
16 727AA 26.5 218.2 Sanctioned on 30.03.2023
Border Bridge on NH 727AA

Total 302.64 7481.621


SANCTIONED PRE-CONSTRUCTION WORKS IN FY 2022-23

S. No. Project Name NH No. Length Cost (Rs. Cr.) Status

Detailed Project Report for Construction to Two Laning


1 with paved shoulder of Dumraon Bypass of NH-120 (Km 120 5.3 40.12 Sanctioned on 13.03.2023
240.200 to Km 245.500) in Bihar on EPC Mode

L.A/Preconstruction of Manuapul-Patzirwa-Paknaha-
2 727AA 26.5 218.2 Sanctioned on 30.03.2023
Pipraghat-UP Border Bridge on NH 727AA

Total 258.32
SANCTIONED DPR WORKS IN FY 2022-23

S. No. Project Name NH No. Cost (Rs. Cr.) Status

Consultancy Services for preparation of Feasibility Study and


Detailed Project Report for construction of Two lanes with paved
1 122A 0.52 Sanctioned on 27.06.2022
shoulder through Green Field from Vishwanathpur to Kharkabasant
(New NH-122A) with land acquisition of Sitamarhi district in Bihar

2 DPR of Supaul Bypass on NH 327E 327E 0.08 Sanctioned on 24.03.2023

3 DPR of NH 139 from Naubatpur to Hariharganj 139 1.38 Sanctioned on 31.03.2023

TOTAL 1.98
Annual Action Plan 2023-24 under NHO
ANNUAL PLAN FOR DPR WORKS
Approx. Cost of
Length in
Category NH. No. Name of Division Name of Works Projects Remarks
Km & Nos.
(Rs. in Cr)
A Four Laning
(i) FS/ Detailed Engineering
333 Lakhisarai Km 0 to km141 141 5.00
322(103) Gulzarbagh Km 0 to Km 58 58 2.00
22(99) Gaya Km 0 (Dobhi) to Km 13(Gosaindih) 13 0.45
727(28B) Motihari Km 25 to Km 94 69 2.40
227A MoRTH Km 100 to Km 142 42 1.45
227(104) MoRTH Km 0 to Km 103 103 3.60
227(104) Jaynagar Km 104 to Km 217 113 3.95
33(110) Gaya Km 0 to Km 89 89 3.10
120 Gaya Km 103 to Km 118 15 0.50
Total 643.00 22.45
B Bye Passes/ Realignment
(i) FS/ Detailed Engineering
131(106) Madhepura Singheshwar Bypass 5.00 0.15
33(110) Gaya Jehanabad Bypass 7.00 0.20
322 Jaynagar Western bypass of Darbhanga 11.00 0.20
527E Jaynagar Spur to Baheri 7.00 0.25
120 Gaya Spur to Balia 15.00 0.50
Total 45.00 1.30
C Missing Link / New NHs
(i) FS/ Detailed Engineering

Total 0.00 0.00


Contd......
Approx. Cost of
Name of Length in
Category NH. No. Name of Works Projects Remarks
Division Km & Nos.
(Rs. in Cr)
D W&S to 2-lane with paved
shoulder
(i) Feasibility Study / DPR
works
727A Chhapra Km 0 to Km 4.5 5 0.15
119(2C) Gaya Km 41 to Km 92 52.00 0.15
Total 56.50 0.30
F Major Bridge
(i) Feasibility Study / DPR
works
4-lane ROB @ Km 202(Bikramganj) (L.C. No.
120 Gaya 1.00 0.15
46B/T)
33(110) Gaya ROB @ Km 34 (Jehanabad) 1.00 0.15
33(80) Bhagalpur ROB @ Km 72 (Safiyasarai) 1.00 0.15
33(80) Bhagalpur ROB @ Km 181 (Shivnarayanpur) 1.00 0.15
33(80) Bhagalpur ROB @ Km 189 (Mirzachowki) 1.00 0.15
Total 5.00 0.75
G Minor Bridge
(i) Feasibility Study/ DPR
131(106) Madhepura Bridge over Kataiya Hydel tail race & Canal 1 0.50
Bridge at Ch. 100.706 (3x16m), at Ch. 104.275
333 Lakhisarai 1 0.26
(3x16m) & at Ch. 105.855 (4x16m) on NH-333
Total 2 0.76
G. Total 751.5 25.56
ANNUAL PLAN FOR PRE-CONSTRUCTION WORKS
Approx. Cost of
Length in
Category NH. No. Name of Division Name of Works Projects Remarks
Km & Nos.
(Rs. in Cr)
A Four Laning
(ii) L.A/ Preconstruction
22(99) Gaya Km 0 to Km 13 13 120.00
139(98) Aurangabad Km18 to Km 154 136 1000.00
227(104) MoRTH Km 0 to Km 103 103 700.00
227A MoRTH Km 100 to Km 142 42 350.00
133E Bhagalpur 4-laning of Dhaka more- Baljhor 31 300.00
Total 325 2470.00
B Bye Passes/ Realignment
(ii) LA & Utility Shifting/
Preconstruction
727(28B) Motihari VTR Realignment 20.00 300.00
33(110) Gaya Jehanabad Bypass 7.00 105.00
131(106) Madhepura Singheshwar bypass 5.00 75.00
139(98) Aurangabad Arwal Bypass 11.00 165.00
333 Lakhisarai Gangata Realignment 50.00 750.00
322 Jaynagar DarbhangaWestern Bypass 11.00 165.00
527E Jaynagar Spur to Baheri 7.00 50.00
120 Gaya Spur to Balia 15.00 110.00
Total 126.00 1720.00
Contd......

Approx. Cost of
Length in
Category NH. No. Name of Division Name of Works Projects Remarks
Km & Nos.
(Rs. in Cr)
C Missing Link / New NHs
(ii) L.A/ Preconstruction
727B Chhapra Km 0 to 28 28.00 150.00
122A Sitamarhi Km 0 to 32 32.00 150.00
322 Jaynagar Samastipur to Darbhanga 31.00 110.00
Total 91.00 410.00
D W&S to 2-lane with paved
shoulder
(ii) L.A/ Preconstruction
119(2C) Gaya Km 41 to Km 92 52.00 585.00
Total 52.00 585.00
F Major Bridge
(ii) L.A/ Preconstruction
120(82) Biharsarif 2 Elevated Corridor of Rajgir 5.00 50.00
Total 5.00 50.00

G. Total 599 5235


ANNUAL PLAN FOR CONSTRUCTION WORKS
Approx. Cost of
Length in
Category NH. No. Name of Division Name of Works Projects Remarks
Km & Nos.
(Rs. in Cr)
A Four Laning
(iii) Construction
4-laning of Darbhanga - Jaynagar km 16 to 54
527B(105) Jaynagar (Pkg-II) 38.00 380.00
133E Bhagalpur 4-laning of Dhaka more- Baljhor 31.00 550.00
131B Bhagalpur Approaches of Vikramshila Setu 13.00 250.00

Total 82.00 1180.00


B Bye Passes/ Realignment
(iii) Construction
322 Jaynagar Darbhanga Bypass 11.00 375.00
120 Gaya Dumraon Bypass 5.00 150.00
322 Jaynagar Samastipur Bypass 9.00 300.00
Total 25.00 825.00
C Missing Link / New NHs
(iii) Construction
333A Biharsarif-2 Km 0 to Km 72 25.00 200.00
333A Lakhisarai Km 72 to Km 134 20.00 160.00
333A Bhagalpur Km 134 to Km 178 25.00 200.00
120 Gaya Approaches of Nasariganj Bridge 12.00 100.00
322 Jaynagar Samastipur to Darbhanga 31.00 300.00

Total 113.00 960.00


Contd......

Approx. Cost of
Length in
Category NH. No. Name of Division Name of Works Projects Remarks
Km & Nos.
(Rs. in Cr)
D W&S to 2-lane with
paved shoulder
(iii) Construction
31(81) Purnia Km 30(Katihar)to Km 55(Labha) 25.00 100.00
333A Bhagalpur Km179(Dhaka More) to Km198(Panjwara) 20.00 80.00
322(103) Gulzarbagh Km 0 to Km 58 5.00 100.00
122B Gulzarbagh Km 0 to 29.73 29.73 175.00
One time improvement including widening to
527E Jaynagar two lane with paved shoulder from Hajma 4 25
chowk to Ramnagar
Total 83.73 480.00

E (i) Strengthening /
Raising
139W Motihari Areraj- Betiah 54 75
727B Chhapra Km 0(Mishrauli) to 29(Bhengari) 29 45

Total 83.00 120.00


Contd......
Approx. Cost of
Length in
Category NH. No. Name of Division Name of Works Projects Remarks
Km & Nos.
(Rs. in Cr)
F Major Bridge
(iii) Construction
139(98) Gulzarbagh 4/6 L Elevated Corridor in Anisabad-AIIMS stretch 10.00 1000.00
120 (82) Biharsarif 2 ROB @ km 43.961 1.00 145.00
120 (82) Biharsarif 2 ROB @ km 48.596 1.00 67.00
ROB @ km 45 in Jehanabad on left out portion of NH-
22 (83) Gaya 1.00 70.00
83
227(104) Jaynagar Kamla Bridge 2.00 400.00
333A Lakhisarai Nariyana 1.00 100.00
333A Lakhisarai Mangobandar 1.00 100.00

120 Gaya 4-lane ROB @ Km 202 (Bikramganj) (L.C. No. 46B/T) 1.00 90.00

33(110) Gaya ROB @ Jehanabad 2.00 250.00


727(28B) Motihari ROB @ Km 97 1.00 80.00
139W MoRTH 6-lane Bridge parallel to J.P. Setu 6.00 3100.00
727AA BRPNNL Gandak Bridge 11.00 4300.00
33(80) Bhagalpur ROB @ Km 72 (Safiyasarai) 1.00 75.00
33(80) Bhagalpur ROB @ Km 181 (Shivnarayanpur) 1.00 90.00
33(80) Bhagalpur ROB @ Km 189 (Mirzachowki) 1.00 100.00
Total 41.00 9967.00
G Minor Bridge
(iii) Construction
131 Madhepura Bridge over Kataiya Hydel tail race & Canal 1 75.00
Total 1.00 75.00
Contd......
Approx. Cost of
Name of Length in
Category NH. No. Name of Works Projects Remarks
Division Km & Nos.
(Rs. in Cr)
H STMC/PBMC :-
131A Purnia Km 1.90 to Km 29.12(Amdabad-Manihari) 27.22 36.00
327E Purnia Km 93.00 to Km 112(Araria -Gitwas) 19.00 32.52
133 Bhagalpur Km 0 to Km 10.96(Pirpanti-Barharwa) 10.96 24.00
333 Lakhisarai Km 61.0 to 75.25(Katauria-Gidhaur) 14.25 29.52
33(80) Lakhisarai Km 0.00 to Km 1.43(Mokama) 1.43 9.18
327E Madhepura Km 154-Km 166(Tamkulha-Jagur) 12 11.42
139(98) Km 62.00 to Km 127.45&Km 130.10 to Km
Aurangabad 89.98 165.93
154.625(Mahabalipur-Aurangabad-Hariharganj)
727A Km 0 to km 4.50
Chhapra 4.50 2.00
(Mairwa – UP Border)
Km 41 to km 92
119(2C) Gaya 52.00 26.00
(Akabarpur - Jardag - UP Border)
319A Km 45 to km 66(p)
Aurangabad 21.00 10.50
(Chausa – Buxar)
527E Km 0 to km 46
Jainagar 46.00 30.74
(Rosera-Shivajinagar-Baheri-Darbhanga)
Km 0 to km 36
227F Motihari 36.00 18.00
(Chakia - Bairganiya)
Total 334.34 395.81