Professional Documents
Culture Documents
Risk MNGMNT Lecture 3+4
Risk MNGMNT Lecture 3+4
Management
Lecture 03
Work Breakdown Structure (WBS)
The total of the work at the lowest levels should roll up to the higher
levels so that nothing is left out (what all is necessary) and no extra
work is performed (only what is necessary), A.K.A. 100% rule.
Cost estimates for the various project activities, along with any contingency
reserves for these activities, are aggregated into associated work package costs.
Project Risk
Management
Lecture 03
Elements of Contract Baseline
Total Contract Price is the total negotiated contract cost plus profit/fee.
Total Contract Cost
Total Contract Cost is the total negotiated contract cost without profit/fee.
Profit/Fee
The Contract Budget Base (CBB) represents the total budget for all authorized
contractual work, minus Profit/Fee. The CBB can only be modified when duly
authorized changes to the contract are received. CBB is always calculated as follows:
Current Estimated cost of additional
negotiated
contract cost
+ authorized un-priced work = CBB
(yet to be negotiated)
Performance Measurement Baseline (PMB)
The Performance Measurement Baseline (PMB) is the time-phased budget plan against which
contract performance is measured. It includes all allocated or Distributed Budgets plus the
Undistributed Budget. PMB does not include Management Reserve.
PMB = Sum of Control Accounts
PMB = Distributed Budgets + Undistributed
Budgets PMB = Contract Base Budget –
Management Reserve
Management Reserve
Once the CBB is established, the Program Manager establishes a Management Reserve (MR)
prior to distributing budgets to the performing organizations. The purpose of MR is to have a
budget for the Program Manager to allocate for unforeseen problems.
MR is not part of the Performance Measurement Baseline because it is held at the program level
only. Transactions into and out of MR are approved by the Program Manager.
Distributed Budgets
Distributed Budgets reflect the contractually authorized efforts allocated to the WBS elements.
Distributed Budgets include budgets assigned to control accounts during baseline establishment as
well as work packages and planning packages.
Distributed Budgets = Budgets assigned to Control Accounts
Undistributed Budgets
Undistributed budget (UB) applies to contractually authorized efforts not yet allocated to WBS elements.
Undistributed budget is an element of the Performance Measurement Baseline, but it is not time-phased.
Many organizations keep contingency reserve under this head, but it largely depends on the practices of those
organization the way they design their contingency reserves. Lump Sum Contingency reserve is placed under
undistributed budget. Whereas, risk events based contingency can be argued as distributed or undistributed
budget. Undistributed budgets are controlled by the Project Manager.