Scheduling
‘Time is nature’s way of stopping everything
happening at once’
Having
worked out a method of doing the project
identified the tasks to be carried
assessed the time needed to do each task need to
allocate dates/times for the start and end of each
activity
2
Activity networks
These help us to:
Assess the feasibility of the planned project
completion date
Identify when resources will need to be
deployed to activities
Calculate when costs will be incurred
3
Objectives of Activity Planning
Feasibility Assessment
Resource Allocation
Detailed Costing
Motivation
Co-ordination
Identifying activities
Work-based: draw-up a Work Breakdown
Structure listing the work items needed
Product-based approach
list the deliverable and intermediate products of
project – product breakdown structure (PBS)
Identify the order in which products have to be
created
work out the activities needed to create the
products
5
Hybrid approach
A Hardware selection 6
B Software design 4
C Install hardware 3 A
D Code and test software 4 B
E File take-on 3 B
F Write user manuals 10
G User training 3 E,F
H Install and test system 2 C,D
Precedence network
A 6 wks C 3 wks
Hardware Install
selection hardware
By convention, dates indicate the end of a period. The project is shown as starting at the end of week 0 (or the beginning of week 1)
A 6 wks C 3 wks
0 Hardware 6 6 Install 9
selection hardware
A 6 wks C 3 wks
0 Hardware 6 6 Install 9
2 selection 8 8 hardware 11
FLOAT
ES LF
activity
Latest start
Float = (ES – LS) or (EF – LF) or (LF – ES – Duration)
A 6 wks C 3 wks
0 Hardware 6 6 Install 9
2 selection 8 8 hardware 11
2 wks 2 wks
0 Hardware 6 6 Install 9
2 selection 8 8 hardware 11 D can be a further 2wk late .
It affects H but not the project
2 wks 2 wks
end date = Interfering float
A 6 wks C 3 wks
0 Hardware 6 6 Install 9
2 selection 8 8 hardware 11
8 wks 2 wks 5 wks 2 wks
A 6 wks C 3 wks
0 Hardware 6 6 Install 9
2 selection 8 8 hardware 11
8 wks 2 wks 5 wks 2 wks