Professional Documents
Culture Documents
Ch.4 Specifications and Market Survey
Ch.4 Specifications and Market Survey
Ch.4 Specifications and Market Survey
• Thus the drawing with the specification “will completely define the
structure.” The “Specification” is furnished separately along with
drawing and is an essential part of all engineering contracts.
Necessity/Object of Specifications
The cost of an unit quantity of work is governed by its specification.
Specification is an essential contract document and is required for Arbitration or court
cases.
The necessity of specification is to verity and check the strength of materials for a
work involved in a project.
Specification is necessary to specify the equipment's, tools and plants to be engaged
for a work and thus enable to procure them beforehand.
A work is carried out according to its specification and the contractor is paid for the
same, Any change in specification changes the tendered rate.
Necessity /Object of Specifications
This also specifies the workmanship and the method of doing the work. Thus specification
of work serves as a guide to the supervising staff of the contractor as well as to the owner
to execute the work to their satisfaction.
As the rate of work is based on specification a contractor can calculate the rates of various
items of works in a tender with his procurement rates of materials and labour. Thus
tender paper without specifications of works is baseless, incomplete and invalid.
Specifications of work are required to describe the quality and quantity of different
materials required for a construction work and is one of the essential contract
documents. Thus a contractor can make a programme to procure the materials required
for a project and the owner can check the quality of materials conforming to the
specification avoiding dispute with contractor.
Importance of specifications :
1. Sometimes, it is not possible to furnish the information on the drawings,
regarding the quality of materials to be used and the quality of workmanship to
be achieved during construction, due to shortage of space. Specifications provide
such useful data in a separate document.
5. The specifications of items are required by the contractor to fill the rates of items in the
tender document.
Use of specifications :
To describe the quality of different materials required for construction work.
It enables the department, engineers, architect and contractor to define, procure and check
the material’s quality as per specifications.
To specify the quality of workmanship and method of doing the same.
Specifications are required to clarify the drawings.
Specifications are helpful to the contractor in filling the
rates of various items in the tender.
Use of specifications :
Specifications of a work serves as a guide to the supervising staff of the
owner as well as the contractor to execute the work to their satisfaction.
Specifications are necessary to verify and check the strength of
materials for a work.
Specification is an essential contract document and is required for
arbitration (dispute between the contractor and owner) and court cases.
Specification is necessary to specify the equipments, tools and plants to
be engaged for a work and thus enables to procure then before hand.
Type of specifications :
The specifications are broadly into two categories :
◦ First Class
◦ Second Class
◦ Third Class
◦ Fourth Class
General Specifications
(Foundation and Plinth)
Workmanship:
Complete description of workmanship, the method of mixing to the proportion, the method of laying,
preparation of base or surface, compaction, finishing and curing etc. specifically applicable to the item
of work shall be clearly stated in different clauses.
How to write specification?
Tools and plants (T.&P.):
The tools and plants to be engaged to carry out a work shall be described. The
method of operation and by whom to be supplied shall be stated.
of newwork:
The method of protection of new works against damage or the method of curing if
required, the test of completed work if necessary shall be described in
separate clauses.
How to write specification?
Expression:
While writing a specification Endeavour shall be made to express the requirements of the specification
clearly and in concise from avoiding repetition and unusual works. The style of tense shall remain
same throughout. The sentences shall be short, simple and concise. As the specifications are the legal
documents, terms such as suitable, proper used and works having more than one meaning shall be
avoided.
The clauses shall be arranged in the order in which work shall be carried out.
Relation with working drawing
with Specification writing…
SPECIFICATIONS OF
EXCAVATION AND FOUNDATION
EXCAVATIO
N
• EXCAVATION is the preliminary activity of the construction
project. It starts from the pits for the building
foundations and continues up to the handing over of the
project.
• For small buildings, excavation is carried out manually by
means of pick axes, crow bars. spades etc. In case of
large buildings and deep excavation, mechanical earth
cutting equipment can be used like Hydraulic excavator,
tractor / trucks.
• Deep excavation or the construction of basements
includes the construction of retaining walls, excavation,
the installation of struts, the construction of foundations
and floor slabs,etc.
DEPTH OF EXCAVATION
Preservation of Property,
Site clearance Antiques and Relics
Setting out
The Contractor shall layout, and
Before excavation, the area coming under cutting Excavating operation shall be
and filling shall be cleared of shrubs, vegetation, construct one or more
trees and saplings of girth up to 30cm measured at conducted in such a manner that permanent bench marks in some
a height of one metre above ground level shall be all properties, facilities, utilities central place before the start
removed up to a distance of 50 metres outside the and improvements on or near
the project site, which are to of the work, from which all
periphery of the area under clearance. The trees
of girth above 30 cm shall be cut only after remain in place, are not important levels for the
permission of the Engineer-in-Charge. damaged. excavations will be set.
Existing structures and services such as old Any finds of archaeological
buildings, culverts, fencing, water supply pipe interest such as relics of
Blasting
lines, sewers, power cables, etc. within or Where hard rock is met with
adjacent to the area if required to be antiquity, coins, fossils or other
diverted/removed, articles of value shall be and blasting operations are
delivered to the Engineer-in- considered necessary, the
In case of archaeological monuments within or Charge and shall be the property contractor shall obtain the
adjacent to the area, the contractor shall provide of the Government.
necessary fencing around such monuments as per approval of the Engineer-in-
the directions of the Engineer-in-Charge Charge
EXCAVATION METHODS
Set out first Bore for Insert tendons Preload Proceed to Build the
Inject grouts anchors and second stage foundation of
excavation stage anchors into the bores
lock them of excavation building
Excavation process
• All excavation operations manually or by mechanical means shall include excavation and ‘getting out’ the excavated materials.
In case of excavation for trenches, basements, water tanks etc. ‘getting out’ shall include throwing the excavated materials at
a distance of at least one metre or half the depth of excavation, whichever is more, clear off the edge of excavation.
• During the excavation the natural drainage of the area shall be maintained.
• In firm soils, the sides of the trenches shall be kept vertical upto a depth of 2 metres from the bottom. For greater depths, the
excavation profiles shall be widened by allowing steps of 50 cms on either side after every 2 metres from the bottom.
Alternatively, the excavation can be done so as to give slope of 1:4 (1 horizontal : 4 vertical).
• In case of excavation for foundation in trenches or over areas, the bed of excavation shall be to the correct level or slope and
consolidated by watering and ramming.
• Where hard rock is met with and blasting operations are considered necessary, the contractor shall obtain the approval of the
Engineer-in-Charge. Where blasting operations are prohibited or are not practicable, excavation in hard rock shall be done by
chiseling.
• In ordinary rock excavation shall be carried out by crowbars, pick axes or pneumatic drills and blasting operation shall not be
generally adopted.
MEASUREMENTS
Why it is used
• Base soil has low bearing capacity or
• Column load are so large that more than
50% of the area covered by
conventional spread footing.
• Resist unequal settlement due to
earthquake.
• Quickness of construction work.
PROCESS
SUITABILITY :
This type of foundation is suitable under the following situations ;
When the soil is very soft and solid base is not available at a reasonable
depth to keep the bearing power within safe limits.
When the grillage and raft foundation are very expansive.
When the building is very high carrying heavy concentrated loads.
When it is necessary to construct a building along the sea shore or river
bed.
CLASSIFICATIO
N
PRE-CAST PILE
Pre means before & cast means made. So precast pile refers to a
pile
that has made before it is being used.
PROCESS
• Steel form is used for the precast pile
manufacture.
• Before pore the concrete in to the
form, mobile or other kind of oil have
been used.
• cement, sand ,aggregate ratio is
normally 1:2:4 in pre cast pile.
• But to make the foundation stronger mix
ratio is used 1:1.5:3
• When the concrete pore in the steel form
CURING
Pictures of Processing Precast pile
• After 3 days, pile have been covering
by the sheet.
• After 3 days of casting, steel form
would be removed.
• Then the piles would be prepare for 4
weeks curing.
• Then the piles are transported to the
site for driving
Market survey
Market survey is the survey research and analysis of the market for a
particular product/service which includes the investigation into customer
inclinations.
Market surveys collect data about a target market such as pricing trends,
customer requirements, competitor analysis, and other such details.