Professional Documents
Culture Documents
Scheduling v2
Scheduling v2
Learning Objectives
Planning your schedule is the last step before actually completing the
tasks on the schedule.
Scheduling
Business also make schedules to show how labor, material and
equipment should be used.
An automobile maintenance and repair facility
The start and finish time for each activitiy
Two kinds of Gantt charts are the load chart and the progress chart.
The finite loading schedule shows how a company plans to use available capacity
center if the work center uses a set number of production hours each day.
For example, if the work center can build 50 wire assemblies per hour and the company
needs 1000 wire assemblies, the job will take 20 hours of capacity at that work center.
Scheduling Work - Work Loading
In a service organization, a doctor’s office is a good example. To spend
10 minutes with each patient, the doctor can have 6 patients scheduled
per hour.
Finite vs. Infinite Loading
Companies benefit from both infinite and finite loading. Infinite
loading identifies resource bottlenecks for a proposed schedule
so that planners can find solutions proactively, such as changing
the schedule and increasing the resource capacity.
Finite loading develops the operational schedule that uses the
available capacity.
Finite and infinite loading assign work to specific work centers
based on a proposed schedule.
Both techniques use either a schedule (infinite loading) or a
prioritized list of jobs to be done (finite loading).
Other Scheduling Techniques
Forward Scheduling – starts processing immediately when a job is received
The disadvantage to finishing a job early is that it causes an inventory buildup if items are not delivered before the
due date.
Backward Scheduling – begin scheduling the job’s last activity so that the job is finished on due date
Backward scheduling shows you how late the job can be started and still be finished on time.
Forward and Backward
Scheduling
When you are using backward scheduling and forward scheduling
together, a difference between the start time of the first activity indicates
slack in the schedule.
Slack means that you can start a job immediately but you do not have to
do so. You can start it any time up to the start time in your backward
schedule and still meet the due date.
Monitoring Work Flow
Input/Output Control
Input/output control is a capacity-control technique used to monitor
workflow at individual work centers. Input/output control monitors the
planned inputs and outputs at a work center against the actual inputs and
outputs.
Planned inputs are based on the operational schedule, whereas planned
Actual input is compared with planned input to ensure that enough work
enters the measured work center. A work center cannot process items that
have not yet arrived.
Actual output is used to identify possible problems in the work center,
Operation sequencing sets projected start and finish times and expected
queues. Techniques are available to do short-term planning of jobs
based on available capacity & priorities
Priorities Rules (commonsense rules)
Priority rules are (simple heuristics used to select the order in which jobs
will be processed) typically classified as local or global:
A local priority rule sets priority based only on the jobs waiting at that
individual work center. For example, the highest priority might be given
to the job that arrives first or the job that can be done the fastest.
lowest first)
Slack per remaining Operations (S/RO)
Slack /(number of remaining operations) (Schedule
lowest first)
How to Use Priority Rules
Decide which priority rule to use
Using priority rule determine which job has highest priority then
second, third and so on
Using SPT and EDD at Jill’s Machine Shop
Using SPT(shortest processing time) and EDD (earliest due date) as a
priority rule, determine the sequence for the following jobs waiting at
Work Center 102 at Jill’s Machine Shop. The job information follows.
Example Using SPT, EDD
Example Using SPT and EDD at Jill's Machine Shop-Work Center 101
Job flow time = time of completion - time job was first available for
processing
Completion
Job Date Due Date Lateness Tardiness
A 10 15 -5 0
B 13 15 -2 0
C 17 10 7 7
D 20 20 0 0
Average 0 1.75
Sequencing Jobs through Two Work Centers
At times, all jobs must be processed through the same two work centers
sequentially.
For example, when you do laundry, clothes go through the washer before
the dryer. Different kinds of clothing need different wash cycles and
different drying times, but the sequence is the same.
To shorten the time it takes to do your laundry, you can use Johnson’s
rule.
Johnson’s rule is a scheduling technique for developing a sequence
when jobs are processed through two successive operations. The operations
can be at machine centers, departments, or different geographical
locations.
Johnson’s Rule – a technique for minimizing makespan in a two-stage,
unidirectional process
Sequencing Jobs through Two Work Centers –Johnson’s
Rule
Step 1 – List the jobs and the processing time for each activity
Step 3 – Repeat step 2 until you have put all activities for the job
in the schedule
Vicki’s Office Cleaners
Vicki’s Office Cleaners does the annual major cleaning of university
buildings. The job requires mopping and waxing the floors in 5 buildings at
Mideast University. Each building must have the floors mopped and stripped
(first activity), and then waxed and buffed (second activity).Vicki wants to
minimize the time it takes her crews to finish cleaning the five buildings.
Use Johnson’s method to develop the sequence Vicki should follow.
Job Sequence
Johnson’s Rule Example:
At the end of each month, a research and development team writes status reports for the projects at work. The team
leaders, Andrew and Julie, submit them to the R&D director on the first Monday of each month. Unfortunately, they forgot
to check their calendar one month until late Friday evening. To their surprise, they discovered that the month ended on
Sunday and the reports were due the following Monday morning. As they had not started writing them, they decided to
come to work early Saturday morning, so they could finish the reports before Monday morning. They split the work as
follows: Andrew writes and edits the reports while Julie collates data and draws all the necessary graphs. Assume that Julie
starts her work on a report as soon as Andrew is finished with it and that Andrew works continuously. Times for the
reports (in hours) are as follows:
a)What is the order of the tasks using Johnson's rule?
b)How many hours will it take them to finish all the reports?
Julie: