Professional Documents
Culture Documents
PM - Week N 06 - Cost Management 2022
PM - Week N 06 - Cost Management 2022
Unit 2 : PMBOK
“Cost Management”
Week : 06
2
Prepared by Prof Augusto Choy
UNIT’S LEARNING OUTCOME
•To recognize and understand the structure of the course in
order to develop and learn PM successfully.
•To review and analyze the main concepts related to Project
Management and how to apply them in their profesional
life.
3
Prepared by Prof Augusto Choy
Unit 2 : PROJECT MANAGEMENT BODY OF KNOWLEDGE
COST MANAGEMENT
◦ Summary
4
Prepared by Prof Augusto Choy
Topics – Cost Management
1. Cost Management
1. Project Cost
2. Cost Management Processes
3. Budget
5
Prepared by Prof Augusto Choy
Cost Management
Type of Costs
Direct and Indirect.
Fixed and Variable.
ABC Costing
7
Reviewing Concepts – Cost Management
Cost Management Processes
Nª Process Process
Group
01 Plan Cost Management
02 Estimate Costs Planning
03 Determine Budget
Monitoring
04 Control Costs &
Controlling
8
Cost Management Processes
Plan Cost Management
Cost Management Plan
10
Plan Cost Management
11
Cost – Estimate Costs
• Process of developing an approximation
of the monetary resources needed to
complete project activities.
• Cost Estimates are generally expressed in units of some
currency (dollares, euro, nuevos soles, etc.).
• Estimate Costs process involves:
Costs of quality and risk efforts.
Cost of Project Manager’s time
Cost of project management activities.
Costs directly associated with the project, and others
12
Cost – Estimate Costs
• Accuracy of Estimates
• Estimates made in the early part of the project will be less
accurate than those made later in project.
• Estimates must be in a range and be refined as the project
progress.
13
Cost – Estimate Costs
• What data do we need before estimating Cost?
The Scope Baseline.
Project Schedule.
Human Resource Plan.
Risk Register.
Project Management Cost.
Organizational Process Assets (policies, templates,
historical information and Lessons Learned).
Enterprise Environmental Factors (market conditions,
published commercial information).
14
Cost – Estimate Costs
• Techniques
Analogous Estimating.
Parametric Estimating.
Three Points Estimating.
Bottom-Up Estimating
15
Cost – Estimate Costs
• Advantages and Disadvantages – Analogous Estimating
Advantages Disadvantages
•Quick •Less accurate
•Activities need not be identified •Estimates are prepared with a limited
amount of detailed information and
understanding of the project.
16
Cost – Estimate Costs
Advantages and Disadvantages – Bottom Up
Estimating
Advantages Disadvantages
•More accurate •Takes time and expense to do this
form of estimating.
•Based on a detailed analysis of the •Requires that the project be defined
project. and well understood before work
begins.
•Provides a basis for monitoring and •Requires time to break the project
controlling, performance down into smaller pieces (Scope -
measurement and management. WBS)
•Gains buy-in from the team if they
have defined the estimates (Time –
Estimate Activity Duration)
17
Cost – Estimate Costs
18
Cost – Determine
Budget
• Process of aggregating the estimated costs of
individual activities or work package to
establish an authorized Cost Baseline
• Cost Baseline includes all authorized budgets,
but excludes management reserves.
• Project budgets constitute the fund
authorization Project execution. Project cost
performance will be measured against the
authorized budget.
19
Cost – Determine Budget
• Cost Aggregation: To create a Budget, activity costs,
including costs for risk contingencies, are rolled up to work
package costs. Work Package costs are then rolled up to
Control Accounts Costs and finally into Project Total. This is
called Cost Aggregation
• Funding Limit Reconciliation: The expenditure of
funds should be reconciled with any funding limits on the
commitment of funds for the project. A variance between
the funding limits and the planned expenditures will
sometimes need the rescheduling of work to level out the
rate of expenditure.
20
Cost – Determine Budget
8. Cost Budget $ 1755
7. Management $ 80
Reserves
Cost Aggregation
6. Cost Baseline $ 1675
5. Contingency
Reserves $ 120
4. Project
Estimates $ 1475
3. Control Account CA 1 CA 2
Estimates $ 675 $ 800
2. Work Package
Estimates
WP 1
$ 175
WP 2
$ 500
WP 3
$ 800 …
1. Activity
Estimates
A1
$ 25
A2
$ 25
A3
$ 50
A4
$ 75
A1
$ 20
A2
$ 45 …
21
Cost – Determine Budget
Cost Baseline, Expenditures (Cash Flow)
and Funding Requirements
22
Cost – Determine Budget
The ‘S’ Curve
• Curve which
represents the
accumulated costs
(by period of time)
of the Project.
23
Cost – Determine Budget
24
Cost – Control Costs
• Process of monitoring the status of the project to update the
project budget and managing changes to the Cost Baseline.
25
Cost – Control Costs
Earned Value Management (EVM)
27
Cost – Control Costs
Terms - Earned Value Management (EVM)
Acronym Term Interpretation
PV Planned Value As of today, what is the estimated value of
work planned to be done?.
EV Earned Value As of today, what is the estimated value of
work actually accomplished?.
AC Actual Cost As of today, what is the actual cost for the
work accomplished?.
BAC Budget at Completion How much did we BUDGET for the TOTAL
(the budget) Project effort?.
EAC Estimate at Completion What de we currently expect the TOTAL
project to cost (a forecast) ?.
ETC Estimate to Complete From this point on, how much MORE do we
expect it to cost to finish the project
(forecast) ?.
28
Cost – Control Costs
Terms – EAC and ETC
Today
BAC
Original PV
Spending
Plan
Actual AC
Spending
Plan
EAC
ETC
ForecastS
pending
Plan
29
Cost – Control Costs
Earned Value Graph
30
Cost – Control Costs
Formulas and Interpretations
Name Formula Interpretation
Cost •< 0, Over Budget (NOK)
Variance EV - AC •>= 0, Under Budget (OK)
(CV)
Schedule •< 0, Delayed (NOK)
Variance EV - PV •>= 0, Ahead of schedule(OK)
(SV)
Cost •We are getting $ CPI worth of
Performance work
Index (CPI) EV / AC of every $ 1.00 spent.
•>= 1 OK; < 1 NOK
Schedule •We are progressing at SPI % of
31
Performance the
Cost – Control Costs
Forecasting
Name Formula Interpretation
•It is used when the original
AC + ETC estimate was fundamentally
flawed.
•It is used if no variances from
BAC have occurred or you will
EAC BAC / CPI continue with the same rate of
Estimate spending.
at
Completio •It is used when current variances
AC + (BAC – are thought to be atypical of the
n EV) future.
AC + •It is used when current variances
32
are though to be typical of the
Cost – Control Costs
Forecasting
Name Formula Interpretation
33
Cost – Control Costs
TCPI – To Complete Performance Index
TCPI is the
calculated projection
of cost performance
that must be achieved
on the remaining
work to meet a
specific management
goal, such as the BAC
or the EAC.
TCPI = (BAC – EV) / Or (BAC – EV) /
(EAC - AC)
(BAC - AC) 34
Cost – Control Costs
Let’s solve some exercises about Earned
Value
35
Cost – Control Costs
36
Earned Schedule
37
Earned Schedule
BCWS = PV
38
Earned Schedule
Let’s see this example
Period (week) EV PV
T=8 1800
T+1 = 9 2000
T+2 = 10 2300 2100
>= 1; OK
< 1; NOK
40
Earned Schedule
Final Duration Forecast
(Independent Estimation at Completion)
41
Cost Management
Summary
42
Cost Management
Summary
There are two kinds of reserves:
Contingency and Manage Reserves.
Cost Baseline includes Contingency
Reserves, and Cost Budget includes Cost
Baseline and Manage Reserve.
Earned Value Management integrates Time,
Cost and Scope (work done) and its
variables are: PV, EV and AC.
43
Cost Management
Summary
In Earned Schedule is important previous data
in order to perform linear interpolation
method.
Earned Schedule consider its own SPI(t) and
IEAC(t)
44
References
45
Prepared by Prof Augusto Choy
Thank-you