Professional Documents
Culture Documents
Failure of CT and Remedial Strategies
Failure of CT and Remedial Strategies
1
GSFC BACKGROUND
2
IMPORTANCE OF COOLING TOWER
3
HISTORY OF COOLING TOWER FAILURES
industries but total collapse of cooling tower was unheard of upto 2001.
• This is the time to analyse the problem and take corrective actions.
4
LIST OF COOLING TOWER COLLAPSES
11 ISPAT INDUSTRIES
5
COOLING TOWER COLLAPSE EVENT AT GSFC
6
DECISIONS TAKEN
• The remaining intact portion of cooling tower along with fan assembly were
inspected for operability. Additional strengthening where ever required was
provided
• To safeguard the remaining intact tower, the return header running through
top of the cooling tower deck was shifted to ground levels to increase the
reliability of one side operation. CW feed to individual cells was given from
bottom header with help of riser pipes
• The header for collapsed side was provided with isolation valve
• Southern part of cooling tower was covered with tarpaulin sheets to avoid
short circuiting of air flow and to obtain required cooling for partial operations
of CT. Approach of CW to the tune of 5 O C could be achieved
• The fabrication of bottom header with riser pipes could be completed within
13 days period. CT shutdown was taken for provision of isolation valves and
on 16th day, CT part operation / Ammonia productions could be established
• Erection of cells in phased manner and increase in plant loads continued
• Complete CT operations could be resumed after two and half months period
8
CHRONOLOGICAL ACTIVITES FOR RE-ERECTION
22
CHRONOLOGICAL ACTIVITES FOR RE-ERECTION
23
RE-ERECTION AT A GLANCE
24
SIMILARITIES OBSERVED IN FAILURES
25
PREVENTIVE MAINTENANCE MEASURES
26
THANK YOU
27