Professional Documents
Culture Documents
Presentation Model For Trading Facilities
Presentation Model For Trading Facilities
Introduction
Trading Facility phase-1 comprises the following:
12 October 2019
OVERAL LAY OUT OF TRADING FACILITIES
PRODUCT
TERMINAL
GANTRY AREA
LVS STATION
7 NO’S OF PIPILINES
24’’ – 5 NO’S(INCLUDING
REJECT WATER LINE)
48’’- 2 NO’S (CRUDE LINES)
12 October 2019
TRADING FACILITIES AERIAL SNAPSHOT
12 October 2019
AERIAL VIEW OF PRODUCT TANKS
12 October 2019
DYKE WALL WORKS
12 October 2019
`TANK FARM & TRADING FACILITY (P-1)
CIVIL WORKS
The following activities are covered under Product tank farm and trading facility
scope:-
1. Roads
2. Drains
3. Sleepers
4. Dyke wall
5. Pump station
6. UG pits and sump
7. Dyke wall & Fire wall
8. Sandtrap,Valvepit, inside dyke drain, pavement, Cable trenches
9. Buildings
10. Manholes for UG piping
11. Culverts- PWC and Box culvert
12. Sanitary Sewer Sump-04
12 October 2019
Roads for Trading Facilities and Associated
Pavement
7
ROADS: TRADING FACILITY & PRODUCT TANK AREA
Total
Total Length (M) Completed (M) Balance Qty. (M) % Completion
Numbers of
road
8
Completion Outlook: Road Works
COMPLETED
ITEM SCOPE LENGTH (M) BALANCE LENGTH (M)
LENGTH (M)
9
AREAS OF CONCERN
Area of concern:
• JBN to be expedited for taking parallel work fronts as 02 nos roads are yet to be
started.
• PWC works by SINOMA needs to be expedited (06 nos balance out of total 41 nos)
• Drain works shall be expedited to increase the performance of road during
ongoing monsoon
10
PRODUCT TANK DRAINS-25.15 KM
Summary of Drain works
• Agency 1- M/s Demark (Tender no. OT-0025) for Product Tank area drain b/w St-11 to 53
11
Trading facility Culverts
TOTAL % Completion
DESCRIPTION UoM COMPLETED BALANCE
SCOPE
12
Product Tank Fire Water Sleepers
• Firewater sleepers
1. Balance Roads & Drains are to be expedited which are still pending for completion.
13
PROCESS PIPING SLEEPERS
Process Dec-19
Scope (No) Completed (Nos) Balance (No) Nov-19
Sleeper
14
Trading Facility Misc. items
DESCRIPTION` UoM TOTAL SCOPE COMPLETED BALANCE
FLM Nos. 78 30 48
Cu.M
SLOPE PROTECTION(PCC) 3145 0 0
15
TANKFARM / TRADING FACILITY UG PITS
Quantity as
Progress Last Week up
Unit Location Agency Tag No. per drwg. Remarks
to 05.10.2019
(Cu.M)
736 TANK FARM SINOMA 714-VV-1401 135 Completed.
Not started
736 TANK FARM SINOMA 714-VV-1402 150 Sheet pile not available
736 TANK FARM SINOMA 716-VV-1603 150 Sheet pile not available Not started
GANTRY NORTH
736 732-VV-3201 415 Raft Completed Wall in progress.
AREA RIDGE
Adjacent sump pit
GANTRY NORTH
736 732-VV-3202 410 Raft & Wall Completed. & pedestals in
AREA RIDGE progress.
Adjacent sump pit
GANTRY NORTH
736 732-VV-3203 410 Raft & Wall Completed. & pedestals in
AREA RIDGE progress.
GANTRY NORTH
736 732-VV-3204 410 Excavation in progress
AREA RIDGE
GANTRY NORTH
736 732-VV-3205 459 Excavation in progress
AREA RIDGE
16
UG PITS: COMPLETION OUTLOOK
1 714-VV-1401 135 ü
2 714-VV-1402 150 ü
3 714-VV-1403 150 ü
4 716-VV-1603 150 ü
5 732-VV-3201 415 ü
6 732-VV-3202 410 ü
7 732-VV-3203 410 ü
8 732-VV-3204 410 ü
9 732-VV-3205 459 ü
17
Product Tank Farm & Trading Facility
UG MANHOLES:
CASTING ERECTION
TOTAL
DESCRIPTION UOM
SCOPE COMPLETED
BALANCE ERECTION BALANCE
CASTING
MHS Nos 94 94 0 0 94
MHC Nos 46 46 0 25 0
19
SS-19: COMPLETION OUTLOOK
CONTRACTOR: ROCKSEED
21
SRR-11: COMPLETION OUTLOOK
CONTRACTOR: ROCKSEED
23
TANKAGE WORKS
Total : 45 Tanks
12 October 2019
TANKS COMPLETION SUMMARY
Nos 45 30 15 21 09
12 October 2019
SUMMARY OF TANK FABRICATIONS
Compl % Target
Sr.No. Activity Qty Scope Balance
eted Comp Completion
1 Tank Fabrication MT 41707 41246 461 99 Jan-2020
2 Tank Erection MT 41707 32623 9084 78 Dec-2020
3 Blasting & Primer MT 41707 36463 5244 87 Dec-2020
4 Tank Fit-Up & Welding MT 41707 32624 9083 78 Jan-2020
5 Radiography/NDT & PWHT MT 41707 30705 11002 74 Feb-2020
Tank/Structural Final
6 MT 41707 13732 27975 33 April-2020
Painting/Stenciling
7 Foam Pipe Fabrication (CS) ID 36537 8233 28304 23 April-2020
8 Foam Pipe Erection (CS) IM 44525 7178 37347 16 April-2020
9 Foam Pipe Hydrotesting (CS) IM 44525 0 44525 0 April-2020
6 53B DIESEL DAY 3202B CR 326 326 0 322 4 Deflector plate 10t
7 53C DIESEL DAY 3202C CR 326 326 0 322 4 Deflector plate 10t
8 53D DIESEL DAY 3202D CR 326 326 0 322 4 Deflector plate 10t
9 54A JET DAY 3203A IFR 414 414 0 410 4 Deflector plate 10t
10 54B JET DAY 3203B IFR 414 414 0 411 3 Deflector plate 10t
11 54C JET DAY 3203C IFR 414 411 3 411 3 Deflector plate 10t
12 October 2019
FABRICATION STATUS OF PRODUCT TANKS
KEROSENE
12 55A 3204A CR 325 323 2 322 3 Deflector 3 t
DAY
KEROSENE
13 55B 3204B CR 325 322 3 322 3 Deflector 3 t
DAY
SLURRY
14 56A 3205A CR 156 155 1 155 1 Deflector 1 t
DAY
SLURRY
15 56B 3205B CR 156 155 1 155 1 Deflector 1 t
DAY
12 October 2019
FABRICATION STATUS OF PRODUCT TANKS
12 October 2019
FABRICATION STATUS OF PRODUCT TANKS
720-TT-
1 Chemi-tech (T-III) 9 10 43 43 0 Completed
2006
12 October 2019
CONSTRAINTS
12 October 2019
AG-PIPING SUMMARY
% Completion
Area/ Scope Comp. Available
UoM Bal. Qty up to Last
Zone Qty Qty Work Front
Week
12 October 2019
COMPLETION OUTLOOK: AG PIPING
ZONE
Description
UoM
Bal. Qty 19-Oct 19-Nov 19-Dec 20-Jan 20-Feb 20-Mar
of Unit
12 October 2019
PIPING AREA RELEASE STATUS
ZONE D
ZONE E
12 October 2019
AG PIPING AREA RELEASE STATUS
D 140 53 87 37.8%
E 85 13 72 15.26%
12 October 2019
CONSTRAINTS
12 October 2019
UNDER GROUND PIPING SUMMARY
Description of
AREA UoM Scope Qty Completed Qty Balance Qty % Completed
Unit
12 October 2019
UG PIPING DISTRIBUTIONS
12 October 2019
COMPLETION OUTLOOK FOR UG PIPING WORKS
Description of
AREA UoM Bal. Qty 19-Oct 19-Nov 19-Dec Jan-19
Unit
12 October 2019
CONSTRAINTS
1. Balance PPR & uPVC Pipes & fittings for WDK & S Sewer piping.
2. CI Manhole Covers
3. Chequered Plates.
12 October 2019
FIRE WATER PIPING: SUMMARY
12 October 2019
FIRE WATER COMPLETION OUTLOOK
Description of
UoM Bal. Qty 19-Oct 19-Nov 19-Dec 20-Jan Feb-2020
Unit
12 October 2019
FIRE WATER DISTRIBUTIONS
12 October 2019
CONSTRAINTS
1. FIMs fittings (Epoxy coated) for balance UG fire water road crossings not yet
received at site.
2. Fire Water Monitor & Hydrants not yet received at site.
3. Fire Water Hose Reel & Rubber Hose along with Box not yet received at site.
12 October 2019
MECHANICAL EQUIEPMENT: STATIC & ROTARY
SCOPE in
S.No Equipment COMPLETED BALANCE Remarks
Nos.
7 Diesel Generator 1 0 1
8 Weigh Bridge 2 0 2
* 03 Nos. Foundation casting Completed.
12 October 2019
COMPLETION OUTLOOK: UG PITS EQPT.
1 733-PA-CF-101A-C 3 28/10/2019
2 714-PA-1401A-F 6 25/10/2019
3 733-PA-CF-103A-C 3 Completed
4 714-PA-1404A-C 3 Completed
5 714- PA-1410A-B 2 Completed
6 733-PA-CF-105A-C 3 Completed
7 714-PA-1403A-B 2 Completed
8 714-PA-1402A-B 2 Completed
9 716-PA-1607A-C 3 Completed
10 732-PA-3201A-H 8 Completed
48
ERECTION OUTLOOK OF PUMPS
11 732-PA-3204A-C 3 Completed
12 732-PA-3203A-C 3 Completed
13 732-PA-3202A-F 6 Completed
14 732-PA-3205A-C 3 Completed
15 720-PA-2006 1 20/11/2019
16 714-PA-1406 1 10/11/2019
17 714-PA-1408 1 28/11/2019
18 714-PA-1412 1 Completed
19 714-PA-1407 1 14/11/2019
20 716-PA-1610 1 12/11/2019
21 714-PA-1405A-B 2 20/11/2019
22 714-PA-1411A-C 3 20/11/2019
49
GANTRY LOADING ARMS – MSR DATA
EDR AS PER
SI NO MR DESCRIPTION TAG NO QTY FOA VENDOR NAME
MSR
JIANGSU
LOADING ARMS
1 732-LA-001 A/B -10 A/B 20 5037 CHANGLONG 30/11/2018
(ROAD)
TECHNOLOGIES
JIANGSU
LOADING ARMS
2 732-LA-011 - 040 30 5037 CHANGLONG 30/11/2018
(ROAD)
TECHNOLOGIES
JIANGSU
LOADING ARMS
3 732-LA-041 - 057 17 5037 CHANGLONG 30/11/2018
(ROAD)
TECHNOLOGIES
JIANGSU
LOADING ARMS
4 732-LA-058 - 078 21 5037 CHANGLONG 30/11/2018
(ROAD)
TECHNOLOGIES
JIANGSU
LOADING ARMS
5 732-LA-079 - 081 3 5037 CHANGLONG 30/11/2018
(ROAD)
TECHNOLOGIES
JIANGSU
LOADING ARMS
6 732-LA-082 A/B - 086 A/B 10 5037 CHANGLONG 30/11/2018
(ROAD)
TECHNOLOGIES
50
MISC EQUIPMENTS - MSR DATA
Reciprocating
4 732-KA-3201 DOVER INDIA 31/08/2018 31/08/2019
Compressor
12 October 2019
GANTRY STRUCTURAL WORKS COMPLETION
OUTLOOK
GANTRY SCOPE COMPLETED BALANCE 19-Oct 19-Nov
ü
GANTRY1 207.4 202 5.4
12 October 2019
CIVIL WORK AT LVS AND PRODUCT TERMINAL
FDN/PUMS/SKIDS/ CUM
LAUNCHERS 1200 0 1200
12 October 2019
PIPIELINE SCOPE AND STATUS
PRODUCT
TOTAL LINGTH OF LINE COMPLETED BALANCE
S NO. NAME OF THE SIZE
(M) (M) (M)
LINE
12 October 2019
PIPELINE COMPLETION OUTLOOK
PRODUCT
S NO. NAME OF THE SIZE
LINE
(M) OCT'19 Nov'19 Dec'19
12 October 2019
STATION PIPING SCOPE
ID 2100 0 2100
LAND FALL
STATION
IM 6000 0 6000
ID 40000 0 40000
Product Terminal
150000
IM 150000 0
12 October 2019
SUMMARY OF CONTRACTOR SCOPE OF SUPPLY
CONTRACTOR'S SCOPE OF SUPPLY ITEMS STATUS AS ON DATE FOR TRADING FACILITIES BY OMITTI
DRAWINGS/DATA
YET TO BE
TOTAL NO OF SHEET ORDERED BY
SI NO DEPARTMENT ORDERDED REMARKS
ITEMS APPROVED OMITTI
BY OMITTI
STATUS
MTC TO BE
SUBMITTED BY
1 PIPING 45 8 0 45 OMITI FROM
APPROVED
VENDOR
MTC TO BE
SUBMITTED BY
2 MECHANICAL 19 18 3 16 OMITI FROM
APPROVED
VENDOR
MTC TO BE
SUBMITTED BY
3 ELECTRICAL 65 2 0 65 OMITI FROM
APPROVED
VENDOR
MTC TO BE
SUBMITTED BY
4 INSTRUMENTATION 42 0 0 42 OMITI FROM
APPROVED
VENDOR
12 October 2019
CONTRACTOR'S SCOPE OF SUPPLY ITEMS STATUS AS
ON DATE FOR TRADING FACILITIES (M/S OMITTI)
SI TOTAL NO APPROVAL STATUS DRAWINGS,DATA ORDERING STATUS
ITEM NAME
NO OF ITEMS SHEET BY M/S OMITTI
PIPING FITTINGS SMALL BORE MTC TO BE SUBMITTED BY OMITI
1 31
(FOR STATION PIPING) FROM APPROVED VENDOR
INSULATION JOINTS
2 14 Approved
(24'',48'',30,'')
160 ITEMS APPROVED,REST MTC TO
3 VALVES (SMALL BORE) 258
BE SUBMITTED BY M/S OMITTI
4 SCRAPPER TRAPS( 30'' X 24'') 4 Approved
5 QOEC( 30'' X 24'') 4 Approved
JIB CRANE: 2 TON MT PRODUCT NOT YET ORDERD
6 4 Approved
TERMINAL
Pig signaler- on Product Pipeline
7 4 Approved
2"X300#
Pig signaler- on Product Scraper
8 4 Approved
traps2"X300#
Flow tee: (24'x24" 300# UG,
24'x24" 300# AG,48'x24" 150#
9 14 Approved
UG,48'x30" 150# UG,48''x48" 150#
UG)
CASING END SEAL FOR
10 1 Approved RECEIVED AT SITE
COASTAL RDX
11 REJECT WATER COUPLING 192 Approved NOT YET ORDERD
12 WARNING MATE 1 Approved
RECEIVED AT SITE
13 CASING VENT PIPES(4" DIA) 1 Approved
12 October 2019
LIST OF EQUPMENT AT PRODUCT TERMINAL
12 October 2019
CONSTRAINTS
DORC SUPPLY:
1. FIMs pipes, fittings not yet received at site for station piping.
2. LR bends not yet received at site.(Initially it was under Omitti scope)
Areas of Concern:
12 October 2019
ELECTRICAL
61
--THANK YOU--
62