TANK FARM & TRADING FACILITY (P-1)

Introduction
Trading Facility phase-1 comprises the following:

 Civil Works: Sleepers, Manholes, Road & Drains, etc.


 Buildings (CR-4, SFS-4, SS-19,SS-16,SRR-11 MARINE CR).
 Tank-farm,TF-37,40,43,46,50,38,41,44,47,51, 27,52,53,54,55, 56, 59 (comprising of 45
tanks from diameters 12M to 66 M)
 AG & UG piping along with fire fighting system.
 OWS Sump-03, UG pits, equipment, pumps, Sanitary Sump-04.
 Product Loading Gantry consisting of 101 loading arms and associated structural,
piping works
 Product pipe lines (4 no.s – 24”) from LFP to Product terminal including LSVs, metering
skids, pig launcher/receiver and associated equipment
 E&I activities

12 October 2019
OVERAL LAY OUT OF TRADING FACILITIES

TANK FARM AREA

PRODUCT
TERMINAL

GANTRY AREA

4 NO’S 24’’ UNDER


GROUND PRODUCT
PIPELINES (14.8 KM)

LVS STATION
7 NO’S OF PIPILINES
24’’ – 5 NO’S(INCLUDING
REJECT WATER LINE)
48’’- 2 NO’S (CRUDE LINES)
12 October 2019
TRADING FACILITIES AERIAL SNAPSHOT

12 October 2019
AERIAL VIEW OF PRODUCT TANKS

12 October 2019
DYKE WALL WORKS

BLUE : WALL COMPLETED


GREEN: RAFT COMPLETED

12 October 2019
`TANK FARM & TRADING FACILITY (P-1)

CIVIL WORKS
The following activities are covered under Product tank farm and trading facility
scope:-
1. Roads
2. Drains
3. Sleepers
4. Dyke wall
5. Pump station
6. UG pits and sump
7. Dyke wall & Fire wall
8. Sandtrap,Valvepit, inside dyke drain, pavement, Cable trenches
9. Buildings
10. Manholes for UG piping
11. Culverts- PWC and Box culvert
12. Sanitary Sewer Sump-04

12 October 2019
Roads for Trading Facilities and Associated

Pavement

7
ROADS: TRADING FACILITY & PRODUCT TANK AREA

Agency- M/s JBN (Tender No 8013)


Total Road Length – 17.55 km
Total Scope including excavation-201181sqm, sub-base and base course –
44648cum
Total completed till date -823400 Sq.M (73.21% overall)

Total
Total Length (M) Completed (M) Balance Qty. (M) % Completion
Numbers of
road

30 17554 7884 9670 45%

8
Completion Outlook: Road Works

Overall Scope Overall Overall Balance


Oct-19 Nov-19 Dec-19
(M) Completed (M) (M)

17554 7884 9670 2000 3835 3835

SUMMARY-ROAD STREET/ AVENUE TRADING FACILITY STATUS

COMPLETED
ITEM SCOPE LENGTH (M) BALANCE LENGTH (M)
LENGTH (M)

EARTH WORK 17554 17169 385

SUB BASE 17554 16971 583

BASE 1 17554 8109 9445

BASE 2 17554 7884 9670

9
AREAS OF CONCERN

Area of concern:
• JBN to be expedited for taking parallel work fronts as 02 nos roads are yet to be
started.
• PWC works by SINOMA needs to be expedited (06 nos balance out of total 41 nos)
• Drain works shall be expedited to increase the performance of road during
ongoing monsoon

10
PRODUCT TANK DRAINS-25.15 KM
Summary of Drain works
• Agency 1- M/s Demark (Tender no. OT-0025) for Product Tank area drain b/w St-11 to 53

Scope Qty Completed %


Activity UoM
Cu.M till date Complete
Pre-casting/ cast in
CuM 8166 7660 98.89%
situ
Installation M 18004 12800 90.25%

• Agency 2- M/s Rockseed (Tender no. OT-0027)


• Scope Qty Completed %
Activity UoM Remarks
Cum till date Complete
• Status of works:-
Precasting/cast in situ CuM 2650 795 30.0%
Drain b/w ST
49 to ST 50,
Installation M 7150 1850 25.87% ST53 North

11
Trading facility Culverts

• Precast Box culverts & PWC

Agency- M/s SINOMA (8104)

TOTAL % Completion
DESCRIPTION UoM COMPLETED BALANCE
SCOPE

CULVERTS Nos. 78 77 01 98.71%

PWC Nos. 41 35 06 85.36%

12
Product Tank Fire Water Sleepers
• Firewater sleepers

Agency – M/s SINOMA (Tender No 8104)


Total scope = 2869 nos (2233 zone D and 636 in Zone E)
Precasting completed = 2869 nos (100%)
installation completed = 1530 nos. (53.33%)
Completion outlook
Fire water Completed
Scope (nos) Balance (Nos) Nov-19 Dec-19
sleeper (Nos)

Pre-casting 2869 2869 Completed - - -


Installation 2869 1530 1339 700 639
Area of concern:

1. Balance Roads & Drains are to be expedited which are still pending for completion.

13
PROCESS PIPING SLEEPERS

 Agency – M/s SINOMA (Tender No 8104)


 Total Scope= 1578 nos.
 Completed = 92.9%
Completion outlook

Process Dec-19
Scope (No) Completed (Nos) Balance (No) Nov-19
Sleeper

Cast-in-situ 1578 1466 112 112 0

14
Trading Facility Misc. items
DESCRIPTION` UoM TOTAL SCOPE COMPLETED BALANCE

DYKE WALL Cu.M 23000(12.5km) 3680 19320

FIRE WALL Cu.M 1080 0 1080

SAND TRAPS Nos. 46 0 46

VALVE PIT Nos. 46 03 43

OWS SUMP-03 Cu.M 795 0 795

SANITARY SEWER SUMP-04 Cu.M 110 0 110

INSIDE DYKE PAVEMMENT Cu.M 21500 0 21500

DRAIN INSIDE DYKE WALL Cu.M 4550 0 4550

RCC PAVEMENT TRADING FAC Cu.M 108000 0 108000

CABLE TRENCH (RCC) Cu.M 5000 0 5000

CABLE TRENCH (Block Work) Cu.M 1000 0 1000

FLM Nos. 78 30 48
Cu.M
SLOPE PROTECTION(PCC) 3145 0 0

15
TANKFARM / TRADING FACILITY UG PITS
Quantity as
Progress Last Week up
Unit Location Agency Tag No. per drwg. Remarks
to 05.10.2019
(Cu.M)
736 TANK FARM SINOMA 714-VV-1401 135 Completed.
Not started
736 TANK FARM SINOMA 714-VV-1402 150 Sheet pile not available

736 TANK FARM SINOMA 714-VV-1403 150 Raft PCC in progress

736 TANK FARM SINOMA 716-VV-1603 150 Sheet pile not available Not started
GANTRY NORTH
736 732-VV-3201 415 Raft Completed Wall in progress.
AREA RIDGE
Adjacent sump pit
GANTRY NORTH
736 732-VV-3202 410 Raft & Wall Completed. & pedestals in
AREA RIDGE progress.
Adjacent sump pit
GANTRY NORTH
736 732-VV-3203 410 Raft & Wall Completed. & pedestals in
AREA RIDGE progress.
GANTRY NORTH
736 732-VV-3204 410 Excavation in progress
AREA RIDGE
GANTRY NORTH
736 732-VV-3205 459 Excavation in progress
AREA RIDGE

16
UG PITS: COMPLETION OUTLOOK

Sl.no Description Qty (CuM) Oct-19 Nov-19 Dec-19 Jan-19

1 714-VV-1401 135 ü
2 714-VV-1402 150 ü
3 714-VV-1403 150 ü
4 716-VV-1603 150 ü
5 732-VV-3201 415 ü

6 732-VV-3202 410 ü

7 732-VV-3203 410 ü

8 732-VV-3204 410 ü
9 732-VV-3205 459 ü
17
Product Tank Farm & Trading Facility
UG MANHOLES:

Agency:- M/s OMITI and M/s Onshore

CASTING ERECTION

TOTAL
DESCRIPTION UOM
SCOPE COMPLETED
BALANCE ERECTION BALANCE
CASTING

MHO Nos 241 225 16 122 119

MHS Nos 94 94 0 0 94

MHC Nos 46 46 0 25 0

*Additional gang mobilized.


18
TRADING FACILITY BUILDINGS
TOTAL % RCC
DESCRIPTION UoM COMPLETED BALANCE REMARKS
SCOPE COMPLETION

SS-19 Cu.M 1800 615 1185 34.16% Raft completed.

40.08% Super Structure


SS-16 Cu.M 998 400 598
work in progress
Raft completed &
SRR-11 Cu.M 1655 940 835 50.44% Wall reinf. in
progress.

53.15% Sub structure in


CR-04 Cu.M 1840 978 862
progress.

51.11% Plinth beam works in


SFS-04 Cu.M 450 230 220
progress.

MARINE Cu.M 790 380 410 48.10% 1st Slab in progress


CONTROL

TOTAL 7533 3543 3990

19
SS-19: COMPLETION OUTLOOK
CONTRACTOR: ROCKSEED

Items UOM Qty. Status Oct-19 Nov-19 Dec-19


Substructure
Excavation CUM Completed
backfilling CUM Completed
Pcc CUM Completed
RCC CUM 482.00 241.00 241.00
Superstructure
400
RCC CUM 1265.5 600 265.54
Brick work CUM 233 116.5 116.5
Plaster SQM 14221 7110.5 710.5
flooring SQM 4126. 1500 1500 1126
Water proofing SQM 1853 853 1000
False celling SQM 1548 774 774
UNDERDECK INSULATION SQM 1670.48 835.24 835.24
Doors &window NOS 87 43 44
Painting SQM 14000 700 700
20
CR– 04 : COMPLETION OUTLOOK
CONTRACTOR: ROCKSEED / SINOMA

Items UOM Qty. Status Sep-19 Oct-19 Nov-19 Dec-19


Substructure
Excavation CUM Comp.
Backfilling CUM Comp.
Pcc CUM 36.66 Comp.
Rcc Sub structure CUM 980 45 630 196

Super structure CUM 860 0 500 380

Brick work CUM 538.92 400 138


Plaster SQM 3950.3 1500 1750 700
Flooring SQM 1600 750 850
1512
Water proofing SQM 1512
1000 677
False celling SQM 1677.32
31
Dors and window NOS 31
Painting SQM 3559.0 1779.5 1779.5

21
SRR-11: COMPLETION OUTLOOK
CONTRACTOR: ROCKSEED

Items UOM Qty. Status Sep-19 Oct-19 Nov-19 Dec-19


Substructure
Excavation cum Comp.
Backfilling cum Comp.
Pcc cum Comp.
422
120 300
Rcc cum 842
Superstructure
Rcc cum 710 310 400
Brick work cum 160 160
Plaster sqm 2170 1170 1000
Flooring sqm 1341 541 800
Water proofing sqm 727 727
False celling sqm 516 516
Doors and window nos 27 10 17
Painting sqm 1800 900 900
22
MARINE CR COMPLETION OUTLOOK
CONTRACTOR: M/s ARBICO
Completion Schedule
S No Activity Qty. Unit
Comp. Bal. Oct-19 Nov-19 Dec-19

400 Cum 400 0


1 RCC- Sub Structure
RCC- Super 390 Cum 30 360 110 130 120
2 Structure
Block Work 470 Cum 0 140 210 120
3 Masonry
Door/Window/ 74 Nos. 0 45 29
4 Ventilator
580 Sqm 0 280 150 150
5 Flooring

Misc. Architectural 1 Unit 0 0.5 0.25 0.25


6 Work
7 Final Completion 1 Unit 0 1

23
TANKAGE WORKS

All Day Tanks &


TF-37, 40, 43, 46, 50, 36,38,39,40, 41,42,
43,44,47,51,59,55,56,54,55,52,27,49

Total : 45 Tanks

12 October 2019
TANKS COMPLETION SUMMARY

HYDRO HYDRO TEST


TOTAL MECH. BALANCE FOR
UoM TEST IN
SCOPE CLEARANCE MC
COMPLETED PROGRESS

Nos 45 30 15 21 09

12 October 2019
SUMMARY OF TANK FABRICATIONS

Compl % Target
Sr.No. Activity Qty Scope Balance
eted Comp Completion
1 Tank Fabrication MT 41707 41246 461 99 Jan-2020
2 Tank Erection MT 41707 32623 9084 78 Dec-2020
3 Blasting & Primer MT 41707 36463 5244 87 Dec-2020
4 Tank Fit-Up & Welding MT 41707 32624 9083 78 Jan-2020
5 Radiography/NDT & PWHT MT 41707 30705 11002 74 Feb-2020
Tank/Structural Final
6 MT 41707 13732 27975 33 April-2020
Painting/Stenciling
7 Foam Pipe Fabrication (CS) ID 36537 8233 28304 23 April-2020
8 Foam Pipe Erection (CS) IM 44525 7178 37347 16 April-2020
9 Foam Pipe Hydrotesting (CS) IM 44525 0 44525 0 April-2020

10 Cooling Pipe Fabrication (GI) ID 67400 40145 27255 60 April-2020


11 Cooling Pipe Erection (GI) IM 119822 47604 72218 40 April-2020
12 Tank Hydrotesting Nos. 44 28 16 64 April-2020
13 Insulation (3205A &3205B) SQM 22890 0 22890 0 April-2020

14 Heating Coil (3205A&3205B) Mtr 360 0 360 0 April-2020


15 Tank Calibration Nos. 44 4 40 9 April-2020
12 October 2019
FABRICATION STATUS OF PRODUCT TANKS
Balance
SCOPE COMPLETED BALANCE ERECTION ERECTION Fabrication/
S.N TF SERVICE TANK TYPE
(MT) (MT) (MT) COMPLETED BALANCE Erection Activity
(MT)
GASOLINE
1 27A 3201A IFR 1,385 1,375 10 1375 10 Deflector plate 10t
DAY
GASOLINE
2 27B 3201B IFR 1,385 1,375 10 1375 10 Deflector plate 10t
DAY
GASOLINE
3 52C 3201C IFR 1,385 1,375 10 1375 10 Deflector plate 10t
DAY
GASOLINE
4 52D 3201D IFR 1,385 1,375 10 1375 10 Deflector plate 10t
DAY
5 53A DIESEL DAY 3202A CR 326 326 0 322 4 Deflector plate 10t

6 53B DIESEL DAY 3202B CR 326 326 0 322 4 Deflector plate 10t

7 53C DIESEL DAY 3202C CR 326 326 0 322 4 Deflector plate 10t

8 53D DIESEL DAY 3202D CR 326 326 0 322 4 Deflector plate 10t

9 54A JET DAY 3203A IFR 414 414 0 410 4 Deflector plate 10t

10 54B JET DAY 3203B IFR 414 414 0 411 3 Deflector plate 10t

11 54C JET DAY 3203C IFR 414 411 3 411 3 Deflector plate 10t

12 October 2019
FABRICATION STATUS OF PRODUCT TANKS
KEROSENE
12 55A 3204A CR 325 323 2 322 3 Deflector 3 t
DAY
KEROSENE
13 55B 3204B CR 325 322 3 322 3 Deflector 3 t
DAY
SLURRY
14 56A 3205A CR 156 155 1 155 1 Deflector 1 t
DAY
SLURRY
15 56B 3205B CR 156 155 1 155 1 Deflector 1 t
DAY

16 38G GASOLINE 1401G FR 1,643 1,635 8 1635 8 Deflector 8 t

17 38H GASOLINE 1401H FR 1,643 1,635 8 1635 8 Deflector 8 t

18 41E DIESEL 1404E CR 768 760 8 760 8 Deflector 8 t

19 41F DIESEL 1404F CR 768 760 8 760 8 Deflector 8 t

20 44E KEROSENE 1403E CR 768 760 8 760 8 Deflector 8 t

21 44F KEROSENE 1403F CR 768 760 8 760 8 Deflector 8 t

Shell -7 job erection


22 47E JET 1402E IFR 1,314 1,277 37 259 1,055 going on & Bal. 6 nos.
Shell Course & Deck.

12 October 2019
FABRICATION STATUS OF PRODUCT TANKS

Erection of 7th shell in progress


23 47F JET 1402F 1,314 1,277 37 231 1,083
& 6th shell & deck bal.
Erection of 7th shell in progress
24 51C ETHANOL 1607C 1,305 1,287 18 456 849
& 6th shell & deck bal.
Erection of 6th shell in progress
25 37E GASOLINE 1401E 1,546 1,507 39 505 1,041
& 5th shell & deck bal.
Erection of 6th shell in progress
26 37F GASOLINE 1401F 1,546 1,505 41 487 1,059
& 5th shell & deck bal.
Erection of 9th shell in progress
27 40C DIESEL 1404C 768 758 10 245 523
& 8th shell.
Erection of 9th shell in progress
28 40D DIESEL 1404D 768 759 9 188 580
& 8th shell.
Erection of 7th shell in progress
29 43C KEROSENE 1403C 768 757 11 393 375
& 6th shell.
Shell -8 job erection going on &
30 43D KEROSENE 1403D 768 757 11 352 416
Remaining 7 Shell Course
Erection of Shell-1 erection in
31 46C JET 1402C 1,314 1,301 13 1038 276
progress & Deck balance.
Erection of Shell-1 erection in
32 46D JET 1402D 1,314 1,305 9 1244 70
progress & Deck balance.

33 50A ETHANOL 1607A 1,305 1,295 10 1295 10 Deflector plate 10 t

12 October 2019
FABRICATION STATUS OF PRODUCT TANKS

34 50B ETHANOL 1607B 1,305 1,295 10 1295 10 Deflector plate 10 t

35 36C GASOLINE 1401C 1,643 1,635 8 1635 8 Deflector plate 8 t

36 36D GASOLINE 1401D 1,643 1,635 8 1635 8 Deflector plate 8 t

37 39A DIESEL 1404A 812 804 8 804 8 Deflector plate 8 t

38 39B DIESEL 1404B 812 804 8 804 8 Deflector plate 8 t

39 42A KEROSENE 1403A 812 804 8 804 8 Deflector plate 8 t

40 42B KEROSENE 1403B 812 804 8 804 8 Deflector plate 8 t


Deck Fab & Erection
41 45A JET FUEL 1402A 1,384 1,375 9 1355 29
in progress
42 45B JET FUEL 1402B 1,384 1,375 9 1372 12 Deflector plate 12 t
CBFS/ Foundation work in
43 49A 1405A 832 810 22 0 832
SLURRY progress
CBFS/
44 49B 1405B 832 812 20 138 694 Shell 9 in progress.
SLURRY
12 October 2019
FABRICATION STATUS

Surge protection tank-(Tankage-III)

HEIGHT Erection Erection


SI NO TAG NO contractor DIA(M) WT(T) Hydro-test
(M) comp Bal

720-TT-
1 Chemi-tech (T-III) 9 10 43 43 0 Completed
2006

12 October 2019
CONSTRAINTS

M/s CTL Scope:


 Gratings & foam platform.
 Delay in foam piping works due to non-availability of adequate
manpower & resources.

M/s DORC SCOPE OF SUPPLY:

1. Flame arrestor for tank 3201A-D, 08 Nos.


2. Level Transmitter LT1&LT2 (Radar Type)-45 nos.
3. Multipoint Temperature Element TE-45 nos.
4. Pressure Vacuum Relief Valve PVRV for tank 1607a-c- 3 nos.

12 October 2019
AG-PIPING SUMMARY

% Completion
Area/ Scope Comp. Available
UoM Bal. Qty up to Last
Zone Qty Qty Work Front
Week

ID 196988 16991 179997 8.63% 18692


D
IM 1661814 162347 1499467 9.77% 238789

ID 140098 998 139100 0.71% 0


E
IM 537450 0 537450 0.00% 0

ID 337086 12114 324972 3.59% 18692


Total
IM 2199264 129756 2069508 5.90% 238789

12 October 2019
COMPLETION OUTLOOK: AG PIPING

ZONE
Description

UoM
Bal. Qty 19-Oct 19-Nov 19-Dec 20-Jan 20-Feb 20-Mar
of Unit

ID 179997 20999.5 32999.5 32999.5 32999.5 29999.5 29999.5


Product
D
Tank Area
IM 1499467 209912 256711.2 258411.1 249911.2 265911.2 258610.41

ID 139100 23183.33 23183.33 23183.33 23183.33 23183.33 23183.333


Trading
E
Facility
IM 537450 89575 89575 89575 89575 89575 89575

ID 324972 44182.83 56182.83 56182.83 56182.83 53182.83 53182.833


Total

IM 2069508 299487 346286.2 347986.1 339486.2 355486.2 348185.41


Total

Manpower Projection as per Annexure-1

12 October 2019
PIPING AREA RELEASE STATUS

ZONE D

ZONE E

12 October 2019
AG PIPING AREA RELEASE STATUS

TOTAL BAL. AREA


AREA
ZONE PIPING TO BE % RELEASED
RELEASED
AREAS RELEASED

D 140 53 87 37.8%

E 85 13 72 15.26%

12 October 2019
CONSTRAINTS

1. Piping areas (Sleepers) not released due to non-completion of dyke


wall works.
2. FIMs balance pipes 24”& balance fittings not yet received.
3. Balance Piping areas 164 nos. not yet released by Civil agency.
4. Gantry Area pipe sleepers and rack not yet released.

12 October 2019
UNDER GROUND PIPING SUMMARY

Description of
AREA UoM Scope Qty Completed Qty Balance Qty % Completed
Unit

ID 54100 13223 40877 24.44%

IM 270000 65527 204473 24.27%


Trading Facility/
Product Tank
Area
ID 16700 4502 12198 26.96%

IM 53808 10972.8 42835.2 20.39%

12 October 2019
UG PIPING DISTRIBUTIONS

12 October 2019
COMPLETION OUTLOOK FOR UG PIPING WORKS

Description of
AREA UoM Bal. Qty 19-Oct 19-Nov 19-Dec Jan-19
Unit

ID 40877 10219.25 10219.25 10219.25 10219.25


D
Trading Facility/ IM 204473 51118.25 51118.25 51118.25 51118.25
Product Tank
Area (OWS,
CBD & CRW) ID 12198 3049.5 3049.5 3049.5 3049.5
E
IM 42835.2 10708.8 10708.8 10708.8 10708.8

ID 53075 13268.75 13268.75 13268.75 13268.75


TOTAL
IM 247308.2 61827.05 61827.05 61827.05 61827.05

•Provided balance fittings for CBD, OWS are issued by 19-Oct.

••Manpower Projections as per Annexure-II

12 October 2019
CONSTRAINTS

01. Balance FIMs Valves & fittings for CBD, OWS.

03. Non-completion of drains in gantry area caused water logged.

CONTRACTOR’S SCOPE OF SUPPLY (Not yet Delivered at site):

1. Balance PPR & uPVC Pipes & fittings for WDK & S Sewer piping.

2. CI Manhole Covers

3. Chequered Plates.

4. Adequate numbers of manpower & resources like excavator, dewatering pumps,


coating tools etc. to be mobilize by M/s OCLLC.

5. MHS Concrete adaptors.

12 October 2019
FIRE WATER PIPING: SUMMARY

Description Scope Qty Comp. Qty Bal. Qty % Completion

Inch Dia 36418 3200 33218 8.7%

Inch Meter 305768 65000 240768 21.25%

Hydrant 346 0 346 0

Monitor 229 0 229 0

12 October 2019
FIRE WATER COMPLETION OUTLOOK

Description of
UoM Bal. Qty 19-Oct 19-Nov 19-Dec 20-Jan Feb-2020
Unit

ID 33218 6643.6 6643.6 6643.6 6643.6 6643.6


Trading Facility/
Product Tank
Area
IM 240768 48153.6 48153.6 48153.6 48153.6 48153.6

HYDRANT Nos 346 - - - - -

MONITOR Nos 229 - - - - -

12 October 2019
FIRE WATER DISTRIBUTIONS

12 October 2019
CONSTRAINTS

1. FIMs fittings (Epoxy coated) for balance UG fire water road crossings not yet
received at site.
2. Fire Water Monitor & Hydrants not yet received at site.
3. Fire Water Hose Reel & Rubber Hose along with Box not yet received at site.

12 October 2019
MECHANICAL EQUIEPMENT: STATIC & ROTARY

SCOPE in
S.No Equipment COMPLETED BALANCE Remarks
Nos.

Foundation not yet


1 Rotary 62 0 62
handed over

Foundation not yet


2 Static 10 0 10
handed over

3 Loading Arms 101 0 101


4 COMPRESSOR 1 0 1
5 Air Compressor 1 0 1

HFO/ LFO Engine


6 2 0 2
Generator

7 Diesel Generator 1 0 1
8 Weigh Bridge 2 0 2
* 03 Nos. Foundation casting Completed.

12 October 2019
COMPLETION OUTLOOK: UG PITS EQPT.

Expctd Date of FDN


Sl.no Description Qty (CuM) Oct-19 Nov-19 Dec-19 Jan-20 Feb-20
Readiness

1 714-VV-1401 135 Completed ü


2 714-VV-1402 150 15-10-19 ü
3 714-VV-1403 150 31-10-19 ü
4 716-VV-1603 150 31-10-19 ü
5 732-VV-3201 415 08-09-19 ü
6 732-VV-3202 410 15-07-19 ü
7 732-VV-3203 410 31-07-19 ü
8 732-VV-3204 410 15-10-19 ü
9 732-VV-3205 459 30-10-19 ü
12 October 2019
ERECTION OUTLOOK OF PUMPS

Qty Expctd Date of FDN


S.No Description 19-Oct 19-Nov 19-Dec
(Nos) Readiness

1 733-PA-CF-101A-C 3 28/10/2019 
2 714-PA-1401A-F 6 25/10/2019 
3 733-PA-CF-103A-C 3 Completed 
4 714-PA-1404A-C 3 Completed 
5 714- PA-1410A-B 2 Completed 
6 733-PA-CF-105A-C 3 Completed 
7 714-PA-1403A-B 2 Completed 
8 714-PA-1402A-B 2 Completed 
9 716-PA-1607A-C 3 Completed 
10 732-PA-3201A-H 8 Completed 

48
ERECTION OUTLOOK OF PUMPS
11 732-PA-3204A-C 3 Completed 
12 732-PA-3203A-C 3 Completed 
13 732-PA-3202A-F 6 Completed 
14 732-PA-3205A-C 3 Completed 
15 720-PA-2006 1 20/11/2019 
16 714-PA-1406 1 10/11/2019 
17 714-PA-1408 1 28/11/2019 
18 714-PA-1412 1 Completed 
19 714-PA-1407 1 14/11/2019 
20 716-PA-1610 1 12/11/2019

21 714-PA-1405A-B 2 20/11/2019 
22 714-PA-1411A-C 3 20/11/2019 

49
GANTRY LOADING ARMS – MSR DATA
EDR AS PER
SI NO MR DESCRIPTION TAG NO QTY FOA VENDOR NAME
MSR

JIANGSU
LOADING ARMS
1 732-LA-001 A/B -10 A/B 20 5037 CHANGLONG 30/11/2018
(ROAD)
TECHNOLOGIES

JIANGSU
LOADING ARMS
2 732-LA-011 - 040 30 5037 CHANGLONG 30/11/2018
(ROAD)
TECHNOLOGIES

JIANGSU
LOADING ARMS
3 732-LA-041 - 057 17 5037 CHANGLONG 30/11/2018
(ROAD)
TECHNOLOGIES

JIANGSU
LOADING ARMS
4 732-LA-058 - 078 21 5037 CHANGLONG 30/11/2018
(ROAD)
TECHNOLOGIES

JIANGSU
LOADING ARMS
5 732-LA-079 - 081 3 5037 CHANGLONG 30/11/2018
(ROAD)
TECHNOLOGIES

JIANGSU
LOADING ARMS
6 732-LA-082 A/B - 086 A/B 10 5037 CHANGLONG 30/11/2018
(ROAD)
TECHNOLOGIES

50
MISC EQUIPMENTS - MSR DATA

Item Code / Tag Contractual Expected Date


SI NO Item Description Vendor Name
No. Delivery Date of Readiness

HFO / LFO Engine


1 736-MD-1001 Powerica Ltd 31/12/2018 15/04/2019
Generator

HFO / LFO Engine


2 736-MD-1002 Powerica Ltd 31/12/2018 15/04/2019
Generator

3 736-KA-1001 Air Compressor Atlas Copco Ltd 31/03/2018 Dispatched

Reciprocating
4 732-KA-3201 DOVER INDIA 31/08/2018 31/08/2019
Compressor

12 October 2019
GANTRY STRUCTURAL WORKS COMPLETION
OUTLOOK
GANTRY SCOPE COMPLETED BALANCE 19-Oct 19-Nov
ü
GANTRY1 207.4 202 5.4

GANTRY2 207.4 207.4 0

GANTRY3 207.4 207.4 0

GANTRY4 207.4 207.4 0 ü


GANTRY5 207.4 90 117.4 ü
GANTRY6 151.9 0 151.9 ü
GANTRY7 207.4 130.6 76.8 ü
GANTRY8 225.18 118.435 106.745

GANTRY9 79.55 37.425 42.125 ü


GANTRY10 49 20.36 28.64 ü

GANTRY11 108.25 102.459 5.791 ü

12 October 2019
CIVIL WORK AT LVS AND PRODUCT TERMINAL

Work Description UOM Scope Completed Balance

PIPING SUPPORTS NO'S 0


(LVS Station) 20 20

PIPING SUPPORTS NO'S 0


(PRODUCT TERMINAL) 535 535

FDN/PUMS/SKIDS/ CUM
LAUNCHERS 1200 0 1200

SEALING OFFICE CUM 118 0 118


(TWO BUILDINGS)

12 October 2019
PIPIELINE SCOPE AND STATUS

PRODUCT
TOTAL LINGTH OF LINE COMPLETED BALANCE
S NO. NAME OF THE SIZE
(M) (M) (M)
LINE

1 JET/KO 24" 3702.255 2296.147 1406.108

2 DIESEL 24" 3650.811 2424.899 1225.912

3 GASOLINE 24" 3694.202 2275.046 1419.156

4 ETHANOL 24" 3703.922 2352.712 1351.21

TOTAL 14751.19 9348.804 5402.386

12 October 2019
PIPELINE COMPLETION OUTLOOK

BALANCE TARGET COMPLETION

PRODUCT
S NO. NAME OF THE SIZE
LINE
(M) OCT'19 Nov'19 Dec'19

1 JET/KO 24" 1406.108 469 469 469

2 DIESEL 24" 1225.912 409 409 409

3 GASOLINE 24" 1419.156 473 473 473

4 ETHANOL 24" 1351.21 450 450 450

TOTAL 5402.386 1801 1801 1801

12 October 2019
STATION PIPING SCOPE

Pipeline UOM Total Scope Completed Balance

ID 2100 0 2100

LAND FALL
STATION

IM 6000 0 6000

ID 40000 0 40000
Product Terminal

150000
IM 150000 0

12 October 2019
SUMMARY OF CONTRACTOR SCOPE OF SUPPLY

CONTRACTOR'S SCOPE OF SUPPLY ITEMS STATUS AS ON DATE FOR TRADING FACILITIES BY OMITTI

DRAWINGS/DATA
YET TO BE
TOTAL NO OF SHEET ORDERED BY
SI NO DEPARTMENT ORDERDED REMARKS
ITEMS APPROVED OMITTI
BY OMITTI
STATUS
MTC TO BE
SUBMITTED BY
1 PIPING 45 8 0 45 OMITI FROM
APPROVED
VENDOR
MTC TO BE
SUBMITTED BY
2 MECHANICAL 19 18 3 16 OMITI FROM
APPROVED
VENDOR
MTC TO BE
SUBMITTED BY
3 ELECTRICAL 65 2 0 65 OMITI FROM
APPROVED
VENDOR
MTC TO BE
SUBMITTED BY
4 INSTRUMENTATION 42 0 0 42 OMITI FROM
APPROVED
VENDOR

12 October 2019
CONTRACTOR'S SCOPE OF SUPPLY ITEMS STATUS AS
ON DATE FOR TRADING FACILITIES (M/S OMITTI)
SI TOTAL NO APPROVAL STATUS DRAWINGS,DATA ORDERING STATUS
ITEM NAME
NO OF ITEMS SHEET BY M/S OMITTI
PIPING FITTINGS SMALL BORE MTC TO BE SUBMITTED BY OMITI
1 31
(FOR STATION PIPING) FROM APPROVED VENDOR
INSULATION JOINTS
2 14 Approved
(24'',48'',30,'')
160 ITEMS APPROVED,REST MTC TO
3 VALVES (SMALL BORE) 258
BE SUBMITTED BY M/S OMITTI
4 SCRAPPER TRAPS( 30'' X 24'') 4 Approved
5 QOEC( 30'' X 24'') 4 Approved
JIB CRANE: 2 TON MT PRODUCT NOT YET ORDERD
6 4 Approved
TERMINAL
Pig signaler- on Product Pipeline
7 4 Approved
2"X300#
Pig signaler- on Product Scraper
8 4 Approved
traps2"X300#
Flow tee: (24'x24" 300# UG,
24'x24" 300# AG,48'x24" 150#
9 14 Approved
UG,48'x30" 150# UG,48''x48" 150#
UG)
CASING END SEAL FOR
10 1 Approved RECEIVED AT SITE
COASTAL RDX
11 REJECT WATER COUPLING 192 Approved NOT YET ORDERD
12 WARNING MATE 1 Approved
RECEIVED AT SITE
13 CASING VENT PIPES(4" DIA) 1 Approved

12 October 2019
LIST OF EQUPMENT AT PRODUCT TERMINAL

SL. NO EQUPMENT NO DESCRIPTION VENDOR PO EDD REMARKS


LAUNCHER FOR ETHANOL & NOT YET
1 733-ML-00-101 M/S OMITTI SCOPE 3001
GAOLINE ORDERED
NOT YET
2 733-MR-00-102 RECEIVER FOR GASOLINE M/S OMITTI SCOPE 3001
ORDERED
NOT YET
3 733-ML-00-103 LAUNCHER FOR JET/SKO M/S OMITTI SCOPE 3001
ORDERED
NOT YET
4 733-MR-00-104 RECEIVER FOR HSD M/S OMITTI SCOPE 3001
ORDERED
DANIEL MEASUREMENT SOLUTIONS (P)
5 733-SRV-1201 SRV SKID FOR GASOLINE 5179 31/10/2018
LIMITED
DANIEL MEASUREMENT SOLUTIONS (P)
6 733-SRV-1301 SRV SKID FOR ETHANOL 5179 31/10/2018
LIMITED
DANIEL MEASUREMENT SOLUTIONS (P)
7 733-SRV-1601 SRV SKID FOR GASHSD 5179 31/10/2018
LIMITED
DANIEL MEASUREMENT SOLUTIONS (P)
8 733-SRV-1801 SRV SKID FOR GAS JET/SKO 5179 31/10/2018
LIMITED
DANIEL MEASUREMENT SOLUTIONS (P)
9 733-M-001 METERING SKID FOR GASOLINE 5178 31/05/2019
LIMITED
DANIEL MEASUREMENT SOLUTIONS (P)
10 733-M-002 METERING SKID FOR HSD 5178 31/05/2019
LIMITED
DANIEL MEASUREMENT SOLUTIONS (P)
11 733-M-003 METERING SKID FOR JET/SKO 5178 31/05/2019
LIMITED
DANIEL MEASUREMENT SOLUTIONS (P)
12 733-PA-CF-102 A/B/C GASOLINE TRANSFER PUMP 5178 31/05/2019
LIMITED
13 733-PA-CF-104 A/B/C HSD TRANSFER PUMP ITT/GOULDS 5117 29/11/2018

14 733-PA-CF-106 A/B/C JET/SKOTRANSFER PUMP ITT/GOULDS 5117 29/11/2018

15 733-PA-SM-112 A/S SUMP PUMP Flowserve 5074 31/08/2019


SUMP TANK FOR
16 733-VV-102 Fabtech Projects 5096 28/02/2019
GASL,ETH,HSD,& JET/SKO

12 October 2019
CONSTRAINTS

DORC SUPPLY:
1. FIMs pipes, fittings not yet received at site for station piping.
2. LR bends not yet received at site.(Initially it was under Omitti scope)

Areas of Concern:

• Offloading process from m/s OMITTI to be speed up.


• Contractor scope of supply items to be directly procured by DORC to avoid further
more delay.
• Gantry structural works Slow progress by M/s Omiti, Manpower needs to be
increased.

12 October 2019
ELECTRICAL

61
--THANK YOU--