Professional Documents
Culture Documents
Workshop Cost Estimating
Workshop Cost Estimating
Workshop Cost Estimating
Cost estimating may be used to quantify, cost and price any investment
activity, such as building an office building or process power plant, developing
a software program, or producing a stage play. The basic estimating steps are
the same: Understand the scope of the activity to quantify the resources and
material required, then apply costs to those resources and materials
Estimate Terminology
1. Predictive process used to quantify, cost, and price the resources
required by the scope of an investment option, activity, or project.
Cost Estimating
Benchmarking
Capacity factored,
Screening or feasibility parametric models,
Class 4
Budget authorization or Semi-detailed unit costs
with assembly level line
10% to 40% 2 to 6 3 to 10
Class 3 control items
Class 1
Estimate Methodology
In general, estimating methodologies commonly fall into two
broad categories: conceptual and deterministic.
– Parametric Method
A parametric model is a mathematical representation of cost relationships that provide a
logical and predictable correlation between the physical or functional characteristics of a
plant. For example Total Installed Cost/Dim in mile for pipelines.
Estimate Methodology
Deterministic Estimating Methodologies
– A detailed estimate is one in which each component comprising a project scope definition is
quantitatively surveyed and priced using the most realistic unit prices available. Detailed
estimates are typically prepared to support final budget authorization, contractor bid tenders,
cost control during project execution, and change orders (Class 3 through Class 1 estimates).
–If the construction costs for a 25 guest room hotel was $8,000,000
what would a 95 guest room hotel cost be utilizing the end product
methodology?
$30,400,000
$33,300,000
Application of Estimate
Methodology
End Product Estimating Methodology
–If the construction costs for a 100 parking space garage was
$13,000,000 what would a 30 parking space garage cost be utilizing
the end product methodology?
$3,900,000
$2,700,000
Application of Estimate
Methodology
Physical Dimensions Estimating Methodology
– If the house next door which is 50’ wide x 100’ long cost
$400,000 to build last week, what would your approximate cost be
for your 5000 square foot house?
$400,000
Application of Estimate
Methodology
Ratio or Factor Estimating Methodology
– In 1947, Hans Lang first published an article in Chemical Engineering introducing
the concept of using the total cost of equipment to factor the total estimated cost of
plant.
– Lang proposed three separate factors based on the type of process plant (see table
below). Lang’s factors were meant to cover all the costs associated with the total
installed cost of a plant.
Lang Factor
– If the total equipment cost for a wood pellet solid process plant
was $5,000,000 what would the Total Plant Cost be?
– Total Plant Cost = $5,000,000 x 3.1
– Total Plant Cost = $15,500,000
Deterministic Estimating
Methodologies – Understanding
Direct & Indirect costs
–The installation hours associated with a worker installing piping
inside of a module would be considered a Direct or Indirect Man-
hour?
Direct
–The travel time between hotel and the module where the worker is
installing the pipe would be considered a Direct or Indirect Man-
hour?
In-Direct
1. Direct 2. In-Direct
Deterministic Estimating
Methodologies – Understanding
Direct & Indirect costs
–Snow removal man-hours and equipment needed to get access to the
module where the workers are installing piping inside of the module
would be considered a Direct or Indirect cost?
In-Direct