Professional Documents
Culture Documents
Draft Reply
Draft Reply
Inquiry Remark
If the proposed land has highway going
Yes. The project layout allowed to be presented as one layout with single entity
across and dividing the land of PJT into two
1 ownership. There shall be connection within both plots either under pass or over
patches(A,B), is the proposed land able to
bridge.
be recognized as a single patch land ?
Green Belt shall be mandatorily provided along the boundary of both the plots,
however need not be essentially 33% of individual parcels of land. Green Belt of
composite 33% over the total land area proposed is mandatory. Percentage
distribution of green belt on any part of the total plot shall be justified by the type
if the proposed land is able to be recognized of units/facility proposed on the part of the total land.
as a single patch land for PJT, should the
Land parcel 2
size of mandatory green belt account for As per the standard TOR of EAC (Industry-1):
33% of total land(A+B)? Green Belt development consisting of 3 tiers of plantations of native species all
along the periphery of the project of adequate width shall be raised in 33% of total
area with a tree density shall not less than 2500 per ha within a time frame of one
year shall be submitted. Survival rate of green belt shall be monitored on periodic
basis to ensure that survival rate not be less than 80 %.
if the proposed land is not able to
recognized as a single patch land, should
3 Connectivety of different land parcels are madatory.
each land parcel satisfy the 33% greenbelt
regulation independently?
When it comes to national highway
construction, In accordance with guide line
1 of Indian Govt, Does it has to leave Yes.
Highway 500metre of land on both side of high way
construction mandatorily?
Is there any flexibility in size of land that
No.
2 need to be placed on the both side of
highway? (perhaps less than 500metre)
Category No. Inquiry Remark
Can we apply for environmental clearance if we Application for TOR can be filed with part possession of land. However, for the
have the land more than certain amount out of land not in possession; credible document like intent to sell land to Industry
Land owned 1 total project land? Any criteria in regard? etc. need to be submitted to the Ministry. For the land in possession- 7/12
by different extract and other ownership documents with conversion certificate to
party industrial use, as applicable need to be submitted.
within the if the part of land is owned by not project
No.
proposed land proponent but someone else, Is it possible to
2 Land possession document shall be mandatorily required at the stage of EC
obtain the environmental clearance and begin the
grant.
construction ?
Yes.
Can we apply for Environmental clearance on
Depending upon the type of litigation, EAC may grant TOR. However, land
1 certain land in case there are ongoing litigation or
ownership dispute shall not be there at the stage of EC. Also, the EC. If
any kind of claims?
Environment ranted will be subject to order related to dispute.
clearance Is there any important things to consider when
2 constructing ISM except 33% greenbelt ratio, ZLD is mandatory.
ZLD?
ISM
4km
Rajathagarh
Station Railway
132kV
S/S
NH55
20km
13.2km
220kV
Mahanadi river S/S Cuttack