Dasthagiri (20018-C-071)
Dasthagiri (20018-C-071)
ON
“CONSTRUCTION OF BITUMENS
ROAD”
(Under Panchayat Raj Department, Tirupati.)
Presented
by
D.DASTHAGIGI
Internal Guide 20018-C-071 Training Incharge
K.RAJIV M.MOHAN
LECTURER ASSISTANT ENGINEER
CONTENTS
INTRODUCTION
MATERIALS
MACHINERY
CONSTRUCTION PROCEDURE
CONCLUSION
INTRODUCTION
Bitumen emulsion : Bitumen emulsion is a liquefied type of bitumen with a low viscosity.
By dispersing bitumen in water and adding an emulsifier, ordinary bitumen turns into a low
viscosity liquid that can easily be used in a variety of applications, including repairing and
maintaining roads, waterproofing, spraying, etc.
Machineries
Batch Mix Plant:A bitumen mixing plant, also
called asphalt mixing plant, is road surface
paving material production equipment that is
used to blend cold aggregate, liquid bitumen,
and other admixture to form blacktop, which is
widely used for road construction
Paver : A paver is a piece of construction
equipment used to lay concrete or Portland
cement concrete on roads, bridges, parking lots
and other such places. It lays the material flat and
provides minor compaction.
Roller : vehicle used to compact soil, gravel, concrete,
or in the construction of roads and foundations
Truk : Truck, also called lorry, any motor vehicle designed to carry materials from
one place to other place.
CONSTRUCTION PROCEDURE
SITE CLEARENCE
PREPARATION OF SUBGRADE
PREPARATION OF GRANULAR SUB BASE
LAYING OF WMM LAYWER
BITUMINIOUS SURFACING COURESE
COMPACTION
OPENING TO TRAFFIC
The work shall consist of cutting,trimming
SITE CLEARENCE removing and disposing of all materials such as
tress,tress branches,bushes,shrubs,roots,grass,top
organic soil not exceeding 150 mm in
thickness,loose stone etc….
Clearing and grubbing shall be performed less than
one month in advance of earthwork operation.
Reclearing of the site of any vegetation,grass shrubs
During clearning and grubbing ,the contractor shall
take all adequate precations for preservation of all
vegetation adjacent to road land against soill
erosion, water pollusion etc..
Tools & Equipment as per approved by engineer
shall be adopted for the work . If the area has thick
vegetation/roots/tress,a tractor-dozer may be
requied for clearance purpose..
Excavators..
Backhoe…
Hand clearnind etc…
PREPARATION OF SUBGRADE
PREPARATION OF MIX
The GSB material must be natural river bed
material with the right gradation or crushed
stone aggregate devoid of organic .
SPREADING OF MIX
laying spreading , crushed, well-graded granular
materials on a prepared and approved Granular
sub base. Thickenss 250mm…..
COMPACTION
The material is well mixed with water and rolled to
a dense mass. It shall be laid on one or more layers as
per line and level, grade.compact thinness 200mm
OPENING TO TRAFFIC
LAYING OF BIYUMENS ROAD SURFACE
The main purpose of bitumen in flexible pavements is to strongly bind and hold the
other pavement components together and provide a smooth and leveled surface for
the moving vehicles. Bitumen is a naturally occurring material and is found in large
quantities in the solid or semi solid forms of petroleum.
Bitumen is a binding agent produced from petroleum. Bitumen is known for being
strongly adhesive and resistant to damage from water and oil spills. This makes
bitumen the ideal binder for asphalt because asphalt is commonly used as a surface
for roads, car parks and driveways.
It is used to make the surface of roads, as well as to provide a base for roads.
CONSTRACTION OPERATION (BITUMEN ROAD SURFACE )
Preparation of
surface :Whenre the
exisiting surface is
granular ,all loose materials
shall be removed and shall
be clearned of all loose and
extraneous matter and the
surface lightly watered.
The surface finish of all
granular layer on which
bituminous works are to be
placed shall be free from
dust.
All such by means of layer
on BT works are to be
capable swept, after the
removal of any non-integral
loose materials by
mechanical broom.
PRIME COAT OVER GRANULAR BASE
A prime coat is the application of a suitable bituminous binder applied to a
non-bituminous granular base as a preliminary treatment before the
application of a bituminous surfacing
Prime coats protect the integrity of the granular base during construction and
help reduce dust.Prime shall be allowd to cure for at least 24 hours long period
This will usually be from 1.0 to 2.5 litres per square metre, and at a temperature
within the range called for in Table 3.4-6 for the particular material being used.
TACK COAT OVER GRANULAR BASE
Tack coat is a sprayed application of an asphalt binder upon an existing asphalt
or Portland cement concrete pavement prior to an overlay, or between layers of
new asphalt concrete.
To create a strong adhesive bond without slippage
Curing period for most tack coat materials require 1 to 2 hr to fully cure (set)
(Kg/M2)
1) Normal bituminous surface 0.20-0.25