2023.11.12 Daily Work Report PT. GLOBAL
2023.11.12 Daily Work Report PT. GLOBAL
LIK -
▣ Renovation Project – CHANG SHIN FACTORY
Times : 8 am – 3.00 pm Times : 3 pm – 6.00 pm
2023-11-12
Progress
Division Unit
Total Before Today Accum. %
FLASING FOR FRP(SAMPING FRP ONLY) 0,3T with Water proof type m1 12,480 0 0 0 0%
REMOVE ROOF AND WALL TO INSTALL GUTTER m1 1,488 0 130.2 130.2 8.75%
PT. LIK -
▣ Renovation Project – CHANG SHIN FACTORY
Worker
Division Staff Supir SUM Remark
Roof worker Cleaning operator
Manpower 1 1 7 2 11
Equipment
□ Schedule
6.11 30.12
Devision
0 10 20 30 0 10 20 30
11/06 FINISH 12/30
FRP
JJC
JJC – Plan C
JJC - ACC
JJC – Plan B
JJC – Plan A
PT. LIK -
DOCUMENTATION WORK