Professional Documents
Culture Documents
Alternative Access Road (LGICT) 100423
Alternative Access Road (LGICT) 100423
Alternative Access Road (LGICT) 100423
Introduction
Purpose
BICUTAN
Location of Alternative LGICT Access Road CP S-03
SUCAT
CP S-07
Item for Discussion
Introduction NSCR CP S-07
▣ Introduction
1. The original plan at the time of bidding was to access the site via ①Manila South Road
→ ②Banlic Mamatid Road → ③Villa Palao Road. However, due to changes in the site
conditions of CP S-06 (delay in Site land Acquisition), the original access roads cannot
be used as planned. Therefore, an alternative access road was needed, and this
document is a plan for the alternative access road.
▣ Purpose
2.1 LGEJV to obtain Schedule for the Permanent Road along Villa Palao Road towards
CP S-07 site.
Location of Alternative LGICT Access Road NSCR CP S-07
CP S-07(Depot)
CP S-06 CP S-06
LGICT
Security Point 2
Security Point 5
Security Point 1 Unpaved Road (L=532m)
Security Point 3
Stabilized Road (L=900m)
Security Point 4
CP S-07 (Depot)
○ Date : 14-Sep-2023
○ Request Item
LGICT
Site Lay-out Plan (Detailed Drawing for Interface Section) NSCR CP S-07
CP
S-0
6B
oun
dar
Pi e
12
y
M
r-1
18
5
4M
10.
CP S-07 (Depot)
M
CP S-07 Fence 50
4M
10.
Pie
r-1
18
6
CP
S- 0
6F
LGICT
en c
e
Site Lay-out Plan (Photo for Interface Section) NSCR CP S-07
Site Lay-out Plan (Photo for Interface Section) NSCR CP S-07
Site Lay-out Plan (Detailed Plan for Interface Section) NSCR CP S-07
L=50M
RC PIPE
① LEFT SIDE
Base Course (300mm)
② RIGHT SIDE
Embankment
RC Pipe (Depth Varies)
LGICT
CP S-07 (Depot)
2023
Oc t o b e r No v e m b e r
De s c r i p t i o n Re m a rk
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2
D+ 1 D+ 2 D+ 3 D+ 4 D+ 5 D+ 6 D+ 7 D+ 8 D+ 9 D+ 10 D+ 11 D+ 12 D+ 13 D+ 14 D+ 15 D+ 16 D+ 17 D+ 18 D+ 19 D+ 20 D+ 21 D+ 22 D+ 23 D+ 24
E x c a v a t i o n ( De p e n d o n S i t e C o n d i t i o n ) E x c a v a t i o n ( De p e n d o n S i t e C o n d i t i o n )
P NR R a i l w a y
In s t a l l a t i o n G e o t e x t i l e & R C p i p e E m b a n k m e n t & C o m p a c t i o n ( Ap p r o x i m a t e l y 2 . 5 m )
In t e r fa c e
S e c t io n
E m b a n k m e n t & C o m p a c t i o n ( Ap p r o x i m a t e l y 2 . 5 m ) T r i m m i n g &Le v e l i n g
Co n s t ru c t io n
S c h e d u le
T r i m m i n g &Le v e l i n g La y i n g &C o m p a c t i o n o f b a s e c o u r s e ( 3 0 0 m m )
La y i n g &C o m p a c t i o n o f b a s e c o u r s e ( 3 0 0 m m )
Site Photo NSCR CP S-07
1
3
2
1
2 3
Item for Discussion NSCR CP S-07
2. Period of Use
4. Safety and Site Security between the 2 packages (CP S-07 & CP S-06)
6. Other matters