Professional Documents
Culture Documents
FX Risk Case Studies Consolidated 31may2021 Final
FX Risk Case Studies Consolidated 31may2021 Final
FX Risk Case Studies Consolidated 31may2021 Final
3
Line 4 (yellow) of São Paulo Subway
Context Problem Innovation
• Executed on November 29, 2006, Line 4 was • Direct payments from the State of São • To mitigate FX risk arising from mismatch between
the first PPP (public private-partnership) in Paulo and tariff revenues are
Brazil debt service on IDB financing and local currency
Brazil, in a strict sense, i.e, governed by Law denominated in Brazilian currency and revenues of the project, a relevant portion of such FX
11,079 of 2004 and thus relying on some level indexed to local inflation risk is objectively allocated to the Granting Authority
of financial contribution of the Granting Authority
2 (the State of São Paulo), as opposed to the • Nevertheless, debt service on IDB • Objective risk allocation was an innovation of the then
more traditional common concessions (relying financing was denominated in US new PPP legislation. Such objective allocation is
Line 4 of São Paulo solely on tariffs from end-users) dollars. IDB finance to the automatic and does not require a long and less
Subway concessionaire consisted originally of a predictable contractual revision process which would
• Such PPP was based on the sponsored USD 128.9 million A-loan, combined necessarily result from the traditional economic
modality, pursuant to which the concessionaire with a USD 213.2 million B-loan equilibrium rebalancing doctrine
Innovation Type: is entitled to direct payments from the
FX Risk partially and government, complementing revenues derived • At that time, as the first PPP project and • Section 12.3.1 of the Concession Agreement
objectively allocated to from tariff collected from end-users the first private concession of a subway expressly attributes to the Granting Authority the risk
Granting Authority,
under the relevant
line in Brazil, local sources of financing of “variations in the foreign exchange rate of the
• With a stated value of BRL 790 million at the were not available at an affordable cost. Brazilian Reais against the US Dollar, which may
Concession Agreement time of its execution, and an original term of 30 IDB had international experience on cause an impact in the payment of foreign currency
years, it was also one of the first private financing other subway lines, had
concession of subway lines in Brazil (*). debt”, within the limits and conditions set forth in the
Useful Links: already helped the State of São Paulo Agreement. The FX Impact must be demonstrated by
Concessionaire was responsible for providing on prior phases of the project and was
ViaQuatro
the rolling stock, relevant systems, and the the presentation of an opinion of a qualified auditor.
IDB Info committed to support the PPP The agreement also provides for additional conditions
operation of the line. State of São Paulo
remained responsible for the excavation and for the recognition of the Concessionaire right to
claim for the rebalancing of the agreement
construction works Timeline
Stakeholders Involved May December November May May
2004 2004 2006 2008 2010
• CCR, the controlling shareholder of Via Quatro, the
concessionaire of Line 4.
• State of São Paulo, as the Granting Authority
• Companhia do Metrô de São Paulo, the state-owned Enactment of Enactment of Execution of Approval of Commercial operation
company of the State of São Paulo responsible for the the São Paulo the Federal the PPP IDB of the first segment:
operation of the other lines in the São Paulo subway system State PPP Law PPP Law Contract financing Faria Lima - Paulista
• IDB, as the main lender for the project, on an A-B Loan 4
(*) MetrôRio was, in 1998, the first private concession of a subway line in Brazil.
structure
Line 4 (yellow) of São Paulo Subway
Brazil
Results/Impact
2
Results/Impact
Brazil
• Atlas Renewable Energy is • Atlas is an international developer and • Following a 2019 law that reinforced the right of companies
Brazil developing the 187MWp wanted to access international funding for to freely allocate risks in contracts entered between
Jacarandá Solar Project, in the the project themselves (the Economic Freedom Law), and a general
Municipality of Juazeiro, State of recognition that certain offtakers (e.g. exporters) may also
4 • However, power generation projects in benefit from US dollar indexation in their long term
Bahia
Brazil generate Brazilian currency contracts (as corroborated by several bills of law in that
• It will count with 450 solar revenues, usually indexed to local inflation direction), Atlas and its offtaker relied on an interpretation
Jacaranda Solar
Power (Atlas) modules and produce sufficient (IPCA) of existing legislation (Section 2, V, of Decree-Law 857/69),
Project power to meet the nees of a city to conclude that, on certain conditions, it would be
of 750,000 inhabitants • PPAs to supply power to the captive permissible for their PPA to remain denominated and
market, through distribution utilities, must payable in Brazilian currency, but indexed to US dollar FX
• The project required financing of follow standardized terms, set forth by the variation
Innovation Type: approximately USD 70 million for Government/ regulator (the so-called
PPA long term revenues regulated market), without flexibility for • In the case of Jacarandá project, there were several
were indexed to US
its implementation
adjustments elements of connection to justify the US dollar indexation
Dollar
(project finance all in dollars, foreign sponsor, offtaker an
• PPAs to large consumers (the free market) exporter and subsidiary of foreign company etc.)
may be negotiated between the parties, but
the market has traditionally interpreted • There are at least 3 bills of law in advance stages of
Useful Links: Brazilian laws as prohibiting foreign legislative process aiming at, among other purposes,
Project Website currency indexation in contracts between expressly clarifying the possibility of such foreign currency
IDB Info Brazilian parties indexation in long term energy or infrastructure related
agreements with exporters
Stakeholders Involved
Timeline
• Atlas Renewable Energy, the sponsor
• Jacarandá Solar Complex, formed by 4 generation plants 2017 June 2020 October 2020 February 2021
called Juazeiro V, VI, VII and VIII
• BID Invest, acting as project lender, and manager of the
Clean Technology Fund and Canadian Climate Fund
• DNB Bank ASA from Norway, acted as co-lender Execution of Execution of USD
Launching of Installation of
• A Brazilian subsidiary of Down Inc., as the offtaker Altas Renewable 15-year PPP 67 million 14.8y
first trackers 8
Contract Project Financing
Jacaranda Solar Power (Atlas) Project
Brazil
9
RenovAr Program – Chubut Norte III y Chubut Norte IV Wind Farm
Context Problem Innovation
Argentina • The program launched in 2015 • The Chubut project secured a USD 131 million financing agreement
aims to shift the source of 20% of • Difficult scenario in terms of
foreign investment, due to with KfW bank
the energy consumed in Argentina
5 to renewable sources until 2025, by macro-economic conditions
which entail high levels of • The bankability of the projects within the scope of the RenovAr
promoting renewable projects Program was strengthened by several key features, of which we
necessary to produce 1.2GW per institutional risk, currency
fluctuations, and sovereign debt highlight the following:
RenovAr Program – year
risk • PPA tariffs in US dollars, but payable in local currency (ARS)
Chubut Norte III and
Chubut Norte IV • RenovAr was designed to mitigate • Compensation triggered by payment default or convertibility
Wind Farm relevant risks faced by investors in • Currency devaluation,
international monetary defaults, restrictions in the form of a put option granted by the
renewable energy projects
and strict regulations to deal Government of Argentina and payable out of a pre-funded
Innovation Type: • Wind farms Chubut Norte III (57.66 with FX risk have been common liquidity and guarantee fund (FODER)
Financial structuring - MW) and Chubut Norte IV (83 MW) occurrences in Argentina, thus • Optional World Bank guarantees in the event that the above-
PPA long term revenues affecting potential investments
developed in the scope of round 2 mentioned compensation is not paid or in the event of
indexed to USD
of the program came into operation inconvertibility or non-transferability
in 2021 with the capacity to
annually produce 669,100 MWh of • State-owned company, CAMMESA, acts as offtaker under PPAs,
energy supplied to the Argentine being therefore responsible for the acquisition of the generated
Useful Links:
RenovAr Info Interconnection System (SADI) energy and the sale and distribution of the energy to the consumers
Genneia Info (in pesos)
IFC Report Stakeholders Involved
• FODER is responsible for mitigating liquidity and offtaker credit risks
• Genneia and Pan American Energy (sponsors)
•
by providing guarantees and direct financing for the projects
Government of Argentina (granting authority and
responsible for the program) Timeline
• Fondo para el Desarrollo de Energias Renovables - July October August February
FODER (guarantor and financing provider within 2015 2016 2016 2017 2021
RenovAr generally)
• Compañía Administradora del Mercado Mayorista
Eléctrico – CAMMESA (offtaker)
• World Bank (guarantor) RenovAr is Chubut Norte III and IV 10
• KfW (lender) Round 1 Round 1.5 Round 2
launched commercial operation
RenovAr Program – Chubut Norte III y Chubut Norte IV Wind Farm
Argentina
11
Road Interconnection Concession: Vial Santiago –
Valparaíso – Viña del Mar, Route 68
Innovation
Chile Context Problem
• As one of the first and most relevant PPPs in Chile, the
• The Santiago-Valparaíso-Viña Del • Direct payments from the Government
6 project financing was structured through a bond issuance
Mar toll road project consists of the of Chile and tariff revenues are
with an innovative “multilateral wrap” model with IDB
construction and operation and denominated in Chilean peso and
maintenance of a total of 141.36 km, indexed to local inflation • This was the first cooperation of a multilateral institution
Vial Santiago –
Valparaíso – Viña del
contemplating 4 tunnels, 16 bridges, with a private monoline insurer. IDB was the guarantor of
22 interchanges and 14 crossings • At that time (late 90s), structuring and
Mar, Route 68 record before bondholders and Financial Security
and additional 19.6 km of rural financing of similar projects were
Assurance (FSA) co-guaranteed the remaining amount,
service streets especially challenging due to the lack
benefitting from IDB’s preferred creditor status. The
of long-term local funding and lack of
structure is analogous to IDB’s A/B loan structure
Innovation Type: • With an original term of 25 years, the long term foreign exchange hedging
FX Risk partially and concession favors the fluid instruments available • The issuance amounted to 11 million Unidades de
objectively allocated to transportation of cargo and Fomentos (UF) (USD 300 million equivalent). UF is a
Granting Authority, passengers and allows easy access • In addition, as the Concession System
under the relevant Deference unit readjusted to cover inflation
to the port of Valparaíso and other was only gaining initial traction, the
Concession Agreement project companies and
inner cities, also improving • A relevant portion of FX risk was objectively allocated to
accessibility to Gran Santiago concessionaires expected more the Granting Authority through a public insurance
governmental activity and support available at the time, to compensate the concessionaire
Useful Links: for the adverse impact on the debt service of
Project Page depreciation against the US dollar by more than 10%
IJGlobal Info relative to a rate locked in at the time of the debt
Stakeholders Involved placement
Timeline
• Sociedad Concesionaria Rutas del Pacífico S.A., as the
February May August April
concessionaire and its shareholders Vias Chile S.A. and
1998 1998 1999 2002
Abertis Autopistas Chile III SPA
• Government of Chile, the Ministry of Public Works, as the
Granting Authority
• IDB as guarantor
Economic Decree officially Beginning of Financial
• FSA as guarantor
Offers Opening granting the the Concession Closure 12
Date Concession Term
Road Interconnection Concession: Vial Santiago –
Valparaíso – Viña del Mar, Route 68
Chile
Results/Impact
Useful Links:
the Concessionaire, constituted as a joint venture composed of Timeline
Aéroports de Paris (45%), VINCI Airports (40%) and Italy’s
Project Page December
InfraPPP Info Astaldi (15%). March October July
• Government of Chile, the Ministry of Public Works, as the 2015 2015 2016 2022
Concessionaire Annual
Report Granting Authority
• Santander Chile, Banco Bice, Banco de Crédito e
Inversiones, Itau Corpbanca, Penta Vida Compañía de
Seguros de Vida S.A., Seguros Vida Security Previsión S.A. Concession Beginning of Financial Estimated
was awarded the Concession Closing commercial
(local lenders)
Term operation 14
• Banca IMI, Credit Agricole, Societe Generale, Banco
Santander Spain and CaixaBank (foreign lenders)
Second Concession Arturo Merino
Benitez International Airport (Santiago)
Chile
7
Results/Impact Key lessons learnt
2nd Concession
Arturo Merino
Benitez Considering that Chile has been successful in
• In an important country as Chile, the modernization and
International Airport maintaining economic stability, with a very low volatility
(Santiago) expansion of its main International Airport offers huge
of its local currency, long term FX hedging is available
social and economic externalities. The investments
at feasible costs. Investors are also keener to face on
planned are aimed at the consolidation of an important
risks that would not be acceptable in other emerging
hub for pan-Pacific traffic
economies
Innovation Type:
FX Risk partially and • Expansion works are currently in progress
objectively allocated to Due to favorable macroeconomic conditions, private
Granting Authority, entities in projects structured in Chile usually mitigate
under the relevant their FX risks through the private banking market. In
Concession Agreement this specific case, the concessionaire entered into
derivatives agreements in order to protect itself from FX
risk and from variable interest and inflation variation
Useful Links:
Project Page
InfraPPP Info
Concessionaire Annual
Report
15
Pacífico 3 Toll Road 4G
Innovation
Context Problem
• 4 Generation PPPs resulted from an improved legal
Colombia • The project includes the improvement • Prior private investment initiatives had framework, starting with the creation of ANI, the National
and construction of 146km of roads as not accomplished great results in Infrastructure Agency
well as tunnels, bridges and viaducts, to Colombia due to inefficient institutional
8 connect the regions of Antioquia, Caldas, • Under 4G PPPs, risk is shared between public and private
framework, risk allocation and
and Risaralda. Following construction, parties. Once defined functional units of a toll road are
contractual structure completed, concessionaire shall be remunerated by a
the project will be operated by the
concessionaire for 25 years combination of tolls and payments by ANI (part of which may
Pacífico 3 Toll Road • The Government had limited financial be indexed to US dollars), including payments to mitigate
4G resources for the investments needed risks of construction and demand
• The Project is part of the first wave of and, thus, Colombia had to rely on
Colombia’s National Infrastructure private investment • In case of early termination, concession agreement secures
Innovation Type:
Agency 4G (Fourth Generation) program indemnity payment sufficient to pay outstanding debt
Improved PPP
Framework,
under PPP scheme, which aimed to build • Due to the limited capacity of local
Project financing – or expand 8,000 km of roads investors, the 4G Program had to be • The financing structure used in this project (total of
Issuance of bonds attractive for foreign investments as well approximately USD 650 million) included a USD 260 million
internationally and 144A/Reg S note, which was the first overseas bond for a
FDN credit • An increased sector-concentration and Colombian toll road
enhancement emerging regulations restricted
• The complete multi-tranche, dual-currency, hybrid financing
commercial banks’ capabilities to provide
package includes three separate loan tranches along with a
the financing for infrastructure projects credit enhancement facility provided by Financiera de
Useful Links:
Stakeholders Involved
Desarrolo Nacional (FDN), a Colombian state-owned
GIHub Info economic development bank
Bonds&Loans Case Study
• FDN - Financiera de Desarrolo Nacional
S.A. (state-owned development bank,
• The introduction of the FDN was one of the main institutional
lender) Timeline innovations. FDN grants subordinated loans and liquidity
• ANI – National Infrastructure Agency guarantees, and at the same time may finance the
(Granting Authority) September February structuration of projects and advice regional governmental
• Conexión Pacifico Tres S.A.S. 2014 2016 Apr 2020 entities
(concessionaire)
• MHC Constructora, Meco, El Condor (as • Although revenues of the project were in local currency, based
shareholders/ sponsors) on the overall structure, risk sharing and credit enhancement
Date of Completion of of FDN, foreign investors buying USD denominated notes
• Goldman Sachs (book runner for bonds) Concession Tesalia Tunnel
financial were willing to absorb FX risk 16
was awarded closing drive
Pacífico 3 Toll Road 4G
Colombia
Key lessons learnt
8
Results/Impact
17
Bogota Line 1 PPP Project
Innovation
Context Problem
• Empresa Metro de Bogota awarded a single concession for the
Colombia • The project seeks to improve access • The Project is too big for a private construction of civil works, rolling stock and railway systems, as well
to jobs and quality transit for public concessionaire to finance its full as its partial financing, operation and long-term maintenance
9 transport users in the area of construction cost, but Government
influence of the Metro Line of Colombia needs an • The Concessionaire was responsible for financing only USD 1.1 billion
experienced private out of total project costs. The difference will be financed by EMB itself
• It will stretch over 24km, and include concessionaire to undertake and then paid to the concessionaire throughout the construction phase
the construction of 15 stations and overall construction, operation and (a portion of which in US dollars)
Bogota Line 1 PPP acquisition of 23 trains each able to
Project
maintenance with required • The Colombian Government is providing most of the funding to EMB.
carry 1,800 passengers, with a efficiency Nevertheless, EMB will also resort to project finance from IDB, IBRD
maximum capacity of 72,000 and the European Investment Bank (EIB) amounting to around
passengers per hour • Segregation of the project in USD 1.7 billion (guaranteed by the Republic of Colombia)
Innovation Type: different concessions could
Combination of • Bogota Line 1 PPP Project is the jeopardize the coordinated and • The multilateral loans are intended to cover initial costs of the project.
public and private largest infrastructure project ever integrated development of the Given the mismatch between multilateral financing ( in USD) and
financing, and undertaken in Colombia, with a total project project revenue (in COP), the parties resorted to hedging mechanisms
appropriate risk
construction cost in excess of put in place to prevent Empresa Metro de Bogota from taking
sharing between
state owned USD 4.3 billion devaluation risk. Multilaterals helped borrower to access currency
company and swaps in a more efficient manner
concessionaire Stakeholders Involved • More recently, in July 2020, Empresa Metro de Bogota issued COP-
denominated bonds on the Colombia stock exchange as part of its
• China Harbour Engineering Company (sponsor, leader of the finance package for construction phase. The 23-year bonds are
APCA Transmimetro Consortium, awarded with the concession) Timeline guaranteed by the Government and were designed as a new type of
Useful Links:
• Xian Metro Company (sponsor) local bond, denominated “títulos de pago por ejecución”
IJGlobal Info
The Asset Info • Bombardier (subcontractor)
World Bank Report • European Investment Bank (EIB) August October
Bond Issuance Info • Inter-American Development Bank (IDB) July 2020 2028
2018 2020
• International Bank for Reconstruction and Development
(IBRD)
• Government of Colombia
• Empresa Metro de Bogota (the borrower, a state-owned Loan approval from Expected
Beginning of Issuance of commercial 18
company in charge of implementing the project and its overall World Bank, IDB construction local bonds
and EIB operation.
oversight)
Bogota Line 1 PPP Project
Colombia
9
Results/Impact
Key lessons learnt
Bogota Line 1 PPP • The combination of financing to a state-owned company
Project and private financing, under a properly designed Multilateral financing for initial stages of the project was
concession structure, with appropriate risk sharing, used as a strategy by Empresa Metro de Bogota to
made it possible to develop the largest infrastructure demonstrate the project’s efficiency and attract
Innovation Type: project ever in Colombia commercial capital and private finance for the remaining
Combination of stages of implementation thereof
public and private • The multilaterals US dollar funds will be disbursed
financing, and between 2020-2025 and may result in around
appropriate risk USD 300 million being converted into COP annually,
sharing between reason why the Government of Colombia has asked the
state owned While large and complex projects may still need
multilaterals (IBRD, IBD and EIB) support in managing governmental funds and public financing, a
company and
concessionaire the cross-currency swap market combination of public and private financing, through
• This was the first project financed by EIB in Colombia, appropriate risk sharing between public and private
under its Climate Action and Environment Facility and parties, may secure the best of both words, in a true
Useful Links: aimed at promoting climate change mitigation by public private partnership
IJGlobal Info
fostering the use of public transport and helping to
The Asset Info
World Bank Report
reduce pollutant emissions
Bond Issuance Info
• Empresa Metro de Bogota intends to use those US
dollar based funds to make payments to the
Concessionaire which are associated with the acquisition
of rolling stock and imported equipment, thus mitigating
FX risk for all parties
19
Jegurupadu Combined Cycle Power Plant
Indonesia
11
Results/Impact Key lessons learnt
Jasa Marga Komodo • IDR 4 trillion (USD 295 million equivalent) raised in the Komodo bonds may be used for future infrastructure
Bonds issuance, with a coupon of 7,5%, 3 year maturity date financing, given the size of the investor pool and
(demand had in fact reached IDR 15 trillion) absence of currency risk for the issuer. Demand for
Komodo bonds may increase as US interest rates
Innovation Type: decline – investors are also cautious with the country’s
Financial Structuring - FX volatility and this concern is reflected in pricing
Local Currency Cross-
border Bond Project
Financing Komodo Bonds as a reliable source of financing that
may also be explored by other local companies, other
than SOEs. SOEs, however, are in a more privileged
position, due to their government backing and low
Useful Links: liquidity risk
Project Page
LSE Report on Komodo B Since Komodo bonds have been issued offshore, the
onds
additional cross-border withholding tax could present a
potential cost hindrance
25
Local currency financing at the sub-
national level in Mexico
Context Problem Innovation
Mexico
• Mexican sub-national governments faced • Upon use of the well-developed Mexican peso
• Such issues and constraints resulted in a
challenges in obtaining financing due to swap market, IBRD was able to efficiently provide
pricing structure for IBRD loans that was
12 various market conditions and regulations, Mexican peso financing to the Guanajuato State
unattractive to sub-nationals in Mexico
such as the requirement that states may for investment in the State plan which included
and an inefficient allocation of foreign
borrow exclusively in local currency from projects in the toll road and sanitation sectors
Local currency exchange exposure for the government.
local financial institutions and the spread
financing at the Domestic banks were essentially the only
sub-national level in charged by the local financial intermediary • The transaction was structured as follows:
sources of debt financing for sub-
Mexico (BANOBRAS) over the cost of funds from • When borrower submits request to withdraw
nationals
ultimate lender. The conditions thus funds, IBRD executes swap transactions with
resulted in an uncompetitive overall cost • IBRD wanted to create a mechanism to an international financial intermediary
efficiently provide Mexican peso financing • An initial exchange of USD into pesos is
• The financial intermediaries had
to Mexican sub-nationals at a competitive carried out under the swap transaction
Innovation Type: traditionally hedged FX risk through a
cost and, at the same time, reduce the
FX risk transferred to foreign exchange trust fund created by the • The peso amount is disbursed to
currency and interest rate risks to
the market, reducing the Ministry of Finance, which effectively BANOBRAS, which then services and
risks to borrower, BANOBRAS and the guarantor (the
concentrated all FX risk relating to foreign repays that disbursed amount in pesos
guarantor and final Government of Mexico)
currency borrowing by sub-nationals in the • Pricing shall depend on the price IBRD gets
beneficiary
hands of the federal government from the market
• BANOBRAS then adds its own lending
spread and passes the cost to the final
Timeline beneficiary (the sub-national government)
Useful Links:
World Bank Study Stakeholders Involved
Project Page June December
World Bank Report • International Bank for Reconstruction and Development 2004 2009
(IBRD) (lender)
• The Mexican peso loan (equivalent to USD 108 million) was The combination of financial products allowed the sub-
Local currency national government to obtain financing at an attractive
financing at the intended specifically for the Decentralized Infrastructure
Reform and Development Project by the government of the cost
sub-national level in
Mexico Guanajuato State
27
IIRSA Norte Toll Road
Innovation
• Upon completion of certain construction milestones, the
Peru Context Problem project receives CRPAOs (Certificados de
Reconocimiento de Derechos del Pago Anual por
13 • Peruvian government had an • The government faced a shortage Obras), which represent an unconditional and
ambitious plan to rejuvenate 955 km of financial resources to meet the irrevocable payment obligation of the Peruvian
of roads connecting the fluvial port of cost of the project due to its government. The CRPAOs were then used to back up
Yurimaguas with the Pacific port of reliance on the cyclical prices of project bonds issued on international markets to raise
Paita, aiming at promoting economic commodities capital for construction
IIRSA Norte Toll growth in remote areas of the country
Road • There were no local sources of • USD 60 million partial credit guarantee from IDB to back
• The project is also part of a wider plan long term financing available in the financial obligations of the Government under the
to better integrate infrastructure Peru for larger projects concession, including under the CRPAOs (IDB receiving
Innovation Type:
Project financing –
networks across South America, in a counter-guarantee from the Government)
Debt – bonds this case between Peru and Brazil • Thus, the government needed to
guaranteed by attract private investment to the • This was the first Peruvian company to raise financing
unconditional country’s road network via SEC Rule 144-A bonds, denominated in USD and
government payment governed by NY law. Buyers included US and European
obligation
bondholders
29
Rustenburg Water Services Trust (RWST)
Innovation
Context Problem
South Africa • First application of project finance structure in the water
• Expansion of mining operations in the • A lack of sufficient available sector in South Africa. The financing was in local currency
Rustenburg region in South Africa governmental funding for (ZAR), which itself was used as a mechanism to mitigate
14 eventually led to strong population improvement of the local water any currency risks associated with the project
growth and shortened the treated infrastructure
water capacity and availability – which • Private, commercial and public financing – under a
Rustenburg Water had long been constrained • Insufficient water capacity and special purpose vehicle (the RWST) – for improvement of
Services Trust balance the Rustenburg water and wastewater infrastructure. The
PPP • The inefficiency and lack of capacity establishment of a Trust, with revenues ring-fenced from
of the sewage treatment works in the the municipality and strong operating arrangements,
region led to pollution of the Bospoort provided comfort to the lenders. Public funds were used
Innovation Type: Dam mainly to help structure the transaction
Water efficiency
solutions, creditworthy • Use of non-potable treated sewage for industrial purposes
vehicle and strong with long-term offtake agreements with local mines, thus
revenue stream creating a strong revenue stream
South Africa
14
Results/Impact Key lessons learnt
31
Gautrain Rapid Rail Link PPP
Innovation
Context Problem
• The South African Government funded 50% of the
South Africa • The development of the high-speed • Variable interest and foreign exchange development costs of the project and the remainder of
80 km-long rail link project results rates the costs were funded through, among others,
15 from local needs in reducing traffic provincial borrowings, private sector equity and private
congestion, increasing environmental • 28% of development period costs were sector borrowings (including IFC, the African
sustainability and creation of denominated in foreign currency and Development Bank and commercial banks).
employment opportunities hedging costs in connection therewith
were high • During the development phase, payments by the
Gautrain Rapid Government were partially indexed in foreign currency
Rail Link PPP • The transportation demand relating
the 2010 World Cup held in South • National Governmental guidelines – other than for the portion of the private party’s costs
Africa also contributed to the inception provided for denomination of costs in for which local content was required. For such
purposes, in the financial modeling for the project,
Innovation Type: and development of the project local currency
foreign denominated costs were converted by the
Financing structure – granting authority into local currency at a spot rate in
Alternate allocation of FX • The PPP scheme included a 19.5-
2006. FX rates were then fixed until 2011. The National
risk in different project year contract for the construction, Treasury acted as a currency swap counterparty to the
stages operation and maintenance of the Gauteng province, eliminating the additional cost for
Gautrain currency hedging.
Useful Links: Stakeholders Involved • During the Operational Period, FX hedging costs were
Gautrain Management Ag undertaken by the concessionaire.
ency - Case Study
IFC Info • Bombela Concession Company (Pty) Ltd
Gautrain Management Ag (concessionaire) Timeline
ency – 2019/2020 Annual
Report • Gauteng Provincial Government (granting authority,
Centre for Public Impact public partner in the PPP)
• National Treasury and National Treasury 2005 2006 2012 2012-2027
Department of Transport (main financiers)
• Gautrain Management Agency (special agency
created to manage, coordinate and oversee the
Project was Necessary Formal end of
Gautrain Project during the Operational Period) Operational
approved by the federal funding construction
• IFC, African Development Bank and commercial Period
government was approved 32
banks (lenders)
Gautrain Rapid Rail Link PPP
South Africa
15
Results/Impact Key lessons learnt
Gautrain Rapid
Anticipation of future needs and risks relating to the
Rail Link PPP • Creation of the first state-of-the-art Rapid Rail Link project by preparing a financial model design which
project in Africa, which contributed to social-economic accurately indicates allocation of the project’s funds is
growth by creating jobs and enabling economic paramount to ensure the success of a project.
Innovation Type: empowerment.
Financing structure –
Alternate allocation of FX • Increase in tourism-related revenues, due to the Private financing in joint efforts with public
risk in different project sectors/authorities was key to obtaining financing and
stages transportation availability, in the Gauteng Region.
properly mitigating project risks, such as FX risk, which
• The Gautrain has met its main objectives and by 2015 was undertaken both by public and private contracting
(i) there were nearly 60,000 daily individual journeys parties in alternate periods of the project. The definition
Useful Links:
Gautrain Management Ag and the number of journeys exceeded 1.4 million per of clear dispute solution mechanisms was also important
ency - Case Study month; (ii) it was estimated to have replaced about to maintain the cooperation and joint efforts between
IFC Info 21,300 daily car trips, thus reducing their carbon public and private parties.
Gautrain Management Ag
ency – 2019/2020 Annual footprint by 52% per trip; and (iii) more than 4,600 local
Report jobs had been created and retained from 2000 to 2015. Projects can benefit from strong political support and
Centre for Public Impact
commitment from the government. The South African
Government, in this case, provided a great part of the
funding and acted as an important agent in mitigating
key project risks, such as variation in foreign exchange
rates.
33
Başakşehir Çam & Sakura City Hospital PPP Project (also
known as Ikitelli Integrated Health Campus) Innovation
Turkey • JPY 163 billion (USD 1.5 billion equivalent) loan co-
Context Problem financed by JBIC and other Japanese financial institutions
(financing in Japanese currency)
16 • İkitelli Integrated Health Campus Project • The integrated campus required
is a PPP project designed to serve the experienced sponsors due its complex • JBIC provided political risk guarantee for part of the
European side of Istanbul and intended construction and operation features financing whereas NEXI provided insurance for the
to serve 60,000 visitors per day remaining part of the financing
Başsakşehir PPP • Revenues are in local currency and
• It involved the design, construction, • MIGA provided political risk insurance for the Sojitz
Project include (i) quarterly availability
Corporation subsidiary investing in the project (Sojitz
financing and operation of a health payments from the Ministry of Health; Hospital PPP Investment B.V.)
campus, with an investment period of 3 (ii) monthly service payments; and (iii)
Innovation Type: years and operation period of 25 years commercial revenues, which the • In Turkish healthcare PPPs, FX risk is mitigated
Financial structuring – concessionaire is free to collect according to a very complex formula within the PPP
FX risk mitigated by • Core medical services and staff are agreement. In summary, the formula provides for a
comparison between FX provided by the Ministry of Health, but comparison between increase in inflation vs. increase in
rate and inflation. the concessionaire provides foreign currency
maintenance and operation services
• Therefore, if there is an increase in exchange rate that is
• The project was a cooperation between higher than the increase in inflation, the difference is
the Turkish and Japanese governments reflected in an increase to the availability payment and
and private investors the opposite is true as well. However, the availability
Useful Links: payment shall never be higher than the cap nor lower
Ikitelli – SPV Website than the floor (both of which are also determined in the
JBIC Information agreement)
Stakeholders Involved Timeline
MIGA Information
Sojitz Information • Rönesans Healthcare (sponsor)
• Sojitz Corporation (sponsor) January July May
• Japanese Bank for International Cooperation (JBIC) 2016 2017 2020
(lender)
• Nippon Export and Investment (NEXI) (insurance provider)
• World Bank’s Multilateral Insurance Guarantee Agency
Agreement signed between Financial Official
(MIGA) (insurance provider)
the project company and the closing inauguration 34
Ministry of Health
Başakşehir Çam & Sakura City Hospital PPP Project
(also known as Ikitelli Integrated Health Campus)
Turkey
16
Results/Impact
Key lessons learnt
Başsakşehir PPP • The project was awarded with Thomson Reuters “PPP
Project The FX mitigation mechanism allows the projects to
Deal of the Year” and was the first hospital PPP remain bankable while also providing more long-term
supported by Japanese companies and JBIC sustainability and financial health, which has enabled
Innovation Type: the government to attract many foreign investors to
Financial structuring – • Part of the hospital complex opened early, in April
the country’s healthcare PPP sector
FX risk mitigated by 2020, given the rising number of COVID-19 patients in
comparison between FX Istanbul
rate and inflation. The Turkish Treasury has been closely monitoring the
• The USD 1.8 billion landmark PPP project is projects and preparing budgetary and financing
recognized as the world’s largest seismically isolated reports so as to constantly monitor risk exposure
building, with over 2,000 seismic isolators stemming from the PPP projects
35
Thank you
machadomeyer
globalinfrastructurehub