Professional Documents
Culture Documents
LOTO Refresher Training
LOTO Refresher Training
AND THINK!
What is ENERGY ????
WikipediA defines energy as: The ability to do work
What forms of energy can you think of that allow work to
be performed or becomes a HAZARD if released?
Unforeseen Hazard
F a t a lit y
This incident demonstrates what can happen to anyone entering an unsafe environment that is
not under control. The following description is what is believed to have taken place, as no formal
investigation report has been released.
The area around the pressure test had not been identified in
any way: there were no barricades, no warning signs, no
standby person keeping watch to warn passers-by, also, there
had been no general warning of any testing taking place.
TO BE FILLED OUT BY ACP (CHARGEMAN) WHEN ELECTRICAL ISOLATION IS REQUIRED AND BEFORE JOB STARTS
BREAKER No./ LOCATION OPEN / DEENERGISED CLOSED / ENERGISED TAG No LOCK No
12
PIC (backside)
• The Chargeman records the breaker location, isolation
status and tag and lock number on PIC.
TO BE FILLED OUT BY ACP (CHARGEMAN) WHEN ELECTRICAL ISOLATION IS REQUIRED AND BEFORE JOB STARTS
BREAKER No./ LOCATION OPEN / DEENERGISED CLOSED / ENERGISED TAG No LOCK No
13
• After isolation Lock and Tag in the
substation the AAR must conduct the Clear
and Try test in the field (Bump Test). Try to
start the equipment to confirm correct
isolation.
• Our OPU practice is for the Chargeman to
witness the Clear and Try test.
ELECTRICAL ISOLATION
STEP 3 IN THE FIELD
• Operations will prepare the equipment to
ensure it is safe to work on.
• Zero Energy State
• Flushed and drained of toxic and
other hazardous material as per SOP.
EQUIPMENT PREPARATION
STEP 4 IN THE FIELD
• Under the new LOTO system, Operations
will be the only discipline to hang locks and
tags at the field energy isolation points.
• The Group Lock System will be used by
operations for this task.
17
Group Locks
EACH GROUP OF LOCKS HAS A
GROUP NUMBER AND LOCK NUMBER
18
Group Locks
19
Group Locks
• WHEN NOT BEING USED,
THE LOCKS AND KEY
SHALL BE KEPT INSIDE
THE CORRESPONDING
LOCKOUT BOX.
• EACH GROUP OF LOCKS
IN OPERATIONS
DEPARTMENTS (ET UOM &
PE) HAS 10
LOCKS/GROUP.
• ET HAS 20 GROUPS OF
LOCKS IDENTIFIED AS
“ET G1-20 L1-10”
• PE HAS 20 GROUPS OF
LOCKS IDENTIFIED AS
“PE G1-20 L1-10
• WE HAVE 5 DIFFERENT
COLOURS FOR THE LOCK
GROUPS TO HELP WITH
IDENTIFICATION.
Group Locks
Lockout:
When lockout of equipment is required the required number of
locks are removed from a lockout box together with the key and
are used to secure the energy isolating devices i.e. valves,
electrical breaker etc..
Locking Device
21
Group Locks
Lockout:
If the equipment requires more than the 10 locks available in one
group then several groups may be used depending on the number
of isolation points requiring locks.
22
Lockout Box
• AFTER ISOLATION OF THE
EQUIPMENT THE KEY FOR THE
GROUP LOCKS IS PLACED INSIDE
THE LOCKOUT BOX.
• IF MORE THAN ONE GRUP OF LOCKS
ARE USED THEN THE KEYS FOR
EACH GROUP ARE ALL PLACED IN
THE SAME LOCKOUT BOX.
• THE KEY FOR LOCKS USED BY THE
CHARGEMAN FOR ELECTRICAL
ISOLATION ARE ALSO PLACED
INSIDE THE LOCKOUT BOX
• THE LOCKOUT BOX IS THEN LOCKED
BY THE SS WITH AN OPERATIONS
DEPARTMENT LOCK
• WHEN THE RA APPLIES FOR A PTW
TO WORK ON THE EQUIPMENT HE
PUTS HIS DEPARTMENT LOCK ON
THE LOCKOUT BOX.
23
Department Locks
• THESE LOCKS ARE
KEY DIFFERENT.
EACH LOCK HAS
AN INDIVIDUAL
KEY.
• THEY ARE ISSUED
TO EACH
DEPARTMENT IN
EPEMSB
• THEY ARE USED BY
THE AA AND RA TO
LOCK THE DOOR
ON THE LOCOUT
BOX.
• EACH LOCK IS
ENGRAVED WITH
THE DEPARTMENT
ID & LOCK
NUMBER.
Department Lock ID
Department Quantity Labeling / Engraving Details
ET Operations 22 ET D1 inclusive to ET D22
UOM Operations 17 UO D1 inclusive to UO D17
PE Polymer 22 PEP D1 inclusive to PEP D22
PE Compounding 17 PEC D1 inclusive to PEC D17
Central Lab 4 CL D1 inclusive to CL D4
Technical Services Lab 4 TSL D1 inclusive to TSL D4
Admin Department 2 AD D1 inclusive to AD D2
Warehouse 2 WH D1 inclusive to WH D2
Engineering Department 2 ENG D1 inclusive to ENG D2
Engineering Services 12 EnS D1 inclusive to EnS D12
Mechanical 28 MEC D1 inclusive to MEC D28
Instrument 12 INST D1 inclusive to INST D12
Electrical Maintenance 10 EL D1 inclusive to EL D10
Inspection 13 INSP D1 inclusive to INSP D13
PE Technical 10 PET D1 inclusive to PET D10
ET Technical 10 ETT D1 inclusive to ETT D10
RPO 10 RPO D1 inclusive to RPO D10
Lockout Box
• THE LOCKOUT ET
BOXES ARE SET UP UOM
IN THE PTW ISSUE
AREA.
• THESE CABINETS
ALSO HAVE
STORAGE FOR THE
TAGS AND A
SECURE PLACE
FOR THE
DEPARTMENT
LOCKS AND KEYS
26
TAGS
• THE LOCKOUT
BOXES CABINETS
HAVE STORAGE
FOR THE TAGS
27
TAGS
• Blue (plastic) –
Operations
• Red (plastic) –
Chargeman
• Brown (paper) –
Common disposable
tag used at Lockout
Box
• Green (paper) –
Spade/blind
• Yellow (plastic) –
Ionizing Radiation
28
TAGS
• Blue Operations tags
are placed at all
isolation points i.e.
valves, breakers, stop
button etc
• Red Chargeman tags
are placed at breaker
by the Chargeman
• Brown tags are used at
Lockout Box by AA & RA
• Green tags are placed at
blind locations by
Operations.
• Yellow tags are placed at
Ionizing Radiation device
locations by RPO
29
• The new PIC will replace the existing
Mastercard.
32
PIC (backside)
• Additional information is required on the backside. Who
installed the lock and tag, the date and also who
removed the isolation and date.
• REMINDER
Blind tag
PHYSICAL ISOLATION CERTIFICATE
NO WORK IS SO URGENT THAT WE CANNOT TAKE TIME TO DO IT SAFELY
OPEN /
EPEMSB
Page 2 of 2
(GREEN)
numbers must
CLOSED /
ISOLATION DEVICE LOCATION Deenergised OPS TAG NO Installed By: Date Installed Removed By Date Removed
Energised (tic)
(tic)
also be recorded
on the PIC by
AAR.
•The RA must
confirm positive
isolation by
removing the
perforated
TO BE FILLED OUT BY ACP (CHARGEMAN) WHEN ELECTRICAL ISOLATION IS REQUIRED AND BEFORE JOB STARTS
section from
each green tag
BREAKER No./ LOCATION OPEN / DEENERGISED CLOSED / ENERGISED TAG No LOCK No
and attaching
STOP WORK AND EVACUATE AREA ON HEARING OF EMERGENCY ALARM
Original PIC To Be Maintained and Displayed at the Control Room or Office Location Where the PTW is Issued
them to the PIC.
33
• Using the new PIC
35
• The EIC is issued for electrical return to
normal condition.
• Operations removes locks and tags from
field isolation devices
DE-ISOLATION
STEP 8 AT THE FIELD
• The 3 Special certificates are:???
• PIC, EIC & SSBOC
• The Safety System Bypass Override
Certificate has also been revised and needs
to be revalidated every week.
• Waiver available for extended long term
isolation for the Special Certificates.
CERTIFICATE
PTW No.:
EPEMSB NO WORK IS SO URGENT THAT WE CANNOT TAKE TIME TO DO IT SAFELY
Others: …………………………………………
Unit Area / Facility :
main change to the Safety Integrity Level (SIL):……………………………….. (Note: No bypass is allowed for SIL 4 Safety System)
………………………………………………………………………………………………………………………………………………………………………… ………………………………………
………………………………………………………………………………………………………………………………………………………………………… ………………………………………
………………………………………………………………………………………………………………………………………………………………………… ………………………………………
………………………………………………………………………………………………………………………………………………………………………… ………………………………………
Method of Bypass / Override
revalidation section.
Physical Isolation Hardwire Jumper Temporary Change Setting Temporary Remove Setting Key Activation
………………………………………………………………………………………………………
2. Copy No 1: posted in the Control Room
………………………………………………………………………………………………………
revalidated every
I shall implement all precautions as specified above before work starts
SECTION 4: APPROVAL
week by the AA
This applicant is authorised to proceed with the Safety System Bypass / Override described above
SECTION 5: WEEKLY REVALIDATION (Requirement for long term isolat ion to be reviewed daily/every shift by AA )
Week 2 3 4 5 6 7 8 9 10 11 12
AA Name
Signature
Date
The above Safety System Bypass / Override is no longer required. The Bypass / Override has been removed and system is
back to normal.
Endorsed by Receiving Authority Endorsed by Approving Authority
38
Special Certificate Waiver
place a Waiver that I hereby grant special authorisation that the following equipment:
may be applied in be allowed to remain in extended isolation without weekly revalidation and renewal of the Special
Certificate.
The Special Certificates are identified in GQP-HSE-014 Permit to Work Procedure, are either of
remain in effect
Manager
Endorsed by AA
Endorsed by Chargeman
beyond the 12
(as required)
Approval by GM
week period. It is
Confirmed this authorisation is cancelled due to :
Expiry of validity period. This Authorisation is replaced.
Work resume. New Special Certificate is issued.
such as equipment
Endorsed by AA
Endorsed by Chargeman
(as required)
awaiting
Approval by GM
Note: This special dispensation of the normal stipulations outlined in the Permit to Work Procedure is
decommissioning
applicable only when justifiable reasons can be given to support the long term isolation such as mothballing
or equipment awaiting decommissioning.
39
Roles & Responsibilities (1/4)
Approving Authority (AA):
• approving PTW for modification and/or maintenance
work on equipment or systems where energy
isolation is required. PTW application must be in
place before the EIC is issued
• ensure that the Job Method Statement JSA is
available.
• assessing the hazard associated with the work and
recommend control measures.
• ensure only trained and competent personnel
perform the preparation and isolation activities.
40
Roles & Responsibilities (2/4)
Approving Authority Representative (AAR):
• Appointed by the Approving Authority to prepare
and isolate the equipment.
• May also be instructed to install any lockout devices
and tags under the supervision of the Approving
Authority.
• Shall be competent to operate the equipment and
understand the process / system being isolated.
41
Roles & Responsibilities (3/4)
Receiving Authority (RA):
• Responsible for supervising the maintenance
activities
• Ensures that the system or equipment being
worked on has been safely isolated and
disabled with proper lockout and tags.
• Accepts the PTW issued for work to be carried
out under his supervision.
42
Roles & Responsibilities (4/4)
43
Special Case (1/2)
44
Special Case (1/2)
However, single valve isolations effected by instrument
technicians are NOT allowed under the following process
conditions:
Process fluid Pressure* Temperature*
45
Thank You
46