Overall RC Work Plan - Final - 송부용 - RE3
Overall RC Work Plan - Final - 송부용 - RE3
2020. 09
SEOBON
Contents
1. Preliminary
1) Sub-Contractor Introduction
2) Project Summary
3) Organization Chart
2. Logistic
3. Schedule
1) Overall Schedule
2) Manpower Schedule
3) Equipment Schedule
4) Manpower Plan per Zoning
4. Construction Plan
5. Q-HSE Management Plan
6. End
1) Sub-Contractor Introduction
1. Company’s Information
2. Project Introduction(Over sea Project)
1) Sub-Contractor Introduction
□ Company’s Information
COMPANY’s NAME
SEOBON Construction Co., Ltd.
Established (Year)
1995
President
Kwa Y, Lee
Employee
MANAGER(KOR) : 20
ENGINEER (KOR) : 70
INDIRECT STAFF(TCN) : 350
CONSTRUCTION WORKER(TCN) : 3,500
U.A.E
KUWAIT
LIBYA INDIA
Description : RC Work
[SUPERSTRUCTURE]
2. Logistic (Stock yard & office)
Area Information
PHASE-1
SEOBON OFFICE
PHASE-2
MAIN ACCESS
INTERNAL ACCESS
SEOBON STACK YARD
ACCESS TO BASEMENT
11
GROUND FLOOR LEFT WING ACCESS PLAN
2) Logistic
2) Stock yard & office
Hazrat Shahjalal International Airport Expansion Project (HSIA)
Stock yard & office Plan
Office area
Carpenter
shop
Rebar shop
12
3. Schedule
1. Overall Schedule
2. Manpower Schedule
3. Equipment Schedule
4. Manpower Plan per Zoning
3.Schedule
1) Overall Schedule
2020 2021 2022 REMARKS
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
1'st 2'nd 3'rd 4'th 5'th 6'th 7'th 8'th 9'th 10'th 11'th 12'th 13'th 14'th 15'th
Contract
Pile Caps & Capping Beams
Construction Plan
RC
Basement
Contract
UG, Column, Beam, Footing,
Retaining Wall, Pit
Construction Plan
Contract
Ground Floor Slab,
SOG ( Slab On Grade ) & etc.
Construction Plan
RC
Ground FL
GF Column, Wall, Contract
Suspended Beam & Slab,
Staircase Construction Plan
Contract
RC 1st Floor Column, Wall,
1st FL Suspended Beam & Slab, Staircase
Construction Plan
1 Pile Caps & Capping Beams Re-bar Fab. & Install. 785.52 ton 130.92 130.92 130.92 130.92 130.92 130.92 0.11(ton/m3)
2 Pile Caps & Capping Beams Form Works 7,613.00 m2 1,268.83 1,268.80 1,268.80 1,268.80 1,268.80 1,268.97 1.05(m2/m3)
3 Pile Caps & Capping Beams Con'c Casting 7,191.00 m3 1,198.50 1,198.50 1,198.50 1,198.50 1,198.50 1,198.50
4 UG, Column, Beam, Footing, Retaining Wall, Pit Re-bar Fab. & Install. 2,260.01 ton 376.67 376.67 376.67 376.67 376.67 376.66 0.22(ton/m3)
5 UG, Column, Beam, Footing, Retaining Wall, Pit Form Works 21,823.00 m2 3,637.17 3,637.17 3,637.17 3,637.17 3,637.17 3,637.15 2.12(m2/m3)
6 UG, Column, Beam, Footing, Retaining Wall, Pit Con'c Casting 10,282.20 m3 1,713.70 1,713.70 1,713.70 1,713.70 1,713.70 1,713.70
7 Ground Floor Slab, SOG ( Slab On Grade ) & etc. Re-bar Fab. & Install. 253.01 ton 42.17 42.17 42.17 42.17 42.17 42.16 0.04(ton/m3)
8 Ground Floor Slab, SOG ( Slab On Grade ) & etc. Form Works 3,630.00 m2 605.00 605.00 605.00 605.00 605.00 605.00 0.64(m2/m3)
9 Ground Floor Slab, SOG ( Slab On Grade ) & etc. Con'c Casting 5,635.00 m3 939.17 939.17 939.17 939.17 939.17 939.15
10 GF Column, Wall, Suspended Beam & Slab, Staircase Re-bar Fab. & Install. 2,643.61 ton 377.66 377.66 377.66 377.66 377.66 377.66 377.65 0.26(ton/m3)
11 GF Column, Wall, Suspended Beam & Slab, Staircase Form Works 28,958.60 m2 4,136.94 4,136.94 4,136.94 4,136.94 4,136.94 4,136.96 4,136.96 2.88(m2/m3)
12 GF Column, Wall, Suspended Beam & Slab, Staircase Con'c Casting 10,066.60 m3 1,438.09 1,438.09 1,438.09 1,438.09 1,438.09 1,438.09 1,438.06
13 1F Column, Wall, Suspended Beam & Slab, Staircase Re-bar Fab. & Install. 1,982.71 ton 283.24 283.24 283.24 283.24 283.24 283.24 283.27 0.26(ton/m3)
14 1F Column, Wall, Suspended Beam & Slab, Staircase Form Works 21,719.40 m2 3,102.77 3,102.77 3,102.77 3,102.77 3,102.77 3,102.77 3,102.78 2.88(m2/m3)
15 1F Column, Wall, Suspended Beam & Slab, Staircase Con'c Casting 7,550.00 m3 1,078.57 1,078.57 1,078.57 1,078.57 1,078.57 1,078.57 1,078.58
16 2F Column, Wall, Suspended Beam & Slab, Staircase & etc. Re-bar Fab. & Install. 375.36 ton 62.56 62.56 62.56 62.56 62.56 62.56 0.32(ton/m3)
17 2F Column, Wall, Suspended Beam & Slab, Staircase & etc. Form Works 4,424.00 m2 737.33 737.33 737.33 737.33 737.33 737.35 3.75(m2/m3)
18 2F Column, Wall, Suspended Beam & Slab, Staircase & etc. Con'c Casting 1,181.20 m3 196.87 196.87 196.87 196.87 196.87 196.85
Re-bar Fab. & Install. 8,300.22 ton 130.92 507.59 549.76 927.42 927.42 1,210.66 1,079.73 765.62 723.46 723.45 345.80 345.83 62.56 0.20(ton/m3)
Main Work Q`ty Form Works 88,168.00 m2 1,268.83 4,905.97 5,510.97 9,647.91 9,647.91 12,750.85 11,481.86 8,582.04 7,977.06 7,977.06 3,840.10 3,840.11 737.35 2.10(m2/m3)
Con'c Casting 41,906.00 m3 1,198.50 2,912.20 3,851.37 5,289.46 5,289.46 6,368.03 5,169.53 3,652.68 2,713.53 2,713.50 1,275.44 1,275.45 196.85
3.Schedule
2 Manpower Productivity and Schedule
Monthly Work Schedule As the Construction Quantities
SL.
Location Description Quantities Unit Remarks
No.
1'st 2'nd 3'rd 4'th 5'th 6'th 7'th 8'th 9'th 10'th 11'th 12'th 13'th
1 Pile Caps & Capping Beams Steel Fixer 251.76 man/day 41.96 41.96 41.96 41.96 41.96 41.96 0.12 ton/man*day
2 Pile Caps & Capping Beams Carpenter 195.19 man/day 32.53 32.53 32.53 32.53 32.53 32.54 1.5 m2/man*day
3 Pile Caps & Capping Beams Con'c Mason 184.38 man/day 30.73 30.73 30.73 30.73 30.73 30.73 1.5 m3/man*day
4 Pile Caps & Capping Beams Scaffolder 58.56 man/day 9.76 9.76 9.76 9.76 9.76 9.76
5 UG, Column, Beam, Footing, Retaining Wall, Pit Steel Fixer 579.48 man/day 96.58 96.58 96.58 96.58 96.58 96.58 0.15 ton/man*day
6 UG, Column, Beam, Footing, Retaining Wall, Pit Carpenter 419.70 man/day 69.95 69.95 69.95 69.95 69.95 69.95 2.0 m2/man*day
7 UG, Column, Beam, Footing, Retaining Wall, Pit Con'c Mason 197.76 man/day 32.96 32.96 32.96 32.96 32.96 32.96 2.0 m3/man*day
8 UG, Column, Beam, Footing, Retaining Wall, Pit Scaffolder 125.94 man/day 20.99 20.99 20.99 20.99 20.99 20.99
9 Ground Floor Slab, SOG ( Slab On Grade ) & etc. Steel Fixer 97.32 man/day 16.22 16.22 16.22 16.22 16.22 16.22 0.15 ton/man*day
10 Ground Floor Slab, SOG ( Slab On Grade ) & etc. Carpenter 93.06 man/day 15.51 15.51 15.51 15.51 15.51 15.51 1.5 m2/man*day
11 Ground Floor Slab, SOG ( Slab On Grade ) & etc. Con'c Mason 144.48 man/day 24.08 24.08 24.08 24.08 24.08 24.08 1.5 m3/man*day
12 Ground Floor Slab, SOG ( Slab On Grade ) & etc. Scaffolder 27.90 man/day 4.65 4.65 4.65 4.65 4.65 4.65
13 GF Column, Wall, Suspended Beam & Slab, Staircase Steel Fixer 847.28 man/day 121.04 121.04 121.04 121.04 121.04 121.04 121.04 0.12 ton/man*day
14 GF Column, Wall, Suspended Beam & Slab, Staircase Carpenter 556.92 man/day 79.56 79.56 79.56 79.56 79.56 79.56 79.56 2.0 m2/man*day
15 GF Column, Wall, Suspended Beam & Slab, Staircase Con'c Mason 258.09 man/day 36.87 36.87 36.87 36.87 36.87 36.87 36.87 1.5 m3/man*day
16 GF Column, Wall, Suspended Beam & Slab, Staircase Scaffolder 167.09 man/day 23.87 23.87 23.87 23.87 23.87 23.87 23.87
17 1F Column, Wall, Suspended Beam & Slab, Staircase Steel Fixer 635.47 man/day 90.78 90.78 90.78 90.78 90.78 90.78 90.79 0.12 ton/man*day
18 2F Column, Wall, Suspended Beam & Slab, Staircase Carpenter 417.69 man/day 59.67 59.67 59.67 59.67 59.67 59.67 59.67 2.0 m2/man*day
19 3F Column, Wall, Suspended Beam & Slab, Staircase Con'c Mason 193.62 man/day 27.66 27.66 27.66 27.66 27.66 27.66 27.66 1.5 m3/man*day
20 3F Column, Wall, Suspended Beam & Slab, Staircase Scaffolder 125.30 man/day 17.90 17.90 17.90 17.90 17.90 17.90 17.90
21 2F Column, Wall, Suspended Beam & Slab, Staircase & etc. Steel Fixer 96.24 man/day 16.04 16.04 16.04 16.04 16.04 16.04 0.15 ton/man*day
22 2F Column, Wall, Suspended Beam & Slab, Staircase & etc. Carpenter 85.08 man/day 14.18 14.18 14.18 14.18 14.18 14.18 2.0 m2/man*day
23 2F Column, Wall, Suspended Beam & Slab, Staircase & etc. Con'c Mason 30.30 man/day 5.05 5.05 5.05 5.05 5.05 5.05 1.5 m3/man*day
24 2F Column, Wall, Suspended Beam & Slab, Staircase & etc. Scaffolder 25.50 man/day 4.25 4.25 4.25 4.25 4.25 4.25
Steel Fixer 2,507.55 man/day 41.96 138.54 154.76 275.80 275.80 366.58 324.62 244.08 227.86 227.86 106.82 106.83 16.04
Carpenter 1,767.64 man/day 32.53 102.48 117.99 197.55 197.55 257.23 224.69 168.92 153.41 153.41 73.85 73.85 14.18
Manpower
Con'c Mason 1,008.63 man/day 30.73 63.69 87.77 124.64 124.64 152.30 121.57 93.66 69.58 69.58 32.71 32.71 5.05
Scaffolder 530.29 man/day 9.76 30.75 35.40 59.27 59.27 77.17 67.41 50.67 46.02 46.02 22.15 22.15 4.25
Manpower Sum. Total 5,814.11 man/day 114.98 335.46 395.92 657.26 657.26 853.28 738.29 557.33 496.87 496.87 235.53 235.54 39.52 Avg. 447 man/day
3.Schedule
3) Equipment Mobilization Schedule
Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21 Jul-21 Aug-21 Sep-21 Oct-21 Nov-21 Dec-21 Jan-22
1'st 2'nd 3'rd 4'th 5'th 6'th 7'th 8'th 9'th 10'th 11'th 12'th 13'th 14'th 15'th
SL.
NAME OF of EQUIPMENT SPEC. NO.
NO.
1 PICKWAY TRUCK 1
4 CRANE 50 TON 1
5 CRANE 50 TON 1
6 TRUCK 3 TON 2
7 PICK UP 1
8 FORKLIFT 10 TON 1
11 STATIONARY PUMP 1
15 GENERATOR 50KW 2
16 WELDING MACHINE 2
3.Schedule
4) Manpower Zoning Plan(Ground Floor & Basement) 1 team
Foreman : 3
Concrete : 15
4 Team Team Ground floor Carpenter : 15
2 Team Basement Re-bar Wrk : 40
Scaffolder :
LW ZONE 3
[GROUND FLOOR]
3.Schedule
4) Manpower Zoning Plan(First Floor) 1 team
Foreman : 3
Concrete : 10
4 Team, 16 Zone Carpenter :25
Re-bar Work : 25
Scaffolder : 10
LW ZONE 3
[FRIST FLOOR]
3.Schedule
4) Manpower Zoning Plan(2nd Floor) 1 team
Foreman : 3
Concrete : 10
3 Team, 15 Zone Carpenter : 25
Re-bar Wrk : 25
Scaffolder : 10
[2ND FLOOR]
4. Construction Plan
The Wall Form is consist of plywood(Thk.18), GTX (GI PIPE 2”), Prop jack
4.Construction Plan
3. Basement Roof Slab & Column
The Roof slab & Column Form is consist of plywood(Thk.18), GTX (2-4x4), an support (GI PIPE 2”),
For shoring cup lock scaffolding
4.Construction Plan
4. Slab and beam formwork
Supervisor
Supervisor &
& Foreman
Foreman Engineer
Engineer
Supervisor
Supervisor &
& Engineer
Engineer Manager
Manager
Minimize loss
5. Q-HSE Management Plan
Devise
Devise aa comprehensive
comprehensive plan
plan • In 3 months from the time starting work
• Framing of site management plan
Pre Quality
Quality management
management policy
policy and
and
working devise a test plan
devise a test plan
Devise
Devise aa work
work schedule
schedule • Framing by co-worker
• Examination & recognition of site manager
• Making a detail work plan
Devise
Devise aa quality
quality management
management plan
plan
• Making a check list by item
Work
Work by
by drawing
drawing // SPEC
SPEC • Self examination by co-worker
• Examination by section chief
On Co-worker
Co-worker guiding
guiding &
& test
test
• Before 1 month of completion inspection
working Internal
Internal completion
completion inspection
inspection • Quality management team of company
Correction
Correction • Completion
•According to Specification
INSPECTION •According to Method Statement
DOCUMENT •According to Inspection Testing Plan
•Daily report
PROGRESS •Weekly report
REPORT •Monthly report
•3Month report
32
5.Q-HSE Management Plan
3) HSE Conceptual Map
Achievement
Achievementnon-accident
non-accidentsite
site
33
5.Q-HSE Management Plan
4) HSE Education and Training
HSE Manager
Safety introduction for labors All labors Employment 1hour Project Manager
Project Manager
Regular education and train- All labors Monthly 2hours HSE manager
ing for labors Safety Supervisor
Education and training before All labors Before the work change 1hour HSE manager
the work change
Special safety education and All labors Before the dangerous work 2hours HSE manager
training Safety Supervisor
Rigger and scaffolder Skilled labors Before the dangerous work 1hour HSE manager
Safety Supervisor
Safety Supervisor
Tool-box Meeting All labors Before the work 15 minute Foreman
Related safety education and Before the work Safety Supervisor
training Related labors ( Height Work, Hot, etc ) 15 minute Foreman
34
5.Q-HSE Management Plan
5) Edge Protection & Access