M/S For RC Works_Rev01

[Passengers Terminal Building 3]

2020. 09

SEOBON
Contents
1. Preliminary
1) Sub-Contractor Introduction
2) Project Summary
3) Organization Chart
2. Logistic
3. Schedule
1) Overall Schedule
2) Manpower Schedule
3) Equipment Schedule
4) Manpower Plan per Zoning
4. Construction Plan
5. Q-HSE Management Plan
6. End
1) Sub-Contractor Introduction

1. Company’s Information
2. Project Introduction(Over sea Project)
1) Sub-Contractor Introduction
□ Company’s Information
COMPANY’s NAME
SEOBON Construction Co., Ltd.

Established (Year)
1995

President
Kwa Y, Lee

 Employee
MANAGER(KOR) : 20
ENGINEER (KOR) : 70
INDIRECT STAFF(TCN) : 350
CONSTRUCTION WORKER(TCN) : 3,500

 Main Business Areas


CIVIL WORK, BUILDING WORK, STEEL STRUCTURE & CLADDING WORK, CIVIL & MECHANICAL MAINTE-
NANCE WORKS, WASTE WATER TREATMENT
1) Sub-Contractor Introduction
□ Project Introduction(Overseas Project)

U.A.E

U.A.E. Abu-Dhabi Branch Office


ALGERIA # Green Diesel Project
# Ruwais Refinery Expansion Project #4
# Algeria Oman Fertilizer Project # Inter Refineries Pipeline-II (IRP-II) Project
# Shah Gas Development Project
# Inter Refineries Pipeline-II (IRP-II) Project
# Braka Nuclear Power Plant Proeject
# Ruwais Refinery Expansion Project #3
# Mirfa Independent Water & Power Project
# Rumaitha / Shanayel Facilities Phase III
Project PAKISTAN
# Lahore – Islamabad Motorway PJ

KUWAIT
LIBYA INDIA

# AGIP WLGP - WAFA Desert Project # Dhauliganga Hydroelectric Project Stage-01

# BENGHAZI North Combined


Cycle Power Plant OMAN
QATAR
# Oman Sohar Aromatics Project
# WAHA OIL COMPANY Projects
# Q-CHEM II Ethylene Derivatives Project
# Parachute Service Plant and # QAFCO-5 Project VENEZUELA
Para Commandos School # QAFCO-6 Project # Refinery Puerto La Cruz
Deep Conversion Project
# Misurata Combined Cycle
Power Plant NIGERIA
IRAQ # Nigeria Indorama Fertilizer Project SRI LANKA

# KARBALA REFINERY PROJECT Waterfront Intergated Resort


RC Work PKG1
2) Project Summary
2) Project Summary
Hazrat Shahjalal International Airport Expansion Project

Employer : Civil Aviation Authority, Bangladesh (CAAB)

Company : Aviation Dhaka Consortium (ADC)

Contractor : SAMSUNG C&T

Sub-Contractor : SEOBON Construction Co., Ltd.


SEOBON Construction Co.,
Ltd.

Project Location : Dhaka international Airport

Description : RC Work

No. ITEM UNIT Q’TY REMARKS

1 Re-Bar Fabrication & Installation Ton 8,300

2 Form Works M2 88,168

3 Con’c Casting M3 41,906


7
3.Organization
□ Organization Chart

[SUPERSTRUCTURE]
2. Logistic (Stock yard & office)

1. Over all plan


2. Stock yard & office Plan
2. Logistic
1. Stock yard & office Area Information
Hazrat Shahjalal International Airport Expansion Project (HSIA)

Area Information

Stock yard &


office area
MAIN ACCESS

PHASE-1

SEOBON OFFICE
PHASE-2

MAIN ACCESS

INTERNAL ACCESS
SEOBON STACK YARD

ACCESS TO BASEMENT

11
GROUND FLOOR LEFT WING ACCESS PLAN
2) Logistic
2) Stock yard & office
Hazrat Shahjalal International Airport Expansion Project (HSIA)
Stock yard & office Plan

Office area

Carpenter
shop

Rebar shop

12
3. Schedule

1. Overall Schedule
2. Manpower Schedule
3. Equipment Schedule
4. Manpower Plan per Zoning
3.Schedule
1) Overall Schedule
2020 2021 2022 REMARKS

Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan

1'st 2'nd 3'rd 4'th 5'th 6'th 7'th 8'th 9'th 10'th 11'th 12'th 13'th 14'th 15'th

Contract
Pile Caps & Capping Beams
Construction Plan
RC
Basement
Contract
UG, Column, Beam, Footing,
Retaining Wall, Pit
Construction Plan

Contract
Ground Floor Slab,
SOG ( Slab On Grade ) & etc.
Construction Plan
RC
Ground FL
GF Column, Wall, Contract
Suspended Beam & Slab,
Staircase Construction Plan

Contract
RC 1st Floor Column, Wall,
1st FL Suspended Beam & Slab, Staircase
Construction Plan

2nd Floor Column, Wall, Contract


RC
Suspended Beam & Slab,
2nd FL
Staircase & etc. Construction Plan
3.Schedule
□ Main Structure Work Schedule as Construction Quantities
Monthly Work Schedule As the Construction Quantities
SL.
No.
Location Description Q`ty Unit REMARKS
1'st 2'nd 3'rd 4'th 5'th 6'th 7'th 8'th 9'th 10'th 11'th 12'th 13'th

1 Pile Caps & Capping Beams Re-bar Fab. & Install. 785.52 ton 130.92 130.92 130.92 130.92 130.92 130.92 0.11(ton/m3)

2 Pile Caps & Capping Beams Form Works 7,613.00 m2 1,268.83 1,268.80 1,268.80 1,268.80 1,268.80 1,268.97 1.05(m2/m3)

3 Pile Caps & Capping Beams Con'c Casting 7,191.00 m3 1,198.50 1,198.50 1,198.50 1,198.50 1,198.50 1,198.50

4 UG, Column, Beam, Footing, Retaining Wall, Pit Re-bar Fab. & Install. 2,260.01 ton 376.67 376.67 376.67 376.67 376.67 376.66 0.22(ton/m3)

5 UG, Column, Beam, Footing, Retaining Wall, Pit Form Works 21,823.00 m2 3,637.17 3,637.17 3,637.17 3,637.17 3,637.17 3,637.15 2.12(m2/m3)

6 UG, Column, Beam, Footing, Retaining Wall, Pit Con'c Casting 10,282.20 m3 1,713.70 1,713.70 1,713.70 1,713.70 1,713.70 1,713.70

7 Ground Floor Slab, SOG ( Slab On Grade ) & etc. Re-bar Fab. & Install. 253.01 ton 42.17 42.17 42.17 42.17 42.17 42.16 0.04(ton/m3)

8 Ground Floor Slab, SOG ( Slab On Grade ) & etc. Form Works 3,630.00 m2 605.00 605.00 605.00 605.00 605.00 605.00 0.64(m2/m3)

9 Ground Floor Slab, SOG ( Slab On Grade ) & etc. Con'c Casting 5,635.00 m3 939.17 939.17 939.17 939.17 939.17 939.15

10 GF Column, Wall, Suspended Beam & Slab, Staircase Re-bar Fab. & Install. 2,643.61 ton 377.66 377.66 377.66 377.66 377.66 377.66 377.65 0.26(ton/m3)

11 GF Column, Wall, Suspended Beam & Slab, Staircase Form Works 28,958.60 m2 4,136.94 4,136.94 4,136.94 4,136.94 4,136.94 4,136.96 4,136.96 2.88(m2/m3)

12 GF Column, Wall, Suspended Beam & Slab, Staircase Con'c Casting 10,066.60 m3 1,438.09 1,438.09 1,438.09 1,438.09 1,438.09 1,438.09 1,438.06

13 1F Column, Wall, Suspended Beam & Slab, Staircase Re-bar Fab. & Install. 1,982.71 ton 283.24 283.24 283.24 283.24 283.24 283.24 283.27 0.26(ton/m3)

14 1F Column, Wall, Suspended Beam & Slab, Staircase Form Works 21,719.40 m2 3,102.77 3,102.77 3,102.77 3,102.77 3,102.77 3,102.77 3,102.78 2.88(m2/m3)

15 1F Column, Wall, Suspended Beam & Slab, Staircase Con'c Casting 7,550.00 m3 1,078.57 1,078.57 1,078.57 1,078.57 1,078.57 1,078.57 1,078.58

16 2F Column, Wall, Suspended Beam & Slab, Staircase & etc. Re-bar Fab. & Install. 375.36 ton 62.56 62.56 62.56 62.56 62.56 62.56 0.32(ton/m3)

17 2F Column, Wall, Suspended Beam & Slab, Staircase & etc. Form Works 4,424.00 m2 737.33 737.33 737.33 737.33 737.33 737.35 3.75(m2/m3)

18 2F Column, Wall, Suspended Beam & Slab, Staircase & etc. Con'c Casting 1,181.20 m3 196.87 196.87 196.87 196.87 196.87 196.85

Re-bar Fab. & Install. 8,300.22 ton 130.92 507.59 549.76 927.42 927.42 1,210.66 1,079.73 765.62 723.46 723.45 345.80 345.83 62.56 0.20(ton/m3)

Main Work Q`ty Form Works 88,168.00 m2 1,268.83 4,905.97 5,510.97 9,647.91 9,647.91 12,750.85 11,481.86 8,582.04 7,977.06 7,977.06 3,840.10 3,840.11 737.35 2.10(m2/m3)

Con'c Casting 41,906.00 m3 1,198.50 2,912.20 3,851.37 5,289.46 5,289.46 6,368.03 5,169.53 3,652.68 2,713.53 2,713.50 1,275.44 1,275.45 196.85
3.Schedule
2 Manpower Productivity and Schedule
Monthly Work Schedule As the Construction Quantities
SL.
Location Description Quantities Unit Remarks
No.
1'st 2'nd 3'rd 4'th 5'th 6'th 7'th 8'th 9'th 10'th 11'th 12'th 13'th

1 Pile Caps & Capping Beams Steel Fixer 251.76 man/day 41.96 41.96 41.96 41.96 41.96 41.96 0.12 ton/man*day

2 Pile Caps & Capping Beams Carpenter 195.19 man/day 32.53 32.53 32.53 32.53 32.53 32.54 1.5 m2/man*day

3 Pile Caps & Capping Beams Con'c Mason 184.38 man/day 30.73 30.73 30.73 30.73 30.73 30.73 1.5 m3/man*day

4 Pile Caps & Capping Beams Scaffolder 58.56 man/day 9.76 9.76 9.76 9.76 9.76 9.76

5 UG, Column, Beam, Footing, Retaining Wall, Pit Steel Fixer 579.48 man/day 96.58 96.58 96.58 96.58 96.58 96.58 0.15 ton/man*day

6 UG, Column, Beam, Footing, Retaining Wall, Pit Carpenter 419.70 man/day 69.95 69.95 69.95 69.95 69.95 69.95 2.0 m2/man*day

7 UG, Column, Beam, Footing, Retaining Wall, Pit Con'c Mason 197.76 man/day 32.96 32.96 32.96 32.96 32.96 32.96 2.0 m3/man*day

8 UG, Column, Beam, Footing, Retaining Wall, Pit Scaffolder 125.94 man/day 20.99 20.99 20.99 20.99 20.99 20.99

9 Ground Floor Slab, SOG ( Slab On Grade ) & etc. Steel Fixer 97.32 man/day 16.22 16.22 16.22 16.22 16.22 16.22 0.15 ton/man*day

10 Ground Floor Slab, SOG ( Slab On Grade ) & etc. Carpenter 93.06 man/day 15.51 15.51 15.51 15.51 15.51 15.51 1.5 m2/man*day

11 Ground Floor Slab, SOG ( Slab On Grade ) & etc. Con'c Mason 144.48 man/day 24.08 24.08 24.08 24.08 24.08 24.08 1.5 m3/man*day

12 Ground Floor Slab, SOG ( Slab On Grade ) & etc. Scaffolder 27.90 man/day 4.65 4.65 4.65 4.65 4.65 4.65

13 GF Column, Wall, Suspended Beam & Slab, Staircase Steel Fixer 847.28 man/day 121.04 121.04 121.04 121.04 121.04 121.04 121.04 0.12 ton/man*day

14 GF Column, Wall, Suspended Beam & Slab, Staircase Carpenter 556.92 man/day 79.56 79.56 79.56 79.56 79.56 79.56 79.56 2.0 m2/man*day

15 GF Column, Wall, Suspended Beam & Slab, Staircase Con'c Mason 258.09 man/day 36.87 36.87 36.87 36.87 36.87 36.87 36.87 1.5 m3/man*day

16 GF Column, Wall, Suspended Beam & Slab, Staircase Scaffolder 167.09 man/day 23.87 23.87 23.87 23.87 23.87 23.87 23.87

17 1F Column, Wall, Suspended Beam & Slab, Staircase Steel Fixer 635.47 man/day 90.78 90.78 90.78 90.78 90.78 90.78 90.79 0.12 ton/man*day

18 2F Column, Wall, Suspended Beam & Slab, Staircase Carpenter 417.69 man/day 59.67 59.67 59.67 59.67 59.67 59.67 59.67 2.0 m2/man*day

19 3F Column, Wall, Suspended Beam & Slab, Staircase Con'c Mason 193.62 man/day 27.66 27.66 27.66 27.66 27.66 27.66 27.66 1.5 m3/man*day

20 3F Column, Wall, Suspended Beam & Slab, Staircase Scaffolder 125.30 man/day 17.90 17.90 17.90 17.90 17.90 17.90 17.90

21 2F Column, Wall, Suspended Beam & Slab, Staircase & etc. Steel Fixer 96.24 man/day 16.04 16.04 16.04 16.04 16.04 16.04 0.15 ton/man*day

22 2F Column, Wall, Suspended Beam & Slab, Staircase & etc. Carpenter 85.08 man/day 14.18 14.18 14.18 14.18 14.18 14.18 2.0 m2/man*day

23 2F Column, Wall, Suspended Beam & Slab, Staircase & etc. Con'c Mason 30.30 man/day 5.05 5.05 5.05 5.05 5.05 5.05 1.5 m3/man*day

24 2F Column, Wall, Suspended Beam & Slab, Staircase & etc. Scaffolder 25.50 man/day 4.25 4.25 4.25 4.25 4.25 4.25

Steel Fixer 2,507.55 man/day 41.96 138.54 154.76 275.80 275.80 366.58 324.62 244.08 227.86 227.86 106.82 106.83 16.04

Carpenter 1,767.64 man/day 32.53 102.48 117.99 197.55 197.55 257.23 224.69 168.92 153.41 153.41 73.85 73.85 14.18
Manpower
Con'c Mason 1,008.63 man/day 30.73 63.69 87.77 124.64 124.64 152.30 121.57 93.66 69.58 69.58 32.71 32.71 5.05

Scaffolder 530.29 man/day 9.76 30.75 35.40 59.27 59.27 77.17 67.41 50.67 46.02 46.02 22.15 22.15 4.25

Manpower Sum. Total 5,814.11 man/day 114.98 335.46 395.92 657.26 657.26 853.28 738.29 557.33 496.87 496.87 235.53 235.54 39.52 Avg. 447 man/day
3.Schedule
3) Equipment Mobilization Schedule

2020 2021 2022 REMARKS

Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21 Jul-21 Aug-21 Sep-21 Oct-21 Nov-21 Dec-21 Jan-22

1'st 2'nd 3'rd 4'th 5'th 6'th 7'th 8'th 9'th 10'th 11'th 12'th 13'th 14'th 15'th
SL.
NAME OF of EQUIPMENT SPEC. NO.
NO.
1 PICKWAY TRUCK 1

2 TRACTOR WITH TROLLY 1

3 TRACTOR WITH TROLLY 1

4 CRANE 50 TON 1

5 CRANE 50 TON 1

6 TRUCK 3 TON 2

7 PICK UP 1

8 FORKLIFT 10 TON 1

9 BAR CUTTING MACHINE 2

10 BAR BENDING MACHINE 3

11 STATIONARY PUMP 1

12 MOBILE PUMP CAR 1

13 WATER TRUCK 15000L 1

14 AIR COMPRESSOR 120RPM 1

15 GENERATOR 50KW 2

16 WELDING MACHINE 2
3.Schedule
4) Manpower Zoning Plan(Ground Floor & Basement) 1 team
Foreman : 3
Concrete : 15
4 Team Team Ground floor Carpenter : 15
2 Team Basement Re-bar Wrk : 40
Scaffolder :

LW ZONE 3

[GROUND FLOOR]
3.Schedule
4) Manpower Zoning Plan(First Floor) 1 team
Foreman : 3
Concrete : 10
4 Team, 16 Zone Carpenter :25
Re-bar Work : 25
Scaffolder : 10

LW ZONE 3

[FRIST FLOOR]
3.Schedule
4) Manpower Zoning Plan(2nd Floor) 1 team
Foreman : 3
Concrete : 10
3 Team, 15 Zone Carpenter : 25
Re-bar Wrk : 25
Scaffolder : 10

[2ND FLOOR]
4. Construction Plan

1. Pile Cap & Capping Beams


2. Basement Wall
3. Basement Roof Slab & Column.
4. Slab and beam formwork.
5. Column
6. Rebar BBS Control plan
4.Construction Plan
1. Pile Cap & Capping Beams

The Wall Form is consist of steel form, (Props Jack ),


4.Construction Plan
□ Material for Pile Cap (Steel form)
4.Construction Plan
2. Basement Wall

The Wall Form is consist of plywood(Thk.18), GTX (GI PIPE 2”), Prop jack
4.Construction Plan
3. Basement Roof Slab & Column

The Roof slab & Column Form is consist of plywood(Thk.18), GTX (2-4x4), an support (GI PIPE 2”),
For shoring cup lock scaffolding
4.Construction Plan
4. Slab and beam formwork

Coating plywood, GTX, GI PIPE, Cup lock Scaffolding


4.Construction Plan
5) Column

plywood, Timber, GI PIPE, Tai rod 16mm Cup lock Scaffolding


4.Construction Plan
5) Highest Column

plywood, Timber, GI PIPE, Tai rod 16mm Cup lock Scaffolding


4.Construction Plan
6. Rebar BBS Control plan

Bar bending schedule Re check

Supervisor
Supervisor &
& Foreman
Foreman Engineer
Engineer

Bar cutting plan Re check

Supervisor
Supervisor &
& Engineer
Engineer Manager
Manager

Minimize loss
5. Q-HSE Management Plan

1. Quality Assurance & Quality Control


2. QA/QC Document Control
3. HSE Conceptual Map
4. HSE Education and Training
5. Edge Protection & Access
6. Certificate
5.Q-HSE Management Plan
1) Quality Assurance & Quality Control
- Minimize Field Change & Construction Errors
- Apply Best Practice & Provide the Best Product

STAGE Contents Remark


• In 1 month from the time starting work
Devise
Devise aa early
early work
work plan
plan • Examination of early stage work plan

Devise
Devise aa comprehensive
comprehensive plan
plan • In 3 months from the time starting work
• Framing of site management plan
Pre Quality
Quality management
management policy
policy and
and
working devise a test plan
devise a test plan
Devise
Devise aa work
work schedule
schedule • Framing by co-worker
• Examination & recognition of site manager
• Making a detail work plan
Devise
Devise aa quality
quality management
management plan
plan
• Making a check list by item
Work
Work by
by drawing
drawing // SPEC
SPEC • Self examination by co-worker
• Examination by section chief

On Co-worker
Co-worker guiding
guiding &
& test
test
• Before 1 month of completion inspection
working Internal
Internal completion
completion inspection
inspection • Quality management team of company

Correction
Correction • Completion

After • Correction termination & defect type checking


Meeting
Meeting of
of completion
completion inspection
inspection
working

We will align with QA/QC requirements to Main Contractor and Owner


We will obey the procedure of ISO 9001 31
5.Q-HSE Management Plan
2) QA/QC Document Control

TRANSMITTAL •Transmittal by Co-Responding Channel


•Keep a copy transmittal & receipt

•According to Specification
INSPECTION •According to Method Statement
DOCUMENT •According to Inspection Testing Plan

•Daily report
PROGRESS •Weekly report
REPORT •Monthly report
•3Month report

32
5.Q-HSE Management Plan
3) HSE Conceptual Map

Achievement
Achievementnon-accident
non-accidentsite
site

▷ Follow Working safety rules


▷ Improvement working conditions and welfare
▷ Practice the basis
Build
Buildup
upgood
goodworking
workingconditions
conditions ▷ Keep the good site conditions

5 Action Plans in the site

1) Self-safety management 3) Strengthening safety patrol


safety education before the working Workers: Individual Protection
Check the safety instruments and facilities Follow working safety rule
Safety manager : Confirm safety working 4) Ensure site pre-safety
Arrangement after working Check hazards in the site and working
2) Modern Safety Management Safety facility management
Subcontractor : Self-safety management 5) Site arrangement
Fixing the Daily safety management Cycle Make a good site conditions
Site Cleaning and arrangement

33
5.Q-HSE Management Plan
4) HSE Education and Training

Type of the safety education Object Education time Period Instructor

HSE Manager
Safety introduction for labors All labors Employment 1hour Project Manager
Project Manager
Regular education and train- All labors Monthly 2hours HSE manager
ing for labors Safety Supervisor

Education and training before All labors Before the work change 1hour HSE manager
the work change

Special safety education and All labors Before the dangerous work 2hours HSE manager
training Safety Supervisor

Foreman education and train-


ing Foreman Necessity 1hour Safety Supervisor

Rigger and scaffolder Skilled labors Before the dangerous work 1hour HSE manager
Safety Supervisor

Crane & Heavy equipment HSE manager


operator Operator Before the dangerous work 1hour Safety Supervisor

Safety Supervisor
Tool-box Meeting All labors Before the work 15 minute Foreman
Related safety education and Before the work Safety Supervisor
training Related labors ( Height Work, Hot, etc ) 15 minute Foreman
34
5.Q-HSE Management Plan
5) Edge Protection & Access

Edge Plan & Edge Plan &


Access Access

Wall (Typ.) Slab (Typ.)


35
5.Q-HSE Management Plan
6) Certificate

ISO 14001 : 2015 OHSAS 45001 : 2018 ISO 9001 : 2015


36