Weekly Report EMAAR

You might also like

Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 20

BP#04A & BP#04B

Parcel 1 –Villas & Townhomes

Owner
EMAAR MISR FOR DEVELOPMENT

PM
JILL International

Data Date
15 June 2023

Consultant
EGEC

Contractor
REDCON CONSTRUCTION
Project Information
Project Duration 24 months

Advance Payment %
REDCON
Performance Bond %

Retention %

Type of Contract

Turn-keys

Contract Price EGP


Price Summary
Project
Time
Schedule
S_Curve
S_Curve_Construction
KPI
KPIs
KPIs
Progress
Progress Summary

Contract Value
Earned Value Actual Cumulative % 0.00%

Planned Value
Planned Cumulative %
Planned Cumulative % 0.00%
Actual Cumulative %

SPI 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

12.00
Planned Vs Actual / Week 10.00
$1.00
$0.90 8.00
$0.80
$0.70 6.00
$0.60
$0.50
4.00
$0.40
$0.30
$0.20 2.00
$0.10 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 0.00
5/7/2023 5/14/2023 5/21/2023 5/28/2023
Planned Actual Earned Value Planned Value
Progress Summary

Milestones Planned % Actual % BL Project Finish Expected Finish


Project Summary
Project Summary
Phase 01 Phase 02 MOCKUP CONSTRUCTION
Activity Name Schedule % Performance % Schedule % Performance % Schedule % Performance %
Complete Complete Complete Complete Complete Complete
Project Summary
Phase 01 Phase 02 MOCKUP CONSTRUCTION
Activity Name Schedule % Performance % Schedule % Performance % Schedule % Performance %
Complete Complete Complete Complete Complete Complete
Project Summary
Phase 01 Phase 02 MOCKUP CONSTRUCTION
Activity Name Schedule % Performance % Performance %
Schedule % Complete Schedule % Complete Performance % Complete
Complete Complete Complete
Progress Summary
Soil
Excavation Works PC Foundations RC Foundations G.F Columns G.F Slabs F.F Columns F.F Slabs Columns R.F slabs R.F
Replacement
Count. of
Group Type
Plots
Not In Not In Not In Not In Not In Not In Not In Not In Not In Not
Finished In Progress Finished Finished Finished Finished Finished Finished Finished Finished Finished
Started Progress Started Progress Started Progress Started Progress Started Progress Started Progress Started Progress Started Progress Started Progress Started
Progress Summary
Masonary under Ground Floor First Floor Roof Floor Ground Floor First Floor Roof Floor
insulation Backfilling S.O.G
S.O.G Masonary Masonary Masonary Plaster Plaster Plaster
Count. of
Group Type
Plots
Not In Not In Not In Not In Not In Not In Not In Not In Not In Not
Finished In Progress Finished Finished Finished Finished Finished Finished Finished Finished Finished
Started Progress Started Progress Started Progress Started Progress Started Progress Started Progress Started Progress Started Progress Started Progress Started
Mock up Progress Summary

Performance % Completed
Building Foundation Works
Group Plot Type
No. Masonary
slabs G.F columns slabs F.F Columns slabs R.F insulation Backfilling S.O.G under G.F F.F R.F G.F F.F plaster R.F Facade
F.F R.F S.O.G Masonary Masonary Masonary plaster plaster Plaster
THANK
YOU

You might also like