Relevant Pipe Break History

Installatio Cathodic
Date Pipe Size & Contract Drawing n Date (as
Sr. No. Location Protection
Reported Material Number Nos. per As- Status
Built)
T-100 x T-221 162-351-20AX-
01 29.10.2019 600 mm DI 076-C06 February, 1982 Not Provided
(VC-2) CD-505 to CD-519
T-7 x T-138 near 581-340-20CS-
02 22.01.2020 1200 mm DI 581-C22 May, 1987 Provided
VC-03 CD-100 to CD-147
162-352-20EC-
03 22.01.2020 T-195 x T-184 800 mm DI 162-C14 April, 1984 Not Provided
CE-001 to CE-012
T-06 x T-07 at VC- 581-340-20CS-
04 18.01.2021 1200 mm SCRC 581-C22 May, 1987 Provided
04 CD-100 to CD-147
162-352-20EC-
05 03.04.2021 T3 X T138 1000 mm DI 162-C14 April, 1984 Not Provided
CE-001 to CE-012
T-138 NEAR 162-352-20EC-
06 21.11.22 600 mm SCRC 162-C14 April, 1984 Not Provided
CAMP 15 CE-001 to CE-012
162-352-20EC-
07 19.07.23 T-138 x T-295 600 mm SCRC 162-C14 April, 1984 Not Provided
CE-001 to CE-012
162-354-20EC-
08 19.07.23 T-183 x T-218 600 mm SCRC 162-C06 November, 1983 Not Provided
CE-001 to CE-007
162-352-20EC-
09 15.08.23 T-195 LP-043 800 mm DI 162-C14 April, 1984 Not Provided
CE-001 to CE-012