• Parkinson's Law:
It is the old adage that “work expands to fill the time available for its
completion”.
CPM
Lets Suppose there is a project, having 7 smaller tasks with dependencies and
different time duration for their completion. Analyze Critical Path Chain by using
Forward Pass and Backward Pass.
0 4 4 4 3 7 0 11 11
4 6 7 11
C D
5 2 7 7 4 11
16 19 11 16
G F
16 3 19 11 5 16