Lecture 7

Critical Path Chain Method


Critical Path Method(CPM)
• Student Syndrome:
a phenomenon where people delay doing things until right before the deadline.
For example, a student who postpones working on an assignment until the night
before it's due is displaying the student syndrome.

• Parkinson's Law:
It is the old adage that “work expands to fill the time available for its
completion”.
CPM
Lets Suppose there is a project, having 7 smaller tasks with dependencies and
different time duration for their completion. Analyze Critical Path Chain by using
Forward Pass and Backward Pass.

Tasks Code Task Duration (Days) Analysis


A 4 -
B 3 A
C 2 A
D 4 C,B
E 11 -
F 5 E,D
G 3 F
Forward Pass & Backward Pass
0 4 4 7
A B 0
E 11

0 4 4 4 3 7 0 11 11

4 6 7 11
C D
5 2 7 7 4 11

16 19 11 16
G F
16 3 19 11 5 16