Progress Presentation SMELTER FERRONICKEL - KOLAKA 28-02-23

You might also like

Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 13

Weekly Progress

CUT & FILL PEMBANGUNAN


SMELTER FERRONICKEL -
KOLAKA
PT PP (EPC) -
PT DJN
Scope of Work

• 1. Cut and Fill - 1307_SPS_SCM_PP_EPC_719002_II_2023_1676645932

• 2. Site Instruction - SMT-PP-L-23-527


Progress (W-9)
Cut off 18 Februari 2023
PROGRESS
Summary of Progress Achievement
Volume Weight Desember 2022 Januari 2023 Februari 2023 Deviation
NO Description Unit
Ratio Factor 16-Dec-22 31-Dec-22 07-Jan-23 14-Jan-23 21-Jan-23 28-Jan-23 04-Feb-23 11-Feb-23 18-Feb-23 Cumm, up to This Week

A ORE STOCK PILE


Cut M3 28426,98 2973,85 2106,83 395,91 2576,00 9617,39 459,96 4295,74 3500,42 2500,88
(Actual) 20,66% 20,66% 2,16% 1,53% 0,29% 1,87% 6,99% 0,33% 3,12% 2,54% 1,82%
Fill M3 23070,48 2973,85 2106,83 395,91 2576,00 6863,65 459,96 3276,26 3260,87 1157,15
(Actual) 38,04% 16,77% 2,16% 1,53% 0,29% 1,87% 4,99% 0,33% 2,38% 2,37% 0,84%
Disposal M3 5356,50 0,00 0,00 0,00 0,00 2753,74 0,00 1019,48 239,55 1343,73
(Actual) 6,96% 3,89% 0,00% 0,00% 0,00% 0,00% 2,00% 0,00% 0,74% 0,17% 0,98%

B ELECTRIC FURNACE 13760,10


1 Cut M3 11978,46 6846,00 3400,00 1732,46
87,05% 100,00% 49,75% 24,71% 12,59%
2 Disposal M3 11978,46 6846,00 3400,00 1732,46
100,00% 100,00% 49,75% 24,71% 12,59%

C DORMITORY ENFI
1 Cut M3 8721,54 2029,00 3367,00 3325,54
100,00% 100,00% 23,26% 38,61% 38,13%
2 Fill M3 5968,90 0,00 2142,53 3826,37
100,00% 100,00% 0,00% 24,57% 43,87%
3 Disposal M3 2752,64 0,00 1224,47 1528,17
100,00% 31,56% 0,00% 14,04% 5,53%
List of Equipment
No. Jenis alat Total Qty. Satuan Area Sub. Qty. Satuan

1. Excavator 6 Unit Ore Stockpile 3 Unit


Water Intake 1 Unit
ENFI - Disposal 2 Unit
2. Vibro-roller 2 Unit Ore Stockpile 1 Unit
Disposal 1 Unit
3. Bulldozer 2 Unit Ore Stockpile 1 Unit
ENFI - Disposal 1 Unit
4. Dump Truck 5 Unit Ore Stockpile - Disposal 5 Unit
List of Manpower
No Posisi/ Jabatan Qty
1 Team Leader 1
2 Supervisor 3
3 Site Engineer 1
4 Surveyor 1
5 HSSE 2
6 Supply Chain & Logistik 1
7 Quality Control 1
8 Opr. Manager 1
9 Mekanik 3
10 Operator Excavator 6
11 Operator Bulldozer 2
12 Operator Vibro Roller 2
13 Driver Dump Truck 5
14 Assisten Surveyor 2
15 Flag Man 1
16 Dump Man 1
Total 33
Problems :

1. Kondisi cuaca
2. Area disposal
3. Performa Equipment
DATA CURAH HUJAN

PROJECT NAME : LAPAOPAO FERRPNICKEL SMELTER PROJECT AREA : ORE STOCK PILE-ENFI-ELECTRIC FURNACE
CLIENT/OWNER : PT. CERIA NUGRAHA INDOTAMA
MAIN CONTRACTOR : PT. PP (Persero) Tbk, Div. EPC
SUB CONTRACTOR : PT. DWI JAYA NIAGA
PERIODE : DESEMBER 2022

No. Jam/Tanggal 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
1 00:00 - 01:00 1 1
2 01:00 - 02:00 1 1
3 02:00 - 03:00
4 03:00 - 04:00 1
5 04:00 - 05:00 1 1
6 05:00 - 06:00 1 1
7 06:00 - 07:00 1 1
8 07:00 - 08:00 1
9 08:00 - 09:00 1 1
10 09:00 - 10:00 1 1 1 1 1 1
11 10:00 - 11:00 1 1 1
12 11:00 - 12:00 1 1
13 12:00 - 13:00 1 1 1 1 1
14 13:00 - 14:00 1 1 1 1
15 14:00 - 15:00 1 1
16 15:00 - 16:00 1 1 1 1
17 16:00 - 17:00 1 1 1 1 1
18 17:00 - 18:00 1 1 1
19 18:00 - 19:00 1
20 19:00 - 20:00 1
21 20:00 - 21:00
22 21:00 - 22:00
23 22:00 - 23:00
24 23:00 - 24:00
JUMLAH JAM HUJAN - - - - - - - - - - - - 2 - - - - - 8 - - - 15 6 6 6 7 - - - -
Keterangan : Cerah : Hujan

Kondisi Cuaca (Durasi Hujan) Hujan Cerah


07.00 - 16.00 WITA 29 123
16.00 - 18.00 WITA 8 30
18.00 - 00.00 WITA 2 93
00.00 - 07.00 WITA 11 122
DATA CURAH HUJAN

PROJECT NAME : LAPAOPAO FERRPNICKEL SMELTER PROJECT AREA : ORE STOCK PILE-ENFI-ELECTRIC FURNACE
CLIENT/OWNER : PT. CERIA NUGRAHA INDOTAMA
MAIN CONTRACTOR : PT. PP (Persero) Tbk, Div. EPC
SUB CONTRACTOR : PT. DWI JAYA NIAGA
PERIODE : JANUARI 2023

No. Jam/Tanggal 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
1 00:00 - 01:00 1
2 01:00 - 02:00 1
3 02:00 - 03:00 1 1
4 03:00 - 04:00 1 1
5 04:00 - 05:00 1 1 1 1
6 05:00 - 06:00 1 1 1 1 1 1
7 06:00 - 07:00 1 1 1 1 1 1
8 07:00 - 08:00 1 1 1 1 1 1 1
9 08:00 - 09:00 1 1 1 1 1 1 1 1
10 09:00 - 10:00 1 1 1 1 1 1 1 1 1
11 10:00 - 11:00 1 1 1 1 1
12 11:00 - 12:00 1 1 1
13 12:00 - 13:00 1
14 13:00 - 14:00 1
15 14:00 - 15:00 1
16 15:00 - 16:00 1 1
17 16:00 - 17:00 1 1
18 17:00 - 18:00 1 1
19 18:00 - 19:00 1 1 1
20 19:00 - 20:00 1
21 20:00 - 21:00 1
22 21:00 - 22:00 1 1 1
23 22:00 - 23:00 1 1 1
24 23:00 - 24:00 1 1
JUMLAH JAM HUJAN - 3 4 8 4 - - 4 14 6 - 2 - - 4 - - - - - - - - - 4 - 6 5 8 4 -
Keterangan : Cerah : Hujan

Kondisi Cuaca (Durasi Hujan) Hujan Cerah


07.00 - 16.00 WITA 37 211
16.00 - 18.00 WITA 4 58
18.00 - 00.00 WITA 13 142
00.00 - 07.00 WITA 22 195
DATA CURAH HUJAN

PROJECT NAME : LAPAOPAO FERRPNICKEL SMELTER PROJECT AREA : ORE STOCK PILE-ENFI-ELECTRIC FURNACE
CLIENT/OWNER : PT. CERIA NUGRAHA INDOTAMA
MAIN CONTRACTOR : PT. PP (Persero) Tbk, Div. EPC
SUB CONTRACTOR : PT. DWI JAYA NIAGA
PERIODE : FEBRUARI 2023

No. Jam/Tanggal 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
1 00:00 - 01:00 1 1
2 01:00 - 02:00 1 1
3 02:00 - 03:00 1 1
4 03:00 - 04:00 1 1
5 04:00 - 05:00 1 1 1 1 1
6 05:00 - 06:00 1 1 1 1
7 06:00 - 07:00 1 1 1
8 07:00 - 08:00 1 1 1
9 08:00 - 09:00 1 1 1
10 09:00 - 10:00 1 1
11 10:00 - 11:00 1 1
12 11:00 - 12:00 1
13 12:00 - 13:00 1
14 13:00 - 14:00 1 1
15 14:00 - 15:00 1 1
16 15:00 - 16:00 1 1
17 16:00 - 17:00 1
18 17:00 - 18:00
19 18:00 - 19:00
20 19:00 - 20:00 1
21 20:00 - 21:00 1 1 1
22 21:00 - 22:00 1 1 1
23 22:00 - 23:00 1 1 1 1
24 23:00 - 24:00 1 1
JUMLAH JAM HUJAN - 3 3 3 - - - - - - - - 8 - - - - 2 - - - 8 11 5 6 3 - - - - -
Keterangan : Cerah : Hujan

Kondisi Cuaca (Durasi Hujan) Hujan Cerah


07.00 - 16.00 WITA 18 206
16.00 - 18.00 WITA 1 55
18.00 - 00.00 WITA 13 127
00.00 - 07.00 WITA 20 176
Plan 1 Week Ahead

1. Cut and fill area ore stockpile


2. Disposal
3. ENFI temporary facility area elv. 162
finish
Terima Kasih