Arab Republic of Egypt

READY MIX EGYPT CO. (Subsidiary of OCI)

The New Naga Hammadi Barrage


And
The Hydropower-Plant Project
Brief Summary

the Existing Naga Hammad Barrage


 The Existing Naga Hammadi Barrage is
located at 359.500 km. of Aswan
Reservoir

 This barrage has been constructed to lift


water level to provide enough water level
for both of the Western and Eastern Naga
Hammad canals and two pumps which
irrigate approximately 750.000 feddans in
Qena, Sohage and Assuit Governorates
The existing Naga Hammadi Barrage
I t has been constructed in 1930,
and consist of :
• 100.00 bays to allow passing flow.

• Two navigation locks:


1-The old one is 16.00 m wide, 70 m long and
draught with 1.5 m.
2-The new one is 17 m wide, 175 m long and
draught with 2.5 m.

• Two swing steels cross the downstream


heads of the navigation locks.

• The maximum level of water at the front is


65.40 m.

• The road spans the barrage is 6 m wide.


The Old Naga Hammadi Barrage
Reasons lead to think in constructing the New
Barrage
• The existing Barrage has been constructed since 1930.

• Some problems such as wearing concrete among stones


and some cracks.

• Meeting the increased requirements of water , wherever


it is expected that the area located near the old barrage
will be increased to be 750.000 feddans in the near future

• The facility of navigation by constructing two navigation


locks with more dimension to contain the increased
movement of navigation.

• Constructing high bridge with cargo 70 tones to meet the


increased traffic and connecting the eastern and western
roads between Cairo - Aswan.

• Benefit from the balance difference upon the barrage in


The New Naga Hammadi Barrage
• The New Barrage is located at the north of the
existing barrage at 3.5 km.

This location is chosen for the following


reasons
• It lies behind the existing barrage (i.e. in the low
level of water).

• The least width of the River Nile.

• It complies with the Hydraulic studies.

• Clay layer is suitable to construct the Barrage.


The Project Goals
Replacing the New Barrage instead of the old one
to meet the increased requirements of irrigation
water.

Control the water released through the barrage to


maintain the balance difference in generating
clean electrical energy (about 460 GW).

Enhance navigation by constructing 2 Navigation


Locks large enough to accommodate two of the
largest ships operating on the Nile in the same
time.

Have a new road spanning the barrage with a


capacity of 70 tones.

Improve living standard in the project area by


creating job opportunities for the extent of the
project execution.
Project Components

:It consists of 5 lots as follows

 Lot 1 : Civil Works Contract


 Lot 2 : Hydro – Mechanical Works Contract
 Lot 3 : Turbine & Generators Contract
 Lot 4 : Electrical Equipments Contract
 Lot 5 : Electric Works Contract
 Lot 6 : Consulting Services Works for the
Project.
Project General Layout

Permanent
Housing

Closure Dike
New Barrage
Existing
Barrage Diversion
Canal

Reclaimed
Contractor’s
Lands
Camp
General Planning of New Naga Hammadi
Barrage and its Hydro-Power Plant Project

Diversion Canal
Closure Dam

Power Houseُ

Sluiceway

Navigation Locks 2
New Naga Hammadi Barrage
Components
 Sluiceway
 seven bays, each equipped with 17 m wide and
13.5 m high radial gate.

 Hydro Power Plant


 4 Bulb turbine units.
 Total generating capacity is 64 MW
 Generating at average 460 GW/H of energy.

 Navigation Locks
 Structural length of 217 m.
 Chamber length of 170 m, 17 m wide.
 Minimum water depth of 3 m.
Follow – up the New Naga
Hammadi Barrage Components

 Closure Dam of the Diversion Canal


 Crest road width is 9 m.
 High Bridge
 Cargo 70 tones.
Sluiceway Location

Sluiceway
Sluiceway Cross Section
Navigation Locks

Navigation Lock 2
Hydro-Power Plant

The Hydro power Plant consists of:


Bulb turbine Units 4*
*Total Capacity is 64 MW
*Generated energy is 460GW/H
Racking Machine Main Gantry Crane

Trash Upstream Downstream


Rack Gates Gates
Turbine
units
Projects Costs
 Total estimated cost is approximately L.E. 1.4
Billions. These costs are distributed as follows

• 54.1 % for civil works.


• 9.8% for Hydro mechanical works.
• 28.2% for Electrical Equipment & Works.
• 7.9% for the Consulting Services.
Project Consulting Offices Union

 Lahymer GmbH “ Germany”.


 Sogreah “ France ‘.
 Electrowatt “ Switzerland ‘
 Arab Consulting Engineers “ Egypt’.
 Electric Power Systems Engineer
Company “ Egypt’
Focus On Civil Works Contract
Companies Concerned In The Civil Works:
The Contract will be implemented by a
consortium comprising of :

• VINCI GRAND PROJECT “ FRANCE”.


• BILFINGER BERGER “ GERMANY”.
• ORASCOM CONSTRUCTION INDUSTRIES ‘
EGYPT”

In addition to a group of Egyptian and


European companies as subcontractors.

READY MIX EGYPT CO. (subsidiary of OCI) is


one of those subcontractors for which the concrete
supply has been assigned.
CONCRETE
The primary approach to design
concrete appropriate for a water
structures should be for durability
shall be based on the need to
achieve a high quality and relatively
impermeable concrete with a low
heat especially when using mass
concrete like in our case.
Secondary approach for such structures
always comes to be the concrete strength.

For such approaches a blend of Fly Ash and


HSC has been used for more durable (low
alkali, low heat) concrete, in addition to
super plasticizers & well graded washed
aggregates for achieving high performance
& workability.
RME EQUIPMENT
CONCRETE BATCHING PLANTS
Two Concrete Mixing Plants model: C.S Johnson 430
Brand: USA -
.Size : max. 3 m3 / Batch -
- Capacity : 90 m3 / hour ( actual output is 60 / 65
m3 / hour each Plant).
- Control System: Computerized control
system.

One Concrete Mixing Plants model: ELBAMATIC S


Brand: USA -
.Size : max. 3 m3 / Batch -
- Capacity : 90 m3 / hour ( actual output is 60 / 65
m3 / hour each Plant).
- Control System: Computerized control
system.