Professional Documents
Culture Documents
Ammonia CW Case Study 08 Feb 06
Ammonia CW Case Study 08 Feb 06
GNFC AT A GLANCE
Incorporation : Capacity Per Annum Ammonia : Urea : Methanol : Formic Acid : Acetic Acid : Weak Nitric Acid : Conc. Nitric Acid : Calcium Amm. Nitrate : Amm. Nitro phosphate : Captive Power : IT infrastructure : NCPL for Aniline and TDI
May10,1976
4,45,000 MT 5,94,000 MT 1,30,000 MT 8,000 MT 1,00,000 MT 2,47,500 MT 66,000 MT 1,42,500 MT 1,42,500 MT 50 MW VSAT, Info tower, PKI
2
Formic acid, Acetic Acid, Aniline, TDI and Methanol plants are dependent on Ammonia plant
NH3 CO
ACETIC ACID
Tail Gas CO
METHANOL 2
NCPL
4
CW Treatment Monitoring
Dedicated CW water cell Monitoring of Analysis and supervision of Ammonia CT by M/s. Chembond Regular activities: Daily : Performance evaluation by CW cell Weekly: CT cells deck algae cleaning Monthly :
Sterilization of side stream filters Review of exchangers performance Corrosion rate monitoring
Quarterly: Review with M/s Chembond modification in treatment; if required Bio-fouling monitoring Inspection and cleaning during shut down
for
Benefits
With better treatment and Modifying the limits of critical parameters COC improved to 6~6.5 Saving in CW make up : 11,000,00 m3/year. Reduction in corrosion rate : From 3~4 mpy to <1.5 mpy Reduction in scaling Reduction in microbiological activity
TVC SRB
: 50000 : 100~200
CW parameters
pH Make up CW water circulation 7.0~8.0 6.8~7.2
Conductivity
TH Mg Hardness
2500max
800~825 250~350
Ca Hardness Chloride
Silica Turbidity
ppm ppm
ppm NTU
50~85 10~25
10~20 1~2
450~550 250max
100~125 10
10
Typical CW parameters
Ortho PO4 Poly PO4 Organo PO4 Total PO4 Zinc TDS NH3 TVC SRB Circulating water ppm 5~6 ppm 1.5~3.0 ppm 1.5~3.0 ppm 7~10 ppm 0.5~1 ppm 1500max ppm 10 per ml 50,000 mpn /100 100 ml
11
12
History of E706
Synthesis Gas cooler- a critical exchanger condenses 50~60% ammonia in synthesis gas loop Original exchanger started leaking within a year of service
Frequent
better design exchanger : SS304 tubes and split flow of CW side installed
13
New design exchanger installed in 1984 H.T. Area : 1445 m2 Heat Duty : 14.28 MKcal/hr Cooling water : Shell side In/Out temp : 33/43 No of passes : Split flow CW flow : 1500 m3/hr MOC : CS Synthesis gas : Tube side In /Out temp : 79/ 39 Pressure : 230 bar No of pass : 2 , U-tubes No. of tubes : 1095 MOC : SS-304
14
Leakage of E706
After 17 years, first leakage noticed in May-2001 Process gas containing 18 % Ammonia leaks to CW side Gas was coming out with from shell side vent
IN OUT Diff. 7.4 9.1 +1.7 5~10 ppm 15~50 ppm +10~40 1240 324 236 14 664 +320 1150 272 208 16 572 -300 -90 -52 -32 +4 -92 -620
15
Leakage of E706
Consequences
5 ~10 ppm Ammonia in CW circulation system Elevated pH of CW outlet to 8.5 Chlorination limitation High microbiological growth - nitrifying bacteria CW supply pH tends to remain low Biomass fouling in the exchangers Gas pocketing in the exchangers Back pressure in the E706, less CW flow through it Scaling in the exchangers of CW system
16
Repair of E706 :1
In October 2002 S/D
CW side back-flushed:
Sludge of ammonia salts was flushed out
Bundle pulling out was not possible Chemical cleaning with 5% sulphamic acid
Results was not satisfactory
Shell was cut open from one side and cleaned with high pressure Jetting Hydro-test at 12 barg was carried out:
3 leaky tubes plugged
Leakage Persisted
17
Scaling in E706
18
19
20
Repair of E706 : 2
In Jan 03 S/D
In Jan03 opportunity Chemical cleaning with 5% sulphamic acid Leak test was taken. No leakage identified,
Why? During normal operation, press diff. between shell and tube is very high 230 bar, cracks open up at high pressure Shell is low pressure part Leakage not detectable with hydro test at 12 bar pressure
21
Repair of E706 : 3
In April 03 S/D
A special ammonia test carried out Shell plates cut and the bundle cleaned with hydro jetting Shell pressurised to 1 bar with N2 and further to 2 bar with Ammonia Leakage detected by placing Ammonia test paper on the tube sheet and observing color change to blue 12 tubes were detected and plugged However, CW outlet ammonia pick up and pH still indicated leakage after start-up
22
To Sustain Operations
Challenging task : To maintain the thermal performance of E706 E706 performance deteriorated due to scaling and gas back pressure, syn gas outlet temp increased to 50 deg C from 39 deg Load on down stream refrigeration unit was increased, steam consumption increased by 4 Mt/hr
Measures Taken:
1.0 Local gas release provision 2.0 Managing Micro biological activity 3.0 Managing scaling
23
24
E706
25
27
Measures taken to contain scaling: 1. Local Polymeric Dispersants dosing Effectiveness checked by analyzing Ca-Hardness at CW inlet and Outlet, before and after dosing
28
3.
Back flushing: Loose scale partially removed by the exchanger back flushing during short interruptions Nitrogen Bumping: Twice in a day Low pressure N2 blowing for half an hour was done in the exchanger for removing loose scale The removal of scale is ensured by analyzing CW outlet sample indicating rise in Turbidity by 50 ~90 NTU and rise in Ca-Hardness by 10 ~25 ppm.
30
--4 +20
18 28 95
-+10 +77
31
3.3
Managing Scaling
4. Local CW make up at E706 inlet To reduce Hardness- a key factor for scaling CW outlet hardness was reduced from 700 ppm to 550 ppm 5. Local Sulphamic acid dosing To reduce local pH Special arrangement made for dosing
32
33
E706
Plant Operation could be sustained for 3 years till the replacement of the exchanger in April 2004 with the effective problem specific treatment
35
Conclusion
The problems related to cooling water systems can lead to heavy production and energy loss. This can be effectively handled without affecting production and continuity of the plant by thorough understanding of the process as well as CW chemistry involved. Cooling water treatment is a specialized subject. A lot of research and improvements are taking place in this field. This knowledge is available to industry through experts in the field. Industry should adopt the relevant features of advancements for improvement in the system.
36
THANK YOU
37