Professional Documents
Culture Documents
Unit III-B PM
Unit III-B PM
NPV, NPV*
IRR, MIRR
Profitability Index
Non-discounted
Payback Period Method
Projects are:
independent, if the cash flows of one are
unaffected by the acceptance of the other.
mutually exclusive, if the cash flows of one
can be adversely impacted by the
acceptance of the other.
NPV: Sum of the PVs of all
cash flows.
n CFt
NPV = ∑
(1 + r)t
t=0
0 1 2 3
L’s CFs: 10%
-100 10 60 80
0 1 2 3
S’s CFs: 10%
-100 70 50 20
What’s project L’s NPV?
0 1 2 3
L’s CFs: 10%
-100 10 60 80
= NPVL
What’s project L’s NPV?
0 1 2 3
L’s CFs: 10%
-100 10 60 80
9.09
49.59
60.11
18.79 = NPVL NPVS = $19.98.
Which project should be chosen?
Demerits:
NPV is expressed in absolute terms rather in
relative terms and hence does not factor in the
scale of investment.
NPV rule does not consider the life of a project.
Internal Rate of Return:
IRR
0 1 2 3
-100 10 60 80
PV1
PV2
PV3
0 = NPV Enter Cash Flows in CF, then
press IRR:
What’s project L’s IRR?
0 1 2 3
IRR = ?
-100 10 60 80
PV1
PV2
PV3
0 = NPV Enter Cash Flows in CF, then
press IRR: IRRL = 18.13%.
IRRS = 23.56%.
IRR by Short Cut method
0 -1,00,000
1 30,000
2 30,000
3 40,000
4 45,000
(PV of CI at LR – PV of CI at HR)
LR HR
-100000 15% -100000 16%
30000 26,086.96 30000 25,862.07
30000 22,684.31 30000 22,294.89
40000 26,300.65 40000 25,626.31
45000 25,728.90 45000 24,853.10
PV 100,800.81 PV 98,636.36
800.81 -1,363.64
IRR = 15.37%
Merits and Demerits of IRR
Advantages
closely related to NPV
easy to understand and communicate
Disadvantages
may result in multiple answers
may lead to incorrect decisions
not always easy to calculate
Modified Internal Rate of
Return (MIRR)
MIRR is the discount rate which causes the
PV of a project’s terminal value (TV) equal
to the PV of costs.
TV is found by compounding (FV) inflows at
the WACC.
Thus, MIRR assumes cash inflows are
reinvested at the WACC.
MIRR for project L: First, find
PV and TV (r = 10%)
0 1 2 3
10%
0 1 2 3
MIRR = 16.5%
-100 158.1
PV outflows TV inflows
$100 = $158.1
(1+MIRRL)3
MIRRL = 16.5%
Problem
The following cash flow are given below:
Year Project P
0 -120
1 -80
2 20
3 60
4 80
5 100
6 120
Calculate Modified IRR of the above project,
if the cost of capital is 15%.
Solution
Present value of Costs = 120 + 80/(1.15)
= 189.60
TV of Cash Inflows =
20(1.15)^4 + 60(1.15)^3 + 80(1.15)^2 +
100(1.15)^1 + 120 = 467
-100 50 50 50
What is the payback period?
0 1 2 3
-100 40 40 40
What are the payback periods
for projects L and S?
0 1 2 3
L’s CFs: 10%
-100 10 60 80
0 1 2 3
S’s CFs: 10%
-100 70 50 20
Payback for project L
0 1 2 2.4 3
CFt -100 10 60 80
Cumulative -100 -90 -30 0 50
0 1 1.6 2 3
CFt -100 70 50 20