Professional Documents
Culture Documents
Project Managment
Project Managment
Project Managment
10
Project Management
Example of Gantt Chart
Month
0 | 2 | 4 | 6 | 8 | 10
Activity
Design house
and obtain
financing
Lay foundation
Order and
receive materials
Build house
Select paint
Select carpet
Finish work
1 3 5 7 9
Months 11
2. Network Planning Techniques
• Program Evaluation & Review Technique (PERT):
– Developed to manage the Polaris missile project
– Many tasks pushed the boundaries of science &
engineering (tasks’ duration = probabilistic)
FIGURE 6.2
Activity-on-Arrow
Activity-on-Arrow Network
Network
An Activity is an arc with two nodes at its beginning and its end
a
b
c
d FIGURE A6.1
AoA:
AoA: Activity
Activity Predecessors
Predecessors
Task Predecessor
a --- b
a c
b a
c a d
d a
Task Predecessor a
a --- d
b
b --
c
c --
d a,b,c
AoA
AoA May
May Need
Need Dummy
Dummy Activity
Activity
Task Predecessor d
b
a --- a
b a
c
c a
d b,c
• Try this: a,b c and a,d e
Activity-on-Arrow
Activity-on-Arrow Network
Network
FIGURE A6.2
simplified network diagram for a dinner project indicates as follows;
Terms & Definitions:
Activity-
◦ Any portion of a project which consumes
time or resources & has a definite
beginning & an end is called as an activity.
◦ It is denoted by an arrow. The symbol above
arrow indicates activity description & the
number below indicates activity duration in
time units.
DESCRIPTION
DURATION
Event-
◦ The beginning & the completion of
activity is termed as an event.
◦ It indicates a particular instant of time at
which some specific milestone has been
achieved.
Node
Network logic-
This denotes the technical dependencies
among the activities.
e.g. Network logic in the network drawn
below is that activity A must be completed
before activity B can be started.
A B
1 2 3 Series
PRECEEDING SUCCESSOR
ACTIVITY
Example EVENT
network consists of three activities: designing the house, obtaining financing, and
actually building the house:-
1 Design house Obtain financing Build house
2 3 4
Example 1- A simple network
Consider the list of four activities for making a simple product:
Activity Description Immediate predecessors
A Buy Plastic Body -
B Design Component -
C Make Component B
D Assemble product A,C
Immediate predecessors for a particular activity are the activities that, when completed,
enable the start of the activity in question.
Sequence of activities
Activities A and B Can start anytime, since neither of these activities depends upon the
completion of prior activities.
Activity C cannot be started until activity B has been completed
Activity D cannot be started until both activities A and C have been completed.
The graphical representation is referred to as the PERT/CPM network
1 A 3
D 4
B C
2
25
Here the arrows represent activities while the nodes
represent the start and the end of an activity (i.e. events).
C
• Types of activities
Predecessor activity: Activities that must be completed
immediately prior to the start of another activity are called
predecessor activities.
Successor activity: Activities that cannot be started until
one or more of other activities are completed, but
immediately succeed them are called successor activities.
Concurrent activities: Activities that can be accomplished
concurrently are known as concurrent activities.
Types of event-
3
B
A C
1 2 5
D
4
Parallel
Head event- the event which marks the
completion of an activity.
B
A
1 2 C 5
D
4
Burst & merge event-
The nodes from which a number of
activities emerge are called as burst event
or burst node.
The nodes to which number of activities
converges are called as merge nodes or merge
events.
Error in networking
• Looping
• Dangling
• Mistake in succeeding and proceeding r/ship
Network
Errors in drawing Network - Looping
2
A B
1 3
C
Dangling
1 2 4
Dummy activity:
A Dummy activity is an imaginary activity. It does not exist in the Project
activities.
It is used in the network diagram to show dependency relationship or
connectivity between two or more activities
consider a case where B and C have the same job reference and they can be
started independently on completion of A. But, D could be started only
completion of B and C. c
EXAMPLE NW
• Example 1: Assume bank branch opening project has following activities along with
time duration: such as marketing study ,discussion with sharholders,budget ,get
license from NBE,
Activity Duration(months)
1-2 Marketing study 3
1-3 Discussion s.holders 4
1-4 budget 3
2-5 rent 4
3-5 RECRUITING EMPLOYEES 5
4- 5 hiring 7
5-6 License from NBE 3
6-7 OPENING 6
2
3 4
1 4 5 3 6 6
7
3 5
3 7
4
Exercise :1- Draw project network diagram
Activities
1-2
1-3
2-4
3-4
2-5
4-5
5
1
4
3
Exercise :-ABC co. is bringing a new product on line to be
manufactured in their current facility. They have identified 11
activities and their precedence relationships.
Immediate Duration
Activity Description
Predecessor (weeks)
A Develop product specifications None 4
B Design manufacturing process A 6
C Source & purchase materials A 3
D Source & purchase tooling & equipment B 6
E Receive & install tooling & equipment D 14
F Receive materials C 5
G Pilot production run E&F 2
H Evaluate product design G 2
I Evaluate process performance G 3
J Write documentation report H&I 4
K Transition to manufacturing J 2
Critical Path
Path
• Sequence of activities that leads from the starting node to the finishing
node/activity
Critical path
• The longest path; determines expected project duration
• Longest Path through Network
• Drives project completion date
• Least or Zero Float
• Delay on critical Path will delay completion of project
• Critical path is a sequence of activities from start to finish with zero slack
Slack
• Slack or float is the amount of time an activity can be delayed without delaying a
succeeding activity or the project finish date
• The time differential between the scheduled completion date and the required
date to meet the critical path. Slack, or float: The amount of time a noncritical
task can be delayed without delaying the project
• Slack shows how much allowance each activity has, i.e how long it
can be delayed without affecting completion date of project
Critical activities:- Activities on the critical path
……….
• The critical path is vital for successful
control of the project because:
– There is no slack time in any of the events on
this path
– The events on this path are the most critical
for the success of the project
Time Estimates
• Deterministic
– Time estimates that are fairly certain
• Probabilistic
– Estimates of times that allow for variation
40 of 85 .......... Network scheduling
Time estimation
40
Three times values are obtained
Optimistic time-time if no complications arise
Most likely time-takes into account normal
delays
Pessimistic time-time required if unusual
complications arise
Project Financing and Management-Project Wednesday, December 20, 2023
Project Financing and Management-Project Management
Management
41 of 85 8.5 Network scheduling
Average Time
41
activities time 2 15
A,1-2 13
13
B,1-3 12
5
C, 2-4 2 2
D,3-4 8 1
2
E,2-5 15
F,4-5 2 12 8
3 4
43 of 85 8.5 Network scheduling
E=13
2 15
E=28
13
5
E=0 2
1
2
12 8
3 4
E=12 E=20
45 of 85
l=13
2 15
L=28
13
5
l=0 2
1
2
12 8
3 4
l=18 L=26
47
E=13
L=13
2 15 L=28
E=28
13
5
E=0 2
1
2
L=0
12 8
3 4
Project Financing and Management-Project
Management
E=12 E=20
L=18 L=26
PERT and CPM Differences
PERT uses three time estimates (optimistic,
most likely, and pessimistic), CPM uses one
time estimate that represent the normal time
PERT is probabilistic in Nature, based on beta
distribution for each activity time and normal
distribution for expected time duration; CPM is
based on a single time estimate and is
deterministic in nature
48
Comparison Between CPM and PERT
CPM PERT
1 Uses network, calculate float or slack,
identify critical path and activities, guides Same as CPM
to monitor and controlling project
3 Used where times can be estimated with Used where times cannot be estimated
confidence, familiar activities with confidence.
Unfamiliar or new activities
49
Exercise :-draw NW and find CPM
Event time
1-2 12
1-3 10
1-4 11
2-3 8
2-5 11
4-6 18
3-7 25
6-7 13
5-8 17
7-8 9
9
1 10 3
25 7
20 45
11 13
4 18 6
11 29
51 of 85 8.5 Network scheduling
9
10 3 7
1
25
20 45
0 11 13
4 18 6
14
Project Financing and Management-Project 32
Project Financing and Management-Project Management Wednesday, December 20, 2023
Management
52 of 85 8.5 Network scheduling
slack
5
17
52 2 8
12 12 11 23 37 54 54
8
12
9
10 3 7
1
20 20 25
45 45
0 0
11 13
4 18 6
11 29
14
Project Financing and Management-Project 32
Project Financing and Management-Project Management Wednesday, December 20, 2023
Management
53 of 85 8.5 Network scheduling
Slack
Event LOT EOT (LOT-EOT)
53
1 0 0 0
2 12 12 0
3 20 20 0
4 14 11 3
5 37 23 14
6 32 29 3
7 45 45 0
8 54 54 0
Critical Path
5
17
54 2 8
12 12 11 23 37 54 54
8
12
9
10 3 7
1
20 20 25
45 45
0 0
11 13
4 18 6
11 29
14
Project Financing and Management-Project 32
Project Financing and Management-Project Management Wednesday, December 20, 2023
Management
EXAMPLE 2
SUPPOSE A CIVIL ENGINEERING FIRM HAS TO BID FOR THE CONSTRUCTION OF
A DAM. THE ACTIVITIES AND TIME ESTIMATES ARE GIVEN BELOW. DO THE
NEXT REQUIREMENTS.
Activity O m P
1-2 (a) 1 3 4
1-3 (b) 2 4 6
1-4 (c) 2 3 5
2-5 (d) 3 4 5
3-6 (e) 3 5 7
4- 7 (f) 5 7 9
5-8 (g) 2 3 6
6-8 (h) 4 6 8
7-8 (I) 3 4 6
REQUIRED:
a) Draw the project network and identify all the paths.
b) Compute the expected time for each activity and the expected duration for
each path.
c) Determine the expected project length.
d) Identify the critical path and critical activities.
SOLUTION
A)
CONT…..
Solution
B)
Times
Path Activity O m P te = O+4m+P Path total
6
1-2-5-8 a 1 3 4 2.83
b 2 4 6 4.00 10.00
c 2 3 5 3.17
1-3-6-8 d 3 4 5 4.00
e 3 5 7 5.00 16.00
f 5 7 9 7.00
1-4-7-8 g 2 3 6 3.33
h 4 6 8 6.00 13.5
i 3 4 6 4.17
CONT…..
C) The critical path is path 1-3-6-8, since it has the longest expected
duration.
Times
Path
Activity O m P
1-2-5-8 a 1 3 4
b 2 4 6
c 2 3 5
1-3-6-8 d 3 4 5
e 3 5 7
f 5 7 9
1-4-7-8 g 2 3 6
h 4 6 8
i 3 4 6
NEXT SLIDE- PART 2