Professional Documents
Culture Documents
Masonry Arch Bridges - May - 2021
Masonry Arch Bridges - May - 2021
G S Yadav, PB-2
7420041112
gsyadav@iricen.gov.in
Outline of the Webinar:
Under uniform
vertical load
A concentrated live load such as from an axle of train will
disturb the thrust
Stabilising Forces :
(iv) Backfill self weight acts on the unloaded side
(v) Horizontal passive pressure acts on unloaded side
Effect of Fill….contd
Thus the fill generates forces tending to resist
the swaying motion of an arch
Line of Thrust
Hinge
2
1.5
0.5
-7 -6 -5 -4 -3 -2 -1 0
2. Failure due to Sliding
3. Failure due to both hinges and sliding
MULTI-SPAN: 7 or 8 HINGES
Experimental Investigation of 3 Span Arch
Dismantling Of Arch
Bridges
Bhagalpur accident
• 3X30 feet arch bridge no. 153 was being dismantled by
const. organization
Train
Basic principle to be followed while
finalizing dismantling scheme
1. Analyze force diagram at each stage of dismantling
2. At no stage the static equilibrium of forces should
be disturbed
Dismantling of Single/Multi
Span Arch Bridges
(CS no 18 to IRBM)
(Para 224 added to IRBM detailing procedure for dismantling of
single/multi span arch bridges)
Dismantling of Arch Bridges..contd
(c)Part-by-part
PART - B PART - B PART - B
dismantling
C C
SECTIONAL ELEVATION
Netting
Fig. 1(a)
Spendrel Wall
1m
S1 S2
Section - 1 Section - 2
5 6
9 10
13 14 W
11 12
7 8
Section -3 Section - 4
S3 S4
1m
PLAN Section CC
Fig. 1(b) Fig. 1(c)
Insp & Maintenance of Arch Bridges
105
Insp & Maintenance of Arch
Bridges
Defects in arch barrel :
• Extension of vertical cracks from substructure to arch
barrel. These cracks appear as longitudinal cracks in
arch barrel. Cause – differential settlement of
foundation
• Transverse or diagonal cracks in arch
barrel( intrados). These are of serious nature and
indicate tensile stresses at intrados. Generally noticed
in the vicinity of crown at initial stage. Indicate
serious weakness in arch requiring strengthening on
priority.
• Weathering of masonry , Crushing of masonry,
leaching of mortar from joints, loosening of masonry
units.
Defects Associated With Spandrel wall
(1) Where there are longitudinal cracks in arch ring adjacent to inner face
of spandrel walls,
(2) Where spandrel walls and parapets are bulging due to excessive thrust,
(3) Where there are vertical cracks in spandrel walls and parapets
Strength Contribution due to Track
In railway bridges, track helps to distribute load
over a number of sleepers in longitudinal direction
Strength contribution due to haunch fill
Additional strength as percentage of
Nature of haunch fill
arch ring strength
Concreting increasing
the thickness at
springing level by 50% 25%
Concreting level upto
crown 50%
Sand, gravel or boulder
grouted with cement
slurry 10%
Sand, gravel, boulder Nil
Methods of Strength Assessment
UIC 778-3R suggests three levels of strength
assessment :
Over-ringing by a new
reinforced arch on the
extrados of the original
masonry arch .
The new arch ring should be
designed to take the entire
load ( para 5.3.5.2 of ABC)
This method can easily be
adopted in GC projects.
NEAR SURFACE REINFORCEMENT
The collapse mechanism of an arch assumes, four
hinges to be needed for a single span arch to
collapse, opening alternatively at the extrados and at
the intrados
The main idea is that providing tensile reinforcement
(either in the form of CFRP trips or SS bars) to
the arch, either at the extrados or at the intrados,
locks the activation of such a mechanism.
Few firms like “Helifix” are doing this type of work.
NEAR SURFACE REINFORCEMENT..contd
UNDER ARCHING
Under arching may be in three forms all of which require
that secondary arch is fixed to the original abutment
skewbacks of the arch
(1) Sprayed concrete with R/F flexed to intrados of original
arch
(2) a second brick or stone ring constructed under the original
intrados
(3) steel arches under the arch barrel connected to the
original abutment skewbacks of the arch , and the space
between the steel arch and the arch barrel grouted with
expansive mortars or separated by steel wedges
UNDER ARCHING..contd
STEEL CONCRETE
Interning and Jacketing
This method is commonly adopted on IR. ABC specifically
recommends this method.
For strengthening of Piers and Abutments , the
composite action is always considered
Thank You
G S Yadav, PB-2
7420041112
gsyadav@iricen.gov.in
Strengthening of
Abutment/Piers
Strengthening By Jacketing
Preparatory works before
Jacketing
1. If it is possible to
impose SR , work can
be done in-situ , with
RF bars and steel
stools
2. Alternatively RCC bed
blocks can be precast
and fixed to the
masonry using epoxy
resin mortar
Precautions While Jacketing
Foundation shall be exposed only to a limited width
Pumping of water from foundation shall be avoided as
far as possible , as it may endanger safety
Holes for dowels should be drilled and not made by
pavement breakers
The work of jacketing should be done under suitable SR
Relaxation of SR :
If jacketing is done using OPC as per IS 269
1. 50 kmph after 7 days of concreting
2. 75 kmph after 14 days of concreting ; and
3. Normal sectional; speed after 28 days of concreting
• Two APPROACHES:
Modelling of Arch by FEM technique and validating model
by actual values
Apply desired load and measure deflections at crown and
spread of abutments.
1. Modelling of Arch:
• Arch is modelled using FEM tools
• Spread, strain in masonry, deformations at specified locations are
estimated under applied loads.
• Comparison with actual value to Validate the Model.
• Once the Model is validated, ultimate load carrying capacity of arch
can be estimated theoretically.
• This approach to be performed only under expert advice.
2. Application of Load and measurement
of crown deflection and spread at
abutments.
• Over-ringing by a new
reinforced arch on the
extrados of the original
masonry arch .
• The new arch ring should
be designed to take the
entire load ( para 5.3.5.2
of ABC)
• This method can easily be
adopted in GC projects.
NEAR SURFACE
REINFORCEMENT
• The collapse mechanism of an arch assumes, four
hinges to be needed for a single span arch to
collapse, opening alternatively at the extrados and at
the intrados
• The main idea is that providing tensile reinforcement
(either in the form of CFRP dtrips or SS bars)
to the arch, either at the extrados or at the intrados,
locks the activation of such a mechanism.
• Few firms like “Helifix” are doing this type of work.
NEAR SURFACE REINFORCEMENT
Under Arching
STEEL CONCRETE
Strength Assessment Of Arch
Bridges
• Military Engineering Experimental establishment
( MEXE) method
• Limit Analysis – equilibrium methods
• Limit Analysis – mechanism methods
• 2D FEM methods
• 3D FEM methods
• Elastic and elasto-plasto analysis
MEXE Method