Professional Documents
Culture Documents
Turbine Operation Preparation
Turbine Operation Preparation
Presented By:
M.V.Pande
Dy.Director
General Operation Philosophy
Achieving and maintaining the required output of the unit
18. Speed raising to 3000 rpm by setting speed reference value at 3000
rpm without stopping in between
X5 Criterion- M.S. Temperature
X5 Criterion- H.R.H. Temperature
Cold Start-up Steps
19. Soaking of turbine at 3000 rpm to fulfilled X7 criterion (approx. 45
min.), which ensures proper warming of IP turbine with respect to
HRH temperature. Monitoring turbine expansion and shaft/bearing
vibration trend
20. Ensuring TSE upper temperature margin of turbine greater than
35oK
21. Synchronization of generator to grid
22. Load raising to 10% (20MW) through speed reference setter.
23. Closing of all manual operated drains
24. Ensuring closure of HP-LP bypass valves by increasing pressure
set point above M.S. pressure
25. Check that load controller becomes active at about 20 MW.
26. Raising the M.S. pr. to 50 kg/cm2 by taking coal mill into service
and load is raised to 40 MW
27. Charging of LP heaters from steam side and putting the level
controllers of LPH 2 & 3 on auto
Cold Start-up Steps
28. Taking second coal mill into service and raising steam pressure. Ensure
that HP bypass set point is kept at higher value than actual pressure
29. Raise the turbogenerator load to 100 MW. Take HP heaters into service.
30. Establish second air cycle, second BFP, third coal mill and raise the
steam parameters
31. Changing over the deaerator pegging steam supply from CRH to
extraction-4 at about 55% load (when the NRVs release is obtained).
32. Raising the load to 150 MW
33. Taking the fourth coal mill into service. Put at least two mills on Auto.
Stabilize the M.S. pressure at about 140 kg/cm2
34. Putting CMC in to service after adjusting the M.S. Pressure set point to
match with actual pressure
35. Raising the turbogenerator load to 210 MW through unit target load set
point at CMC
36. Monitoring of turbovisory parameters, viz. absolute expansion, differential
expansions, axial shift, bearing & shaft vibrations, casing temperatures at
admission and exhaust locations, bearing temperatures
Turbine Oil System
Check that:
MOT level is normal ( 0+350 mm ) and basket
strainers are cleaned
Fire protection shut-off valve is closed and solenoid is
reset at turbine floor and in MOT room.
Readiness of Lube oil pumps and JOPs
Sub-group control of oil system "Auto-ON"
Ensure one of the lube oil coolers is in service from
oil side and water side.
Turbine Oil System
Turbine Oil System
Turbine Oil System
Operation :
• AOP and JOP can be started manually from PCR or on auto
through “SLC-ON” or through SGC "Auto-ON"
• Take the standby trial of AOP, EOP and JOP
• Watch drop in MOT level after AOP is started (280 mm).
• Put temperature controller SLC "ON"
• Watch the oil temperature at oil cooler outlet and ensure that it is
maintains between 40o – 45oC by temperature controller
Watch following parameters :
-Discharge pressure of AOP : 6.5 kg/cm2
i) -Oil Pressure before cooler : 5.4 kg/cm2
ii) -Oil pressure after cooler : 4.8 kg/cm2
iii) -MOT level : + 25 mm
-Jacking Oil Pressure : 120 kg/cm2
Turbine Oil System
When the turbine is running, check the bearing drain oil temperature and
babbit temperatures :
• Bearing drain oil temperature : < 60oC
• Journal bearing babbit temperature : < 90oC
• Thrust bearing babbit temperature : < 110oC
•
• Permissives for starting turning gear :
• Seal oil to H2 DP : > 1 kg/cm2
• Seal oil pressure TE & EE : > 4.4 kg/cm2
• H2 gas pressure : > 3.3 kg/cm2
• H2 purity : > 97%
• Liquid in generator : Not present
•
• Turning gear can be started by opening gate valve either manually or
through SLC. Observe that turbine speed on turning gear is as follows :
• When no vacuum in condenser : 110 – 120 rpm
• At normal vacuum condition : 150 – 160 rpm
Turbine Oil System
After turning gear is ON, AOP amperes will increase to 125A from 105A.
AOP, JOP and turning gear trip and pick-up speeds are as follows :
Trip Speed rpm Pick-up Spee rpm
i) Turning gear 240 210
ii) J.O.P. 540 510
iii) A.O.P. 2850 2800
When MOP takes over, the discharge oil pressure will be 8.5 – 9.5
kg/cm2 depending on turbine speed.
Interlocks of AOP, EOP & JOP
The standby AOP (SLC ON) will pick-up if discharge oil pressure < 4.8
kg/cm2 or the running AOP is OFF
DC Emergency Oil Pump will pick-up when SLC is ON and if lube oil
pressure is < 1.1 kg/cm2
The standby JOP (SLC ON) will pick-up if running JOP trips.
Condensate & Feedwater Line Charging
Vacuum Pulling and Gland Sealing Checks
• Line-up the steam ejectors
• Ensure 220 V DC supply to the solenoid of vacuum breaker
valve and it is closed
• Ensure water sealing to glands of all the valves in vacuum
circuit
• CW system is established
• Condensate system is established
• Ensure gland steam cooler siphone is filled-up
• Ensure electrical supply to the motors of seal steam leak-off
controller and seal steam supply controller. Their oil pumps
are working on auto to maintain oil pressure of 60 kg/cm2
• Check that valve AS301 (CRH Steam to glands) is in closed
position
• The turbine is put on turning gear
Vacuum Pulling and Gland Sealing
Vacuum Pulling and Gland Sealing Operation
• Charge the gland steam header by opening AS 378 valve and build up
the pressure 6 –6. 5 kg/cm2. Set the pressure 6.5 kg/cm2 and put the
ejector steam pressure control on auto.
• Start vacuum pulling through starting ejector by first opening steam
valve and then the air valve.
• Start one exhauster fan of gland steam cooler
• After building up 0.2 kg/cm2 vacuum, open the gland seal steam supply
valve and charge the header at pressure 0.01 kg/cm 2(g). Put the gland
steam pressure control on auto.
• After opening the steam supply valve, the header drain valve MAL-81
will close on auto.
• After establishing the gland sealing, the condenser vacuum will improve
at a faster rate
• When vacuum builds-up to 0.7 kg/cm2, take one main ejector in to
service by opening first its steam valve (AS02 or AS03) and then the air
valve. Cut-off the starting ejector by closing air valve and then steam
valve.
• Note the final value of vacuum at which it stabilizes (0.92 kg/cm 2) and
also note HPT/IPT & LPT differential expansions
Warming of Steam Piping
Checks :
Ensure all the drain valves M.S., CRH and HRH lines are open
M.S. line to be charged when drum pressure is raised to
10 kg/cm2 after blow-down
Operation :
Charge the M.S. line by opening the boiler outlet bypass valves
(MS 301A/302A)
Ensure that there is no hammering in M.S. pipeline
Watch the temperature rise of ESV mid wall
Rate of heating of steam pipelines should not exceed 25 o to 30oC
per 5 min.
During heating of M.S. & R.H. steam pipelines; the temperature
difference between LHS & RHS pipelines should not exceed
15oC. But this difference should not exceed 10 oC when the set is
on load
HP-LP Bypass System Charging
Checks :
• Ensure that HP Bypass control oil pumps are running on auto and
maintaining the pressure oil pressure 110 kg/cm2 and oil tank level is
normal
• All the oil supply/return/leak-off Sulzer valves are open and there is no oil
leakage in the system
• ESV and IVs are closed
• Cooling water to HP BP valve gland from CEP is open
• Isolating spray valve before BD valve is open and BD valve is closed on
auto. Ensure that it is not passing.
• All controls of HP bypass are on manual mode and all valves are closed.
• Ensure power supply to HP BP panel is normal
• Ensure that control oil pressure to LP bypass station is > 5.5 kg/cm2
• All manually operated & auto injection water valves (V1, V2, V3, V4) of LP
bypass station are closed.
• All the drain valves of HP &LP bypass are open
• Ensure condenser vacuum is > 0.75 kg/cm2
• BFP & CEP are running and discharge header pressures are adequate
HP-LP Bypass System
HP-LP Bypass System Charging
Operation :
Set the fixed pressure set point of LPBP at 3 kg/cm2
Put the LP Bypass controller on “Auto”
Make the automatic control interface "ON"
Ensure drain valves of CRH, HRH and Warm-up valves are
open
Open HPBP warm-up valves locally.
Set the pressure master set point at 35 kg/cm2
Put spray water control valves BPE1 & BPE2 of HPBP on
“Auto”
After warming up for 15 min. open HPBP valves BP-1 and
BP-2 about 5%.
Increase the BP1 & BP2 position manually in a step of 5%
Check that LPBP valves and injection water valves open on
auto to maintain HRH pressure
HP-LP Bypass System Charging
Operation contd… :
Close LPBP warm-up valve
When LPBP position goes to 25% increase the oil-firing rate in
boiler by taking into service CD oil elevation pairs 1-3 & 2-4.
When the controller demand of HP BP matches with BP 1 and BP2
actual position, put BP1 and BP2 on auto to maintain M.S. pressure
as per the set point.
Automatic control interface of LP bypass will increase the fixed
pressure set point value to 12 kg/cm2 and then it will be off.
Check the following parameters :
HRH pressure which maintains at 10 –12 kg/cm 2
CRH temperature after attemperation which should rise
M.S./HRH temperature should rise
The steam parameters suitable to turbine condition are build-up
through this process to get the required steam temperature and
flow at preset pressure before rolling of turbine
Turbine Start-up