Professional Documents
Culture Documents
03-01 Cost Risk Analysis (CRA) - CRA Workshop Presentation Template
03-01 Cost Risk Analysis (CRA) - CRA Workshop Presentation Template
03-01 Cost Risk Analysis (CRA) - CRA Workshop Presentation Template
Location
date
Probability / Likelihood
1 2 3 4 5
Very Low Low Medium High Very High
0 - 5% 5 - 20% 20 - 50% 50 - 80% 80 - 100%
Impact:
5 10 15 20 25 5
100% 1463
200
95% 1294
90% 1254
180
4 8 85% 1233
12 16 20 4
80% 1215
160
75% 1203
140
3 6 70% 1191
9 12 15 3
65% 1181
60% 1173
120
Cumulative Frequency
H1190 - Engineering/Manufacturing MOBO/Caisson - All 44%
55% 1166
2 4 6 8 10 2
Hits
50% 1154
100
H1760 - Engineering/Manufacture of ALM 30%
45% 1147
35% 1132
60
1 2 3
H1034 - Engineering/Manufacture Xtree Systems #1through #11 - All
30% 1124 4 5 22% 1
25% 1117
A2350 - Engineering/Manufacture Xtree Systems - First One Ready far Delivery 13%
40 20% 1105
20 10% 1082
Facilitator
Job Title
Safety Moment
Agree Cost Risk Ranges & Identify Correlations between cost line items
Way Forward:
Brainstorming • Triangular
• Personnel from Including
Optimism and Risk Register to • Uniform
Risk ranking • Schedule
Key Disciplines Pessimism around • Discrete
• Structured based on • Cost Estimate
deterministic values • Other
• Prompt Lists Probability/Impact
As many
Schedule: PRA • Modelling Logic Based on review Modify Assumptions/ iterations
Cost: @RISK • Result P10; P50; P90
• S-Curves
findings; current Distributions to as required
• Spread Validity info and Understand
• Tornado Charts • Key Drivers benchmarks Sensitivities
Deterministic
Method having an outcome that is
based on single values for each
parameter (input).
SINGLE
OUTCOME
Probabilistic
Method used to generate a full range
of possible outcomes that is based on
uncertainty ranges and discrete risk
assumptions.
MANY
OUTCOMES
Uncertainty (or Risk & Opportunity) can manifest itself in one of two
ways:
Uncertain Performance which is reflected in a range of possible
outcomes depending on several considerations, e.g. Productivity, scope,
price etc.
Uncertain Events which have alternative outcomes, pass or failure of a
test as an example.
X% Risk Occurs
%
Risk / Opportunity
Mapping
R 1 .2 8 : C ontinge nc y c a s ing R 1 .8 : M a jor Los s Tim e Inc ide nt (not c ov e R 3 .1 : U nc e r ta in W e ll Loc a tions
Triangular:
0.00 1.50 3.00 4.50 6.00 0.00 1.50 3.00 4.50 6.00 0.00 200.00 400.00 600.00 800.00
Uniform:
Number of Days
40.000
Discrete: 30.000
20.000
10.000
.000
2.00 2.75 3.50 4.25 5.00
80 % %
Positive:
Activity Duration
80 %
%
Activity Duration
Negative:
%
20%
Activity Duration
P10 / P90
But consider P0 / P90 where applicable or
Agree minimum Range Delta between Optimistic & Pessimistic (to be used as a
guide) to counter the tendency to underestimate the uncertainty ranges
Suggestion (pre FID): 30 – 35 basis points, e.g. –5% / +30%
Consider the 3 general sources of Uncertainty for each line item when making
the assessment
Scope / quantity
Productivity (excluding cost of schedule delay as the result of the schedule risk
analysis be included in the cost risk analysis separately)
Price as well as Benchmarks !!!
Copyright of Shell P&T Cost Risk Analysis 01/01/2024 13
COST UNKNOWN-UNKNOWNS
Minimum: 85.6
P50: 109
Maximum: 146.9
23.5% chance of values
being less than 100
Minimum: 95
P50: 113.3
Maximum: 145
10% chance of values
being less than 100
For the Answer, change font color from White to Black in the "Answer" Column
Minimum Most Likely Maximum Group Score Answer
The original cost estimate of the
1 Sydney Opera House was $7 m. $102 m
What was the final cost?
The original cost estimate of the
2 Channel Tunnel was £ 6.1 bln. What £11 bln
was the final cost?
The original cost estimate of the
3 Denver International Airport was $2 $4.8 bln
bln. What was the final cost?
The original cost estimate of the
Scottish Parliament Building was
4 £414 million
between £10 - £40 million. What
was the final cost?
How many tulip bulbs were planted
5 in Keukenhof gardens in 2003 (mill) 7 million