DSR - Costing Process, Cost Planning Control - Week 12

You might also like

Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 22

THE COSTING PROCESS,

COST PLANNING &


CONTROL
RMK 363 – CONSTRUCTION ECONOMICS
Cost Management

• Construction Cost Management is the establishment of realistic


capital costs of construction projects.

• It embodies detailed cost planning and cost control services to


ensure construction projects are bid, documented and completed
within a pre‐agreed cost framework and in the most economical
manner consistent with program requirements and aesthetic
considerations.

• A Cost Manager or Quantity Surveyor uses their engineering


judgment and experience in the application of scientific
principles and techniques to analyze and develop the best course
of action in regard to cost estimation, cost control and
profitability of the project.
Cost Management

• Using cost management principles, the Cost Manager or


Quantity Surveyor ensures a project is designed within budget
objectives and meets performance and quality goals.

• The Cost Manager or Quantity Surveyor will work with the


design team to establish the program budget or confirm the
established budget.
Introduction to Estimating

• What is it?
- Calculation of amount of work & expenses that are likely to
occur. It therefore would indicate the approximate of the actual
project cost.

• What is calculated?
- Cost for material, labour, plant and time needed to execute a
project.
Introduction to Estimating (Cont’d)

• Why is it important? – Mistake in estimation could lead to:

- Cost overrun – due to miscalculating amount of works to be


done @ under-estimating works

- Time overrun – missing item / work elements needed to be


done lead to variations thus, extra time is needed to complete
the added works.

- Lose on quality
a. Cost overrun may lead to parties compromising on quality.
b. Shortage of budget could lead to cutting down in budget
thus affecting quality level. / lowering quality specification.
Purpose of Estimating

- The first requirement of any project.

- Help client to decide whether to proceed or abandon the


project
 Depends upon availability of clients budget and resources;
 If a developer is involved, prospective sales ability could
also be accounted.

- To enable decision on procurement method, for example if a


project is of high uncertainty, then a lump-sum approach may
be more appropriate.
Important Information / Data for Proper Estimating
- All relevant drawings, plan, section and details of the
proposed project. These documents should have proper details
to improve accuracy.

- All relevant specifications including details on materials and


construction method to be applied. An information on material
alternatives (in case of unavailability) would also be useful.

- Estimating approaches as required by the client / the ones best


suite the available details.

- Pricing method / rates to be applied for estimating


Techniques of Estimating During the Design Stages

• Functional unit method


• Superficial method
• Cube method
• Functional area method
• Storey enclosure method
• Approximate quantities method
• Elemental method

8
Functional Unit Method
Cost per functional unit:
(Used at Brief Stage)

• Schools, universities, colleges - per student


• Hotels, hospitals - per bed
• Restaurants, cinemas - per seat
• Car parks - per car

Example:A Hospital of 640 beds


Cost per bed = $16,000

Total estimated cost = 640 x $16,000 = $10,240,000

9
Functional Unit Method (Cont’d)
Cost per functional unit:
(Used at Brief Stage)

• Disadvantages:
- Difficult to allow for effects of design decisions such as plan
shape, storey height, quality, etc
- Separate allowance must be made for site works and external
services

10
Superficial Method
Cost per square metre of floor area:
(Used at Brief and Outline Proposal Stage)

• Advantages:
- Unit is meaningful to all parties
- Most cost data is published in $/m2
- Estimates are quickly and easily prepared

Example:Project of 852 m2 floor area


Cost per m2 = $1,106

Total estimated cost = 852 x $1,106 = $942,312

11
Superficial Method (cont’d)

• Disadvantages:
- Difficult to allow for effects of design decisions such as plan
shape, storey height, quality, etc
- Separate allowance must be made for site works and external
services
Cube Method

Cost per cubic metre of building volume:


(Used at Brief and Outline Proposal Stage)

• However, this method is already obsolete!!

• Example: Project of 16,000 m3


Cost per m3 = $325

Total estimated cost = 16,000 x $325 =


$5,200,000

13
Functional Area Method

Cost per square metre of functional area:


(Used at Brief and Outline Proposal Stage)

• More accurate than simple superficial method

• No published cost data

• Useful only for client body involved in continuous and


consistent program of similar projects such as:
- Primary and Secondary schools (Ministry of Education)
- Hospitals and medical/community centres (Ministry of
Health)

• Not useful for “one-off” projects 14


Functional Area Method (Cont’d)

Cost per square metre of functional area:


(Used at Brief and Outline Proposal Stage)

Example:Project of 852 m2 functional area


Cost per m2 = $1,106

Total estimated cost = 852 x $1,106 = $942,312

• Disadvantages:
- Difficult to allow for effects of design decisions such as plan
shape, storey height, quality, etc
- Separate allowance must be made for site works and external
services
15
Storey Enclosure Method

Cost per square metre of building envelope:


(Used at Brief and Outline Proposal Stage)

• However, this method is already obsolete!!

• Uses single price rate similarly to functional unit and


superficial methods

• Incorporates cost effect of design features such as height and


shape

16
Elemental Method

(Individual elements used at Sketch Design and Tender Document


Stage) & (Element groups used at Outline Proposal Stage)

• Element cost are expressed in:


- Percentage of total building cost
- Cost per m2 of gross floor area
- Unit rate per m2 of element
- Total element cost

17
Elemental Method (Cont’d)
• Advantages:
- Flexible, adaptable method, suited to Outline Proposal,
Sketch Design and Tender Document Stages.
- Easily understood by all parties
- Facilitates comparison between projects
- Facilitates analysis of cost implications of design decisions

• Disadvantages:
- Time-consuming
- High level of expertise required

18
Approximate Quantities Method

(Used at Sketch Design and Tender Document Stage)

• Not single price rate method


• Simple, reliable and most accurate method
• Uses actual construction rates for each group of related items
• Responds to the current quantity & quality of material
• Can clearly reflect adjustments of quantity and/or quality
• Cost data readily available
• Time-consuming
• A more acceptable method by the QS if all necessary
information is available
• Applicable only in later stages of cost planning

19
Sources of Cost Data

• Rawlinsons Australian Construction Handbook


(published annually, index updated quarterly)

• Cordell’s Building Cost Guide (published quarterly)

• The Building Economist (published quarterly)

20
Good Practice in Performing Estimating

• Recognise that design does not proceed uniformly across all


elements

• Use both rough and sophisticated techniques in the one estimate


if necessary

• Use an appropriate technique for each element

• Technique must reflect amount and quality of information


available

21
Characteristics of a Good Estimator
• A good estimator should:
- Apply correct estimating method
- Have good understanding on drawings & able to properly visualize
works.
- Able to predict or avoid the unexpected.
- Understands construction materials, methods and systems, as well as
the labor and equipment required to complete all tasks in their correct
sequence, on time and on budget.
- Being a systematic, careful and vigilant person would be an added
value for an estimator.
- Have sound knowledge of estimating principles.
- Have sound knowledge of Standard Method of Measurement.
- Carrying out estimates in proper sequence – starting from taking off
quantities  squaring  abstracting  pricing / estimating.

You might also like