Progress TPDM 2023 & Next

Action 2024
Subsurface Data Management
JOB Pertamina Medco E&P
Tomori, Sulawesi
INTRODUCTION
Tomori Petrotechnical Data Management (TPDM) is a system to manage the
subsurface data and deliver the information respectively. The scope of work of the
system are:
• Centralize Subsurface Data System
• Standardize the Subsurface Digital Data
• Digitalize the Hard Copy Dataset
• Extract and Display on web-application
DATA Digital Data Management

USERS

What can we do
with the data?
Issues Consequences Solved?

Multiple
“Gold” version
Duplicates uncontrolled
of data
data

Scattered Difficult to Centralized


location access Database

Indexed
Slow search Not aware
datasets
WORKFLOW

Data Management

TPDM Development

Data Digitalization

Maintenance and Evaluation


DATA STANDARDIZATION
Legacy Dataset: SEGY, PDF, LAS, JPG, DWG, etc.

This naming format is only intended for the file that will be
stored in the database server. (the golden version).

All the managed data will be renamed using the pre-defined


format discussed with user.
Textual/Tabular Dataset: Metadata, extracted information from files
Textual/Tabular Dataset: Metadata, extracted information from files
Textual/Tabular Dataset: Metadata, extracted information from files

PPDM v.3.9 already adapted to the


SQL database used in the TPDM
system

Database imported from PUDC (MDR format) was not included to the inhouse PPDM database.
Temporary db is created for the current phase of database integration.
DATA CENTRALIZATION

Folder scheme used for TSDM subsurface data center.


Seismic folder scheme is soon to be revised (Input from IT department to avoid storage issue in the server that might harm the
application process).
Folder scheme used for ‘Field’
Data Request from Medco database:

Data from Medco database already sorted and waiting approval for the data. Cross-checking with the inhouse data availability is on
process inline with the data digitalization progress (scanning hardcopy data from SIGMA)
DATA DIGITALIZATION
Reorganization hard copy well data acquired from Sigma

Requested data from Sigma has


been sorted into new boxes
according to well name.
DATA DIGITALIZATION – PROGRESS
• Scanned consists of all well log hardcopy data records belonging to SIGMA + JOB that has been digitalized
• Remaining consists of In-House JOB Tomori Data that is yet scanned (as per 03/11/23)
DATA DIGITALIZATION – SIGMA Well Log Data
• Total scanned well logs data (hardcopy) acquired from Sigma: 182 data – ALL SCANNED.
• Mainly consisting of the following wells: Tiaka-1, Tiaka,-2, Tiaka-3, Tiaka-4.
All scanned SIGMA well logs data are accessible through JOB-Tomori Clouds.
Details on each well logs file names and respective depths is also recorded.
DATA DIGITALIZATION – JOB TOMORI Well Log Data
• Total In-House well logs data (hardcopy) existing in JOB Tomori: 181 data
• Data scanned by Request JOB was done in June 2023, meanwhile In-House JOB Tomori
data was received in September 2023 and currently still in scanning process
Scanning process is ongoing for Well Log Data and Well Reports
Digitation on the scanned
Well Log to LAS data
WEB-APPLICATION

• Actual data will be added frequently (including the newly digitalized data)
• The web-application is online at tsdm.job-tomori.com and accessible for every TPD staffs
• Production data dashboard is on progress (utilization SCADA using API for production data
parameters is done, now working on production allocation dashboard and features)
• Seismic viewer feature is accessible, improvement on the feature will be done soon after the
storage is ready.
WEB-APPLICATION INTERFACES
TPDM DASHBOARD INTERFACE

Di halaman dashboard terdapat beberapa fitur


untuk melihat maps, gas production chart dan
beberapa chart yang ada di halaman dashboard
TPDM DASHBOARD INTERFACE

Di halaman individual well terdapat chart


data scada ( yang sudah Terisi otomatis)
dan terdapat juga petrophysisc log
Web Browser Interface

lalu di dalam data browser kita dapat melihat beberapa data well data , seismic data , study dan lain lainnya yang
dapat kita klik untuk melihat data .
File Explorer Interface

File Explorer Interface dapat di gunakan membuka file yang terdapat di halaman TPDM
TIMELINE vs REALIZATION

Due to Covid situation, data digitalization and integration were not able to be executed, thus the amendment
was proposed on this project to finalize these tasks. TPDM features development is included during this
period.
Amendment Timeline:
PHASE 1 DELIVERABILITY:
• The Web-Application has been successfully launched and is undergoing continuous development to
incorporate additional features.
• A centralized data scheme has been established on the development server to facilitate streamlined
data management.
• Data standardization is continuously discussed accordingly
• PPDM database adaptation is completed with modifications tailored to meet specific needs of the
system.
• Digitalization of hard copy data consisting of Well Logs and Well Reports is ongoing
• Digitation of Well Log data from scanned image files to las data is ongoing
PHASE 2
Technical Planning 2023 – Subsurface (PE)
Program Tomori Petrotechnical Data Management Development
PROGRAM TYPE OBJECTIVES TIME SCHEDULE
Month
• Continuously developing Tomori Petrotechnical Data No. Description
1 2 3 4 5 6 7 8 9 10 11 12
OPEX Single Year New Management Adding features
• Adding more tailored features on the Web- 1 onto the interactive
dashboard
Application for ease of analytical purpose for the
BUDGETARY (ribu US$) production team System
2 maintenance and
• Indexing dan catalouging data records based on development
Real YTD Outlook Proposed Total
2022 2023 2023 2023 Project PPDM 3.9. Indexing dan
Catalouging
• Digitalizing and digitizing hard copy Well Log data 3 database based on
- - - 138 138 emphasizing on prioritized wells PPDM 3.9
Digitalizing and
4 digitizing work

BACKGROUND SCOPE OF WORK REMARK


• JOB Tomori Petrotechnical Data Management was • Implementing an Interactive Dashboard to streamline data
established to accommodate all subsurface and well data entry for JOB Tomori users within the system.
• Many inconsistencies were found between hard-copy • Performing maintenance and improving system’s
database index with the ‘actual’ documents stored, some performance
of which have not yet been digitized. • Performing the task of updating/standardizing well
• The need for developing and maintaining JOB Tomori sketches and digitizing well logs from hard copy datasets.
Petrotechnical Data Management System. • Digitalization and digitization of data
Objectives

• Continuously developing Tomori Petrotechnical Data


Management
Objectives

• Adding more tailored


features on the Web-
Application for ease of
analytical/well
monitoring purposes
for the production
team
• Indexing and cataloguing data
records based on PPDM 3.9