RAILWAY CONSTRUCTION PROJECTS

IN
CHHATTISGARH

Chief Engineer (Construction)


East Coast Railway, Jagdalpur
1
PRAGATI TDC- Jan 25
Jagdalpur - Kirandul (150 Km) Doubling

2 2
PRAGATI TDC- Jan 25
Jagdalpur - Kirandul doubling (150 Km) TDC Jan’25

Year of Sanction 2011-12


Sanctioned Cost (Cr) 1440
Exp. upto Mar’23 (Cr) 1199
Outlay 2023-24(Cr) 135
Exp. during 2023-24 (Cr) 103
3
STATUS OF THE PROJECT

 Till date total length commissioned : 106.344 Km out of total 150 Km.

 Planning to commission during this FY-2023-24 : 21.496 Km


(Dantewara - Kamalur & Bacheli – Kirandul)

 Dantewara – Kamalur track linking 9 km done out of 12.353Km.

 Bacheli – Kirandul 8 Km track linking done out of 9.143Km.

 For the balance two block sections of length 21.974 Km, works are in progress and
planning to commission in Jan’2025.
Issues with State Government of Chhattisgarh.
• Maoist activities are largely affecting the progress of works. Incidences of frequent
calls for stoppage of works, burning of contractor’s machinery in few occasions,
threatening to staff working in the project and frequent disturbances by Maoists/Local
villagers are affecting the progress of work.

• Providing security in the balance locations of Dantewada- Kirandul section i.e.


partially between Kamalur-Bhansi stations and partially between Bhansi - Bacheli
stations, where security permission is not yet accorded.

• To allow at least 8 hours of working time at site every day for execution of works.

• Permission for construction of camps at two locations (already identified jointly with
Local Police officials) for staying of security forces.
PRAGATI
Jagdalpur - Kirandul (150 Km) Doubling
Bacheli - Kirandul (DL) (9.05 Km) TDC- 02/24
Activity Scope Completed TDC
ESP 2 Stn 2 Stn Approved
SIP 2 Stn 2 Stn Approved
Utilities Shifting
Availability of Agencies Available
Earthwork 256000 cum 256000 cum Completed
Blanketing 37000 cum 37000 cum Completed
Major Br. including ROB 2 Nos. 2 Nos Completed
Minor Br incl RUB/LHS 27 Nos. 27 Nos. Completed
Station Building 01 No. 01 No Completed
Ballast Supply 35000 cum 35000 cum Completed
Track Linking 9.14 TKM 8.0 TKM 01/24
S&T Work EI : New 2 45% 01/24
OHE Work 9.05 TKm 20% 02/24
Critical Issues Frequent stoppage of works and bandhs by Maoist.

6
PRAGATI Jagdalpur - Kirandul (150 Km) Doubling
Dantewada - Kamalur (DL) (14.50 Km) TDC- 02/24
Activity Scope Completed TDC
ESP 2 Stn 2 Stn Completed
SIP 2 Stn 2 Stn Completed
Utilities Shifting
Availability of Agencies
Earthwork 244000 cum 244000 cum Completed
Blanketing 36000 cum 36000 cum Completed
Major Br. including ROB 2 Nos. 01 No. 01/24

Minor Br incl RUB/LHS 38 Nos. 38 Nos. Completed


Station Building 01 No. 01 Nos. Completed
Ballast Supply 37000 cum 37000 cum Completed
Track Linking 12.35 TKM 9.0 TKM 01/24
S&T Work EI : New1, Alt 1 80% 01/24
OHE Work 14.50 TKm 20% 02/24
Critical Issues Frequent stoppage of works and bandhs by Maoist.

7
PRAGATI
Jagdalpur - Kirandul (150 Km) Doubling

Kamalur - Bhansi (DL) (12.4 Km) TDC- 01/25


Activity Scope Completed TDC
ESP 2 Stn 0 Stn (ESPs approved. Phasing to be
done)
SIP 2 Stn 0 Stn
Utilities Shifting
Availability of Agencies
Earthwork 291000 cum 10000 cum 11/24
Blanketing 39000 cum 1000 cum 11/24
Major Br. including ROB 2 Nos. 0 No. 11/24
Minor Br incl RUB/LHS 44 Nos. 2 nos. 10/24
Station Building 01 No. 0 10/24
Ballast Supply 42000 cum 0 cum 10/24
Track Linking 12.40 TKM 0 TKM 01/25
S&T Work EI : New1, Alt 1 0% 01/25
OHE Work 14.50 TKm 0% 01/25
Critical Issues No working permission by Local police.
Frequent stoppage of works and bandhs by Maoist.
8
PRAGATI
Jagdalpur - Kirandul (150 Km) Doubling
Bhansi - Bacheli (DL) (10.1 Km) TDC- 01/25
Activity Scope Completed TDC
ESP 2 Stn 0 Stn (ESPs approved. Phasing to be
done)
SIP 2 Stn 0 Stn
Utilities Shifting
Availability of Agencies
Earthwork 317000 cum 40000 cum 11/24
Blanketing 46000 cum 0 cum 11/24
Major Br. including ROB 1 No. 0 No. 11/24
Minor Br incl RUB/LHS 35 Nos. 7 nos. 10/24
Station Building 0 0 -
Ballast Supply 35000 cum 0 cum 10/24
Track Linking 10.10 TKM 0 TKM 01/25
S&T Work EI : Alt 2 0% 01/25
OHE Work 14.50 TKm 0% 01/25
Critical Issues Frequent stoppage of works and bandhs by Maoist.
9
PRAGATI
CRITICAL
Koraput - Jagdalpur (106 Km) DL

10 10
PRAGATI TDC: Mar 24
CRITICAL Koraput – Jagdalpur doubling (106 Km) RTDC- Jan 25

Year of Sanction 2015-16


Sanctioned Cost (Cr) 1547.38
Exp. upto Mar’23 (Cr) 937
Outlay 2023-24(Cr) 170
Exp. during 2023-24 (Cr) 109
11
STATUS OF THE PROJECT

 Till date total length commissioned: 85.265 Km out of total 106 Km.

 Length in Chhattisgarh is 24 Km; Length in Odisha is 82 Km

 Chhattisgarh length 24Km commissioned.

 Balance two block sections (20.612Km), works are in progress. Jarati – Maligura consists
of 6 tunnels and tunneling is in progress.

 Planning to commission of the balance two block sections:


Manabar – Jarati (9.207Km) : May’2024
Jarati – Maligura (11.405Km) : Jan’2025