Professional Documents
Culture Documents
SPARC Course IIT D DH Solar Co Simulation Part2 March 2021 VV
SPARC Course IIT D DH Solar Co Simulation Part2 March 2021 VV
SPARC Course IIT D DH Solar Co Simulation Part2 March 2021 VV
4
Integrated transmission and distribution
system modeling
5
Integrated transmission and
distribution system modeling
6
Integrated transmission and distribution system
modeling
• Although transmission systems can be assumed to be
physically three-phase balanced, the typical assumption that
the boundary conditions at the interfaces between
transmission and distribution systems are reasonably
balanced is not always valid, particularly in dynamic
simulation
• In this context, the transmission system should be
represented in either three-sequence or three-phase detail
• To avoid the modeling and computational complexity
involved in three-phase representation and to effectively
reuse the existing sequence component-based models and
simulation algorithms, the transmission system is modeled in
three-sequence in this research
7
Power flow algorithm for integrated transmission
and distribution system
• The proposed TDPF algorithm is formulated based on a
master-slave approach, with the power flow of the
transmission system as the master problem and the power
flow of the distribution systems as the slave problem
• The key enhancements over previous efforts include:
8
Power flow algorithm for integrated transmission and
distribution system
• The boundary information exchanged between the
transmission and the distribution systems during the
integrated power flow solving process is illustrated
in the figure below
Transmission
Bus i (3-sequence) Bus k
LoadPQk(1)
VBiabc LoadPQi(1) VBkabc Iinjk(2)
Iinji(2)
Iinjk(0)
Iinji(0)
Distribution Distribution
(3-phase) ... (3-phase)
9
Power flow algorithm for integrated transmission and distribution system
10
Power flow algorithm for integrated transmission and distribution system
(1)
(2)
13
14
Dynamic simulation for integrated
transmission and distribution system
• The dynamic simulation of power systems can be
mathematically described as a solution to a set of
differential-algebraic equations (DAEs)
(3)
(4)
16
Dynamic simulation for integrated transmission and distribution
system
18
Dynamic simulation for integrated transmission and
distribution system
• A special network solution approach, which is
capable of accommodating multiple sub-systems
and distinct network representation of each
subsystem, is needed at the network solution step
• The multi-area Thévenin equivalent (MATE)
concept is developed based on the diakoptics
concept and the formulation of a modified nodal
analysis (MNA)
• MATE reformulates and extends the diakoptics
approach to make it easier to understand and
program into an algorithm
19
A schematic illustration of the MATE approach
20
Dynamic simulation for integrated transmission and distribution
system
22
Coordination of the subsystem simulation solutions through the link
subsystem using the MATE approach
23
Three-Phase Dynamic Simulation
Developed by extending existing three-sequence system
modeling and TS simulation
• Modeling: Inheritance and the adapter design pattern
• Simulation procedure: the same as the positive-sequence TS except for
the three-phase oriented network solution
Three-phase modeling
Power
Transmiss- Induction
Transformer Static loads Generator electronic
ion line machine
devices
A
A
A
C
A
C
0 | C
0 | C
2 | B
2 | B
B
1
1
1
0
1
0
Power
Transmiss- Induction
Transformer Static loads Generator electronic
ion line machine
devices
Three-sequence modeling
Development of three-phase machine dynamic
Transformation from three-sequence modeling model based on the corresponding three-sequence
to three-phase modeling model using the adapter pattern 24
Performance
Performancemodel of single-phase
model A/C motor
of single-phase A/C motor
Two operating modes: run and stall
Critical performance parameters:
• V5stall (0.50~0.65 pu), Tstall (2 ~ 53 cycles)
4 4
3 3 Stall
Stall
2 2
Run
1 Stall 1 Stall
Run
0 0
0 0.2 0.4 0.6 0.8 1 0 0.2 0.4 0.6 0.8 1
Voltage (pu) Voltage (pu)
Vt A/C performance
algebraic equation Norton
freq Norton current
and protections
Equivalent
p, q source
time
25
The MATE Based T&D dynamic simulation
The 3-sequence coordinate system is used at the MATE based network
solution coordination stage
The transmission system can be further split into subsystems represented
either in 3-phase or 3-sequene detail
The subsystem where an unbalanced fault is applied must be represented in
three-phase detail
Subsystem k Parallelism
Subsystem i
in the
Integration step ... Integration step subsystem
solutions
Subsystem MATE based Subsystem
network T&D network network
solution solution solution
Consider unbalanced
fault(s) in transmission
system
27
Test Cases
IEEE 9 bus system + 3 distribution systems T9D3
IEEE 39 bus system + 6 distribution systems T39D6
Distribution bus re-numbering:
28
Bus 8
230 kV
Bus2 Bus 7 100+j35MVA Bus 9 Bus 3
18 kV 230 kV 230 kV 13.8 kV
G2 G3
192MVA 128MVA
Bus 5 Bus 6
230 kV 230 kV
125+j50MVA
90+j30MVA
Bus 4
230 kV
Bus 3
16.5 kV
G1
247.5MVA
IEEE 9 bus system 29
A portion of the IEEE 39 bus system
30
Test the proposed integrated T&D power flow (TDPF)
algorithm
T9D3 test case Voltage magnitude (pu) Voltage angle (degree)
bus TDPF PSCAD TDPF PSCAD
TDPF vs PSCAD 4 1.028 1.028 -2.23 -2.24
Transmission 5 1.002 1.001 -3.98 -4.02
6 1.014 1.013 -3.81 -3.82
• Positive sequence
7 1.028 1.027 3.56 3.52
Distribution 8 1.018 1.017 0.51 0.49
9 1.033 1.033 1.78 1.79
• 3 phases
Number of iterations
Test case Scenario
between T and D
β=0 3
T9D3 β = 5% 3
β = 10 % 3
β=0 3
T39D6 β = 5% 3
β = 10 % 3
32
Benchmarking integrated T&D dynamic simulation
T9D3: constant impedance loads
Voltage (pu)
1
TDDS vs PSCAD TDDS
phase A PSCAD
A SLG fault applied at 69 kV bus 50 at 0.5
1.0 s, cleared after 0.07 s 0.5 1 (a) 1.5 2
Voltage (pu)
1
1 TDDS
Positive (TDDS) phase B PSCAD
Positive (PSCAD)
0.5
0.8 Negative (TDDS) 0.5 1 (b) 1.5 2
Voltage magnitude (pu)
Negative (PSCAD)
Voltage (pu)
Zero (TDDS)
0.6 Zero (PSCAD)
1
TDDS
0.35 PSCAD
0.4 0.3
phase C
0.5
0.25
0.2 0.5 1 (c) 1.5 2
0.2
0.15
Time (s)
1 1.02 1.041.061.08
0 3-phase line to ground voltages of bus 52
in the distribution system served by bus 5
0.5 1 1.5 2
Time (s)
3-sequence voltages of bus 5
33
Applied to FIDVR study under unbalanced conditions
T39D6 test case
• Load composition in the distribution systems: 50% A/Cs + 50% constant impedances
• A/C performance model: Vstall = 0.65 pu, Tstall = 0.033 s
• A SLG fault applied on phase A of bus 17 at 1.0 s, cleared at 1.07 s
Line-to-neutral voltages of 69 kV bus 150
Voltage (pu)
1
0.8 Phase A
Phase B
0.6 Phase C
0.4
0.95 1 (a) 1.05 1.1
Line-to-neutral voltages of 12.5 kV bus 151
Voltage (pu) 1
Phase A
0.8
Phase B
0.6 Phase C
0.4
3-phase voltages of 0.95 1 (b) 1.05
Line-to-neutral voltages of 12.5 kV bus 158
1.1
buses in the
Voltage (pu)
status
1 0
Bus 151 -1
0 5 10 15 20 25
0.8 Bus 152 (a)
A/C motors connected to phase A of bus 153
Bus 153 1
status
Bus 154 0
0.6 Bus 156 -1
0 5 10 15 20 25
Bus 158 (b)
A/C motors connected to phase A of bus 154
0.4 1
status
0 5 10 15 20 25 0
(a) -1
0 5 10 (c) 15 20 25
1 A/C motors connected to phase A of bus 155
Voltage magnitude(pu)
status
0
-1
0.8 Vstall 0 5 10 (d) 15 20 25
A/C motors connected to phase A of bus 156
1
status
0
0.6 -1
0 5 10 (e) 15 20 25
A/C motors connected to phase A of bus 157
1
0.4 status 0
0.98 1 1.02 1.04 1.06 1.08 1.1 -1
(b) 0 5 10
(f) 15 20 25
A/C motors connected to phase A of bus 158
Time (s) 1
Phase A voltages of the distribution buses
status
0
-1
served by bus 15 0 5 10
(g)
15 20 25
Time (s)
35
Impacts of the FIDVR event on distribution systems
Currents flowing from transmission system into 69 kV bus 150
6
Phase A
Phase current (pu)
5 Phase B
Phase C
4
2
0 5 10 15 20 25
Time (s)
Currents flowing from transmission system into 69 kV bus 150
6
Phase current (pu)
2
0.95 1 1.05 1.1
Time (s)
36
Impacts of the FIDVR event on distribution systems (2)
1
Bus 158
Bus 168
Bus 188
0.8
0.7
A/C
0.4
0.6
stalling
No A/C stalling in
the distribution 0.2 0.5
systems served by
0.4
buses 26 and 28 0
1 1.1 1.2
0 5 10 15 20 25
Time (s)
Phase A voltages of the buses at the end of feeders
37
Impacts of the FIDVR event on transmission system
1.1
Sequence voltages of
transmission buses 15, 27 1
Voltage(pu)
and 28: Bus 15
0.95
0.9 Bus 27
(a) positive sequence 0.9
Bus 28
0.85
0.8 0.8
0.75
0.7 1 1.2
0 5 10 15 20 25
0.2
(a)
0.15 Bus 15
0.15 Bus 27
Voltage(pu)
0.1 Bus 28
0.1
(b) negative sequence 0.05
0.05 1 1.2
-0.05
0 5 10 15 20 25
(b)
Time (s)
38
Impacts of load unbalance and load composition unbalance
0.8 Phase B
0.8 bus 5:
Phase A 320 MW
0.6 Phase B
β = 5%, and α = 0 β = 5%, α = 0
0.4 Phase C phase load:
0.2 A: 106.7 MW, 50% A/C
0 5 10 (a) 15 20 25 B: 101.3 MW, 50% A/C
C: 112 MW, 50% A/C
1 β = 5%, α = 5%
Voltage(pu)
Phase A
Phase B Total load at the
5 Phase C
substation of bus 5:
base case 320 MW
0
0 5 10 15 20 25 Base case: 3-phase balanced,
Time (s) 50% A/C
10 β = 5%, α = 0
Current (pu)
Phase A
Phase B phase load:
Phase C
5
β = 5% A: 106.7 MW, 50% A/C
α=0 B: 101.3 MW, 50% A/C
0
0 5 10 15 20 25 C: 112 MW, 50% A/C
Time (s) β = 5%, α = 5%
10 phase load:
Current (pu)
Phase A
Phase B A: 106.7 MW, 45% A/C
Phase C
5
β = 5% B: 101.3 MW, 50% A/C
α = 5% C: 112 MW, 55% A/C
0
0 5 10 15 20 25
Time (s)
Currents flowing into the distribution system at 69 kV bus 150 42
Problem statement
Stage 1
(0.5 – 1 s)
zoom in Stage 2
(6 – 20 s)
TS EMT-TS
Present:
t=0 Tswitch1 Ttotal t
Proposed: TS EMT-TS TS
The overall efficiency is not satisfactory for some cases where the
simulation has to be as long as 20 s
Proposed solution: switching back to TS simulation after fast dynamics in
the detailed system part settle down
Challenges: (1) initialization of the detailed system portion for simulation
at stage 3; (2) switching criteria; (3) minimizing the changes to the existing
simulation algorithms
43
Proposed approach
Maintain individuality of the detailed and the external systems
Two detailed system representations: EMT and 3-ϕ phasor
3-ϕ /3-sequence dynamic co-simulation for stages 1 and 3
Boundary bus
Detailed
External system
system
(a) Three-sequence
Three-sequence
Boundary bus Dummy boundary bus Thévenin equivalent Three-sequence phasor, Thévenin equivalent
network solution
Virtual Three-phase Three-sequence
Detailed breaker current injection link subsystem current injection
External system
system
3-phase
phasor, Three-sequence phasor,
(b) dynamic Detailed External TS simulation
Detailed External simulation system system
system system
3-phase
phasor
Three-sequence phasor
3-phase
point- Detailed
on-wave system (c) 44
Proposed approach(2)
Use of discrete event signals obtained from the EMT simulation to reconcile
the simulation results
Switching criteria
• Maximum boundary voltage difference less than tolerance for 2 cycles
• The maximum rate of change of boundary current injections less than tolerance
after 0.07 s G2
192MVA Bus 8
G3
128MVA
230 kV
Speed (pu)
Speed (pu)
0.6 Status(3 DS) 0.6 Status(3 DS) 0.6 Status(3 DS)
Bus 5 Bus 10 Bus 11 Bus 12
0.4 0.4 0.4 A
230 kV 69 kV 13.8 kV 13.8 kV
230 kV/69kV 69/13.8 kV B
0.2 0.2 0.2 150 MVA 150 MVA
C
10% 8%
Zfeeder
0 0 0 1-Ф A/C
motor
-0.2 -0.2 -0.2
0.5 1 1.5 2 0.5 1 1.5 2 0.5 1 1.5 2 Constant
Time (s) Time (s) Time (s) impedance
Load = 125 +j50 MVA
(a1) (a2) (a3)
1 1 1
1 1 1
Speed (pu)
Speed (pu)
Speed (pu)
Speed(EM T) Speed(EM T) Speed(EM T)
0.5 Status(3 DS) 0.5 Status(3 DS) 0.5 Status(3 DS)
0 0 0
0 0 0
0.5 1 1.5 2 0.5 1 1.5 2 0.5 1 1.5 2
Time (s) Time (s) Time (s)
(b1) (b2) (b3)
47
Test case (3)
Compared with hybrid simulation without switching back to TS
1.1
With switching back to TS Without switching back to TS
Voltage at bus 5 (pu)
1
1.002
0.9
Speed (pu)
With switching back to TS
0.8 Without switching back to TS 1
Generator at bus 1
0.7
0 1 2 3 4 5 6 7 8 9 10 0.998
time (s) 0 1 2 3 4 5 6 7 8 9 10
time (s)
1.1
Voltage at bus 7 (pu)
1 1.002
Speed (pu)
0.9 With switching back to TS
1
Without switching back to TS
0.8 Generator at bus 2
0.7 0.998
0 1 2 3 4 5 6 7 8 9 10 0 1 2 3 4 5 6 7 8 9 10
time (s) time (s)
Speed (pu)
Computation 1
Simulation method time for 10 s Generator at bus 3
simulation 0.998
0 1 2 3 4 5 6 7 8 9 10
Hybrid simulation without time (s)
switching back to TS simulation 189.2 s
Hybrid simulation with switching
back to TS simulation 15.4 s Speeds of the generators at buses
Three-phase dynamic simulation 1.2 s 1, 2 and 3
48
A new EMT-TS hybrid
simulation tool OpenHybridSim
has been developed and it is
open-sourced:
www.github.com/OpenHybrid
Sim
49
Overview