Presentation Fentoes
Presentation Fentoes
at
FENTONS LIMITED
Thennakoon T.M.N.S.
EG/2017/3232
Department of Mechanical & Manufacturing
Engineering
1 Faculty of Engineering-University of Ruhuna
OUTLINE
• Introduction to Fentons Limited
• Introduction to Proposed Office and Leisure Development
project (Renuka Project)
• Introduction to Marina Square Mixed Development Project
• Training Experience
• Health & Safety
• Problems Encountered
• Conclusion
2
Introduction to
Fentons limited
VISION
“To be the undisputed No.1 in all our business verticals in Sri Lanka and
be a leading player in the region”
MISSION
“To be a winning team that adds value to life through technology
enabled solutions whilst meeting the expectations of all stakeholders viz
customers/clients, shareholders, employees, environment and society.”
Introduction to
Fentons limited
Company Services
MEP (Electrical, Fire, HVAC, Plumbing, and & Lighting) solutions
Security & Surveillance (Extra Low Voltage Systems) solutions
ICT Solutions (Information and Communication Technology)
Facilities Management
Renewable Energy- Solar Power
4
Introduction to Proposed Office
and Leisure Development project
Project Details
5
Introduction to Proposed Office
and Leisure Development Project
About site
6
Introduction to Marina Square
Mixed Development Project
Project Details
7
Introduction to Marina Square
Mixed Development Project
About site
The Complex Will Be Developed On An Expansive Five-acre
Land Consisting Of 1068 Condos Over 36 Floors Across 5
Towers As Well As Having Two Acres Exclusively Allocated
For Recreational Facilities And Common Areas. Located
Minutes Away From The Anticipated Developments Such As
The Colombo International Financial City (Port City) And
Elevated Highway, Marina Square – Uptown Colombo Offers
Modern Living Spaces With Infinite ROI Possibilities And
Unmatched Rental Opportunities.
8
Training Experience
Sprinkler
Smoke detectors Extinguishers
Heat detectors Fire Alarm Systems
Isolator base The Water mist fire
Manual call point system
Addressable
Monitor Module 9
Training Experience
Sprinkler
10
Training Experience
Conduit Laying For Fire Detection System
Material Requirement
-PVC Conduits and Fittings - No conduit greater than 32mm
diameter
-Steel Conduit
-Flexible Conduit
11
Training Experience
Installation Procedure
1) Marking of all fire detection points on the slab formwork by referring the approved
shop drawings issued to the site.
2) Slab conduits wiring should be done in 1.3 mm thick 25 mm size Medium Duty PVC
conduits.
3) Conduit laying will be started once bottom net is in place and will be released for top
net once conduit laying is over.
4) Only Deep junction boxes shall be used in slabs. With Binding wire, properly bind the
PVC conduits.
5) Followed different color coding for junction boxes and conduits.
6) Use PVC solvent for jointing the accessories
12
Training Experience
Cont’d…….
7) Wall drops shall be properly checked for face of wall/beam.
8) All the conducting shall be checked as per services drawing
9) Special precaution shall be taken during concreting of slab.
- All broken pipes are to be replaced
- All joints have are to be watertight joints to avoid
choke up
10) Any choke up to be documented and alternate routing to be
shown in shop drawings and documented for future references.
11) All necessary sleeves shall be provided in beams, columns,
prior to slab casting as per electrical drawings
13
Training Experience
Inspections & Tests
Correct type of conduits & accessories used.
Correct markings.
Dimension checks.
Damage on conduits and accessories.
Fittings and accessories are of proprietary type
14
Training Experience
Inspections Sheets
15
Training Experience
Meggar test
After the cable laying is completed, the cables are
checked for continuity and insulation test
From Meggar Machine.
16
Training Experience
Testing Method
1) Remove all devices in the relevant cable loop which is going to
meggar test. (this test should be prior connecting the devices)
2) Connect all negative and positive cable ends together in device
connecting locations.
3) Apart ends of two wires, before testing positive and negative cables.
4) Perform the meggar test for 500VDC with minimum insulation
resistance of ≥ 0.5 MΏ.
5) Do the same procedure to check the wire insulation.
17
Training Experience
Problems
Loop is not continue at all points.
Solution
Checked loop by point to point and found
the braked points and fixed it.
18
Training Experience
Pipe Painting
Following steps will be carried out during the process of painting.
Check the pipe if there is any corrosion mark and that area has to be
cleaned and zinc phosphate metal primer will be applied prior painting or
cold galvanizing paint shall be used.
Make sure that there
- No dust
- No moisture
- No metal particles on the surface
Apply one coat of Anti Corrosive Paint (Etching primer) on GI pipe
surface.
19
Training Experience
Cont’d…….
Painting will be carried out by either hand paint (brush) or paint spray
machine. Final touchup work will be done after completing the pipe network
by using paintbrush.
20
Training Experience
Smoke / Heat Detector Base Mounting
Below images showing the different types of applications and the base mounting methods
separately
Exposed detector with Pre embedded PVC conduit.
21
Training Experience
Cont’d…….
Exposed detector on the ceiling.
22
Training Experience
Cont’d…….
Exposed Detector inside the ceiling with an exposed Remote
Indicator.
23
Health and Safety
Safety shoes & boots
Safety signs
Safety helmets
24
Problems Encountered
25
Conclusion
26
THANK YOU…