Professional Documents
Culture Documents
CPM - PERT 07122022 023916pm 09052023 095735am 1 11102023 121531pm
CPM - PERT 07122022 023916pm 09052023 095735am 1 11102023 121531pm
Assistant Professor
Bahria University
Rules of Constructing Network
The rules of network construction in Operation Research
are
• No single activity can be represented more than once in a
network.
• The length of an arrow has no significance.
• The event numbered 1 is the start event and an event
with highest number is the end event.
• Before an activity can be undertaken, all activities
preceding it must be completed i.e., the activities must
follow a logical sequence (or – interrelationship) between
activities.
Rules of Constructing Network
• In assigning numbers to events, there should not be any
duplication of event numbers in a network.
• Dummy activities must be used only if it is necessary to
reduce the complexity of a network.
• A network should have only one start event and one end
event.
Conventions of Network diagram
Conventions of Network diagram
Common Errors in Constructing Network
Diagrams
• In network diagrams there are three types of errors that
occur commonly.
I. Looping
II. Dangling
III. Redundancy
Construct the Network
Activities Predecessor Activities Predecessor
A -- A --
B -- B --
C A C A,B
D A D A,B
E B E B
F BB F D,E
G D,E G C,F
H F,G H D,E
I G,H
Construct the Network
Activities Predecessor Activities Predecessor
A -- A --
B -- B --
C A,B C A
D B D B
E A E A
F C F B
G E,F G C,D
H D,F H G,F
I G,H I E
J I J H,I
K J
PERT and CPM
PERT: Program Evaluation and Review Technique
1-2 4 0 4 5 9 5 4
1-3 1 0 1 0 1 0 1
2-4 1 4 5 9 10 5 5
3-4 1 1 2 9 10 8 5
3-5 6 1 7 1 7 0 7
4-9 5 5 10 10 15 5 10
5-6 4 7 11 12 16 5 11
5-7 8 7 15 7 15 0 15
6-8 1 11 12 16 17 5 17
7-8 2 15 17 15 17 0 17
8-10 5 17 22 17 22 0 22
9-10 7 10 17 15 22 5 22
Example
Example (Critical Path by CPM)
Example (Critical Path calculations)
Example
Example
Example
PERT(Program Evaluation Review Technique) Analysis
• Draw the network.
• Analyze the paths through the network and find the
critical path.
• The length of the critical path is the mean of the project
duration probability distribution which is assumed to be
normal
• The standard deviation of the project duration probability
distribution is computed by adding the variances of the
critical activities (all of the activities that make up the
critical path) and taking the square root of that sum
• Probability computations can now be made using the
normal distribution table.
Probabilistic Time Estimates
• Optimistic time
• Time required under optimal conditions
• Pessimistic time
• Time required under worst conditions
to tm te tp
te = t o + 4t m +t p
6
te = expected time
to = optimistic time
tm = most likely time
tp = pessimistic time
Variance
2 (t
= p o– t ) 2
36
2 = variance
to = optimistic time
tp = pessimistic time
Example
Example
Example
Example
Project Time Vs Project Cost
Project Time Vs Project Cost
Example
Example
Example
Example
Example
Example