Job Completion Report Presentation - Hydrostatic Rig-123
Job Completion Report Presentation - Hydrostatic Rig-123
1 Frame No work No work done Checked and found frame condition good so no work done
2 Mast No work No work done Checked and found mast condition good so no work done
3 Canopy No work No work done Checked and found canopy condition good so no work done
Gear box pin 2 nos , lift cylinder pin 2 nos ,
4 Pin & Bushes new making and fitting No work done After new pin making and fitting , it works properly
14 Diesel Tank Cleaning and stunner change No work done No leakage found
15 Hydraulic Tank Cleaning and all filter change No work done When testing , No leakage and no heating issue found
Pin & Bushes:
Work Done Statement
S.No Component Description Work Done Part No Complaints/Suggestions/Instructions
2 Lift Cylinder Upper Pin New making N/A New pin fitting , no problem found
3 Lift Cylinder Lower Pin New making N/A New pin fitting , no problem found
4 Dump cylinder upper pin No work N/A Pin condition ok
18 Dump cylinder bushing New bush making and fitting N/A New bush fitting , no problem found
S.No Component Description Work Done Part No/Serial No Make /Model Complaints/Suggestions/Instructions
No work
3 Engine Fan N/A N/A No crack found
4 Radiator and Pad Servicing N/A N/A No leakage found and radiator works properly
6 Mud Pump Drive Motor No work 11CSD4090W1-M Checked and found condition ok so no workdone
7 Main Winch Motor No work 11CSD4040W1-M Checked and found condition ok so no workdone
3 4/3 Spool Valve Aux . Part No work Checked , found condition ok so no work done
5 Load Sensing Valve - Track No work Checked , found condition ok so no work done
9 Rotation High – Low Valve No work Checked , found condition ok so no work done
11 Main Winch Brake Valve No work Checked , found condition ok so no work done
12 Mud Pump Control Valve No work Checked , found condition ok so no work done
Work Done Statement
Oil Coolers, Hose assemblies & Gauges:
1 Hydraulic Oil Cooler No work 12CSD405W1 Cortech No crack found so only cleaning work done
N/A
2 Hydraulic Hoses 10% hose change Rajdhani After changing damage hose all hose condition ok
N/A
4 Main Pump Pressure Gauge New fitting N/A Main pump pressure gauge working properly
N/A
7 Feed Pressure Gauge No work N/A Checked , condition ok
1 Meters Panel Band repairing , painting , all meters servicing N/A N/A After repairing meter panel condition ok
2 Hour Meter Replaced to new one A2C96911700 VDO Checked , new hour meter works properly
3 Battery New battery fitting with machine N/A Cummins Checked , new battery works properly
6 Wireline Pulley Bearing change 11CSD403010B After bearing change wire line pulley works properly
Checked , condition ok
8 Expansion Bellow No work N/A
9 Mud Pump safety Valve Servicing N/A After servicing , safety valve work
1 Engine Oil Filter New P553000 Donaldson 1 New filter condition ok and working properly
Donaldson
2 Fuel Filter New P5029055 P502913 2 New filter condition ok and working properly
3 Fuel Water Separator New P550248 Donaldson 1 New filter condition ok and working properly
Donaldson
5 Air Filter Inner New 12CSD402020BW1 1 New filter condition ok and working properly
6 Air Filter Outer New 12CSD402020BW1 Donaldson 1 New filter condition ok and working properly
7 Hydraulic Oil Suction New 12CSD402020BW4 1 New filter condition ok and working properly
Filter
8 Hydraulic Oil Return New 12CSD402020BW2 1 New filter condition ok and working properly
Filter 1
9 Hydraulic Oil Return New 12CSD402020BW3 1 New filter condition ok and working properly
Filter 2
10 Fuel Tank Strainer New N/A 1 New filter condition ok and working properly
Work Done Statement
General Consumables - Lubricants:
Machine Testing
Machine Washing
Machine Painting
Cost/Manhour
Silicon Hoses 0
Fasteners 2200
Bearing 139266
Filters 34446
Lubricants 18820
Structural Steels 0
Total Cost
Plan Vs Actual Statement
Type of Cost Cost
Man-Hour Cost
Total Cost
Deviation Justifications
Cost Deviation Workdays Deviation
Signature Panel
Machine Clearance By
Quality Clearance By