Sl No.

Activity
Contractual Contractual Actual start Actual Compl Delay Reason for Delay
Start Date End Date Date Date

Delay in Supply , finalization of


5 Kiln Structure Erection 09-03-2014 21-06-2014 24.03.2017 30.01.2018 1299 erection contractor

Change in Price Schedule approved on: Sinocalci requested NMDC for price
28.09.2018. Sinocalci applied for Price schedule revision to meet their cash
Schedule Revision:-06.02.2018 (Value crunch problem on 06.02.2018.
of Main Imported Equipment 06.02.2018 28.09.2018 After financial/contractual vetting
6 increased , Refractory(Imported ) 232 and after providing necessary
value decreased, Erection of clarification on the changes made,
Technological Structure(indigenous) changes in price schedule was
increased). approved on 28.09.2018.
Direct payment to sub vendors was
approved on 09.11.2018. However
Sinocalci after repeated follow up
Delay in ordering of major indigenous
7 21-03-2013 13-06-2013 09.11.2018 30.03.2020 2447 started ordereing major items after
equipment they received comfort letters which
were issued after the above
approval.
Essentiality Certificate ( 2nd time,
8 including Electrical items ) from 10.01.2019 15.04.2019 95 Clarification regarding inclusion of
Imported Electrical Items
Ministry :- 15.04.2019