Professional Documents
Culture Documents
Foundation Treatment Lecture
Foundation Treatment Lecture
and Treatment
Deputy Director, Embankment Dam (NW&S)
Central Water Commission
Foundation Investigation ?
Knowledge of bedding orientation of fracture planes
and other relevant foundation information is therefore,
essential for design of the dam.
2
Terminology
Some Terminology…
Bedding Plane (or Stratification)
4
Some Terminology…
Bedding Plane (or Stratification)
5
Some Terminology…
Bedding Plane (or Stratification)
6
Some Terminology…
Foliation Plane
Planar arrangement of structural or textural features in
any rock type, but particularly that resulting from the alignment
of constituent mineral grains of a metamorphic rock of the
regional variety along straight or wavy planes.
7
Some Terminology…
Foliated rocks at dam site
8
Some Terminology…
Fault
A fault is a planar fracture or discontinuity in a volume
of rock, across which there has been significant displacement
along the fractures as a result of earth movement.
When rocks slip past each other in faulting, the upper or
overlying block along the fault plane is called the hanging
wall, or headwall; the block below is called the footwall.
The fault strike is the direction of the line of intersection
between the fault plane and the surface of the Earth.
The dip of a fault plane is its angle of inclination measured
from the horizontal.
9
Some Terminology…
Jointed Faulted Rock at Dam site
10
Some Terminology…
Normal Fault
11
Some Terminology…
Reverse Fault
12
Some Terminology…
Thrust Fault
Thrust faults is a low-angle (dip angle) reverse fault.
13
Some Terminology…
Shear Zone
A shear zone is zone along which blocks of rock have been
displaced in a fault-like manner but without prominent
development of a visible fault.
It is a zone of strong deformation (with a high strain rate)
surrounded by rocks with a lower state of finite strain. It is
characterised by a length to width ratio of more than 5:1 .
Shear zones are important in rock engineering because they
posses the prerequisites for a weak layer : continuity over a
large area, and a zone of very low strength, i.e., essentially
zero cohesion and low angle of friction.
14
Some Terminology…
Shear Zone
15
Some Terminology…
Shear Zone
16
Some Terminology…
Shear Zone
18
FOUNDATION INVESTIGATION
INVESTIGATION REQUIRED
To judge the overall permeability in order to enable a
preliminary assessment to be made of the degree of
impermeabilization desired and the feasibility of achieving
the same.
To explore the local variation in the grain size distribution
and permeability in order to ascertain the groutability of the
various strata and the extent of ungroutable layers.
To investigate salt content of the soil as well as ground
water to identify presence of salts which may inhibit
gellation.
20
Investigation …
Parameters should be Determined:
For each material the shear strengths of the intact portions, the sliding
friction strengths of discontinuities, and the shear strength at each
interface with a different material (including the strength at the
interface of concrete and the material exposed at the complete
excavated surface).
21
Investigation …
Investigations data are Used for: 1/2
22
Investigation …
Investigations data are Used for: 2/2
23
RROCK MASS
CLASSIFICATION SYSTEMS
CLASSIFICATION OF IN-SITU ROCK
FOR ENGINEERING PURPOSE
Five ROCK MASS CLASSIFICATION SYSTEMS have been
given in ICOLD Bulletin on Rock Foundation for Dams
(1993) based on:
Weathering Conditions
Layer Thickness
Discontinuity intercepts
Uniaxial Compressive Strength of Rock
Frication angle of the Discontinuities
25
ROCK MASS CLASSIFICATION …
Rock Quality Designation (RQD) :
The Rock Quality Designation index (RQD) was developed
by Deere (Deere et al 1967) to provide a quantitative estimate
of rock mass quality from drill core logs.
26
ROCK MASS CLASSIFICATION …
Rock Quality Designation (RQD)
27
ROCK MASS CLASSIFICATION …
Relation of RQD and Rock Quality :
29
ROCK MASS CLASSIFICATION …
Rock Structure Rating (RSR) :
The significance of the RSR system, is that it introduced the
concept of rating each of the components listed below to arrive at
a numerical value of
RSR = A + B + C.
32
ROCK MASS CLASSIFICATION …
RSR : Parameter B : Joint Pattern, Direction of
drive
33
ROCK MASS CLASSIFICATION …
RSR : Parameter C : Groundwater, Joint
Condition
34
ROCK MASS CLASSIFICATION …
Geomechanics Classification or
Rock Mass Rating (RMR) :
Bieniawski (1976) published the details of a rock mass
classification called the Geomechanics Classification or the
Rock Mass Rating (RMR) system.
The following six parameters are used to classify a rock mass
using the RMR system:
1. Uniaxial compressive strength of rock material.
2. Rock Quality Designation (RQD).
3. Spacing of discontinuities.
4. Condition of discontinuities.
5. Groundwater conditions.
6. Orientation of discontinuities.
35
ROCK MASS CLASSIFICATION …
Rock Mass Rating (After Bieniawski 1989) : 1/3
36
ROCK MASS CLASSIFICATION …
Rock Mass Rating (After Bieniawski 1989) : 2/3
37
ROCK MASS CLASSIFICATION …
Rock Mass Rating (After Bieniawski 1989) : 2/3
* Some conditions are mutually exclusive . For example, if infilling is present, the roughness of
the surface will be overshadowed by the influence of the gouge. In such cases use A.4 directly.
** Modified after Wickham et al (1972).
38
ROCK MASS CLASSIFICATION …
Seismic Refraction Techniques
39
ROCK MASS CLASSIFICATION …
Seismic Refraction Techniques
Velocity Index and Rock-Mass Quality Seismic Refraction Techniques
Compressive Strength
Deformation Modulus
42
FOUNDATION MATERIAL PROPERTIES
44
FOUNDATION MATERIAL PROPERTIES
45
FOUNDATION MATERIAL PROPERTIES
46
COMPRESSIVE STRENGTHS OF ROCKS
47
COMPRESSIVE STRENGTHS OF ROCKS
48
FOUNDATION MATERIAL PROPERTIES
Range of Compressive Strengths of different
Rocks
49
50
51
52
53
54
55
56
FOUNDATION MATERIAL PROPERTIES
Shearing Strengths
Shear strength is used to describe the strength of rock
materials, to resist deformation due to shear stress.
Rock resists shear stress by two internal mechanisms,
cohesion and internal friction.
Cohesion is a measure of internal bonding of the rock
material.
Internal friction is caused by contact between particles, and
is defined by the internal friction angle, φ.
Different rocks have different cohesions and different
friction angles.
57
FOUNDATION MATERIAL PROPERTIES
59
FOUNDATION MATERIAL PROPERTIES
Shear Strengths of Rock Discontinuities
60
FOUNDATION MATERIAL PROPERTIES
Deformation Modulus
Deformability is characterized by a modulus describing
the relationship between the applied load and the
resulting strain.
The fact that jointed rock masses do not behave
elastically has prompted the usage of the term modulus of
deformation rather than modulus of elasticity or Young's
modulus.
Clerici (1993) concluded that "when the value of the
modulus of deformation is determined, even by direct
measurement, the aim cannot be to define an absolute
value, but rather to define a magnitude for the modulus".
61
FOUNDATION MATERIAL PROPERTIES
Three types of in-situ tests are mostly used to determine the
modulus of deformation:
62
FOUNDATION MATERIAL PROPERTIES
Deformation Modulus
3. Radial jacking tests (Goodman jack test) :
The Goodman jack consists of two curved rigid bearing
plates of angular width 90o which can be forced apart inside an
NX size bore hole by a number of pistons.
Two transducers mounted at either end of the 20 cm long
bearing plates measure the displacement.
In addition to these three types the following in situ
deformation tests can be used:
− flat jack tests;
− cable jacking tests;
− radial jack tests;
− dilatometer tests;
− pressure chamber.
63
Deformation Modulus
UNDATION MATERIAL PROPERTIES
64
FOUNDATION MATERIAL PROPERTIES
Fracture Toughness
Fracture toughness of rock materials measures the
effectiveness of rock fracturing. It is typically measured by a
toughness test. There are three fracture mode: (Mode I), (Mode
II) (Mode III), correspondingly, there are three fracture
toughness, KIC, KIIC and KIIIC.
65
FOUNDATION MATERIAL PROPERTIES
Swelling
Swelling is governed by the amount of swelling
montmorillonite clay minerals in the rock material. Rock swelling
is measured in confined and unconfined conditions. Unconfined
swelling is measured by the percentage increase of length in three
perpendicular directions, when a rock specimen is placed in water.
Confined swelling index measures swelling in one direction while
deformations in other two directions are constrained.
66
DESIGN & ANALYASIS
STRUCTURE STABILITY
Stability analyses should be conducted to verify that the
structure, or component thereof, is stable relative to a
failure plane located at the structure-foundation interface,
and the structure foundation is stable relative to a deep
seated failure surface.
68
STRUCTURE STABILITY…
DESIGN REQUIREMENT FOR STABILITY
The design should satisfy the hollowing requirements of
stability:
1. The dam shall be safe against sliding on any plane or
combination of planes with in the dam, at the foundation
or within the foundation;
2. The dam shall be safe against overturning at any plane
within the dam, at the base, or at any plane below the
base; and
3. The safe unit stresses in the concrete or masonry of the
dam or in the foundation material shall not be exceeded.
69
STRUCTURE STABILITY…
REQUIREMENT OF STABILITY
Following are the modes of failure of a gravity dam:
1. Overturning
2. Sliding
3. Compression or Crushing
4. Tension
For consideration of stability following assumptions are made:
1. That the dam is composed of individual transverse vertical
elements each of which carries its load to the foundation
without transfer of load from or to adjacent elements.
And
2. That the vertical stress varies linearly from upstream face to
downstream face on any horizontal section. 70
STRUCTURE STABILITY…
GEOTECHNICAL PARAMETER
Geotechnical parameters normally required to conduct
stability analyses of structures include:
71
STRUCTURE STABILITY…
STABILITY OF FOUNDATION AGAINST SLIDING
Sliding along the structure-foundation interface is ordinarily
assessed using the friction factor method with cohesion
neglected.
The factor of safety against sliding is defined as the ratio of
resisting forces to driving forces and, for a horizontal
sliding plane, is expressed as follows:
72
STRUCTURE STABILITY…
SLIDING STABILITY - Factors of Safety for Various Conditions of Loading
73
STRUCTURE STABILITY…
CHECK FOR SLIDING STABILITY
75
STRUCTURE STABILITY…
MEASURES TAKEN TO IMPROVE SLIDING STABILITY
Roughening of Base
Provision of Shear Keys
Upstream Sloping of Dam Base
Use of Anchors
Use of Mat Foundation
Other Measures
• Providing Buttress Structure
• Struts Bearing Against Sound Rock on the D/S
• Adopting Slightly Arched Alignment of Dam
• Combining blocks resisting on weaker rocks with
adjacent resisting on stronger rocks. 76
STRUCTURE STABILITY…
Roughening of Base
To improve sliding resistance of the dam, proper bond
between the dam base and the foundation rock surface should
be ensured.
This can be done by roughening the rock surface by
providing corrugations so as to improve the frictional
resistance along the contact surface.
This should be done as a part of shaping of foundation.
77
STRUCTURE STABILITY…
Provision of Shear Keys
Shear keys are of two types: One
placed below the heel of the dam and
the Other within the foundation
across seams of soft material, also
known as Shear Plug.
The shear key below the heel of the
dam is provided for keying the Dam
some distance into foundation rock.
This leads to improvement in the
shearing resistance through
mobilisation of passive resistance of
the adjacent rock on the downstream.
78
FOUNDATION TREATMENT
Foundation Treatment ?
To Foundation treatment is the controlled
alteration of the state, nature or mass behaviour
of ground materials in order to achieve an
intended satisfactory response to existing or
projected environmental and engineering
actions.
81
Main Improvement Techniques
Temporary
e.g. dewatering or ground freezing, where the improvement is
only during the application.
Short-term
e.g. some forms of grouting, or use of diaphragm walls for ease
of construction with longer term benefits.
Long-term
e.g. soil nailing, vibro-replacement, curtain grouting of a dam,
where the treatment is integral to the permanent works.
82
Effect on the Ground
Change of state;
i.e. the same ground but made stronger, stiffer, denser, more
durable.
Change of nature;
i.e. the ground becomes a different material by inclusion of
other materials.
Change of response;
i.e. through the incorporation of other materials, the ground
becomes a composite material with enhanced load-carrying or
deformation characteristics.
83
Various steps involved in
Improvement of Foundation
Foundation Treatment
Strengthening Measures
Sealing Measures Drainage Measures
(Curtain Grouting / (Consolidation Grouting/
(Drainage holes/ Filters) dental
Cut Offs/ Core etc.)
treatment/Stabilization
84
Preparatory Works
Clearing: Removal, transport & disposal trees, vegetation,
structures and other obstructions.
86
Core – Abutment Contact
Typical details
87
Foundation Treatment Techniques
88
Parameters for Concept
Soil Characteristics Site Environment
Cohesive or non-cohesive Close to existing
Blocks structure
Water content Height constraints
water table position
Organic materials Time available to build
Soil thickness
Structure to support
Isolated or uniform load
Deformability
89
Main Improvement Techniques:
• by vibration
• by adding load
• by structural reinforcement
• by structural fill
• by admixtures
• by grouting
• by specialist dewatering
90
CRITERIA & GROUTING
TECHNIQUES
Purpose of Grouting
Reduce leakage through the dam foundation
Reduce seepage erosion potential
Reduce uplift pressure under concrete gravity dams
in conjunction with drain holes
92
PERMEABILITY TESTS IN-SITU
93
PERMEABILITY TESTS IN-SITU
Use of post grouting pumping tests for evaluation of the
efficacy of grout curtains is subject to considerable
uncertainty when the curtain is only 5 to 10 m wide. This is
because of the irregularity of the curtain and the
94
GROUTING OF PERVIOUS SOIL
These are applicable where the primary purpose of grouting is
to reduce the permeability of the soil. In such cases consolidation
of the soil is the primary objective.
The seepage through a pervious stratum is generally governed by
the presence of a few pockets or layers of high permeability.
It is necessary to treat only such layers to achieve the necessary
reduction of permeability.
It is judge not merely in terms of the grain sige distribution of
each individual layer or lense but in terms of its contribution to
the over permeability.
95
GROUTING METHODS & THEIR SELECTION
96
GROUTING METHODS & THEIR SELECTION
Cont…
The method of grouting selected should, therefore, satisfy the
following requirements:
97
The limiting Lugeon value given in the table, are recommended
for deciding the necessity or otherwise of grouting. Lugeon
values in excess of those given in the table would indicate that
grouting is desirable.
100
Classification of Grouting
Foundation grouting can be classified into two types:
• Curtain grouting
• Consolidation grouting
101
Curtain grouting
Curtain grouting is designed to create a thin barrier (or
curtain) through an area of high permeability.
102
Typical Profile of Curtain grouting
103
Consolidation Grouting
Consolidation grouting is designed to give intensive
grouting of the upper layer of more fractured rock, in the
vicinity of the dam core, or in regions of 'high' hydraulic
seepage gradient.
104
Consolidation Grouting Pattern
105
Classification of Grout Materials
Three basic types of grout are differentiated according to
composition:
Suspensions : Small particles of solids are distributed in a
liquid dispersion medium
Examples: cement and clay in water.
106
Classification of Grout Materials
Solutions : Liquid homogenous molecular mixtures of two
or more substances.
Examples: Sodium silicate, organic resins, and a wide
variety of other so called chemical grouts.
Limits of Groutability
(based on Karol 1985)
108
Cement grouts used mostly
Mostly grouting is done using cement grout.
Portland cement mixed with water in a high speed mixer to a
water cement of between 0.5 and 5 at which condition it is a
slurry, readily pumpable and able to penetrate
fractures in rock.
For soil foundations or when rock fractures are very
narrow, chemicals are used, which are more expensive.
109
Depth of Grout holes
According to IS: 11293 (Part 1)-1985 “Guidelines for the
design of grout curtains”, the following empirical criteria
may be used as a guide:
D= H/3 to H
112
Sequence of Grouting Operations
The holes are drilled and grouted in sequence to allow testing
of the permeability before grouting and allow a check on
effectiveness of the grout take by the foundation.
113
Staging of grouting
Downstage without Packer
Upstage
Full Depth
114
Downstage without Packer
One of the preferred methods.
115
116
Downstage with Packer
Problem of seating, leakage past the packer.
117
118
Upstage
Full depth is drilled in one go and grouting is done in stages
using packers.
Cheaper, as the drilling rig is set only once, but savings may
be offset by the need for more conservative total depths.
Tests not in harmony with grout takes, small quantity of water, large
cement take
Very little seepage though originally high permeability but grout takes
were low
123
Permeability of joints depends on the
Orientation of joints
124
Different Conditions
125
Water Pressure Test
Tests may be conducted in cycles 1 to 5
126
WPT contd…
127
Pattern of WPT
128
Interpretation
129
Flow vs. Orientation
130
Flow vs. Orientation Contd.
131
Geologic Structures
132
Conclusions
Consider, if grouting is really required.
Take the geological structures and their orientation into
account.
Design Grout Mix appropriately.
Limited utility of Water Pressure Test.
Review the Acceptance criterion.
Consider chemical grouting in special cases.
133
PARTIAL & POSITIVE CUT-OFF
Functions & Design Requirements
of Cut-off:
Functions & of Cut-off:
135
Functions & Design Requirements
of Cut-off:
136
Functions & Design Requirements
of Cut-off: Cont…
Permeability of substrata
138
IMPERVIOUS BLANKET
The horizontal upstream impervious blanket is provided to
increase the path of seepage when full cut-off is not practicable
on pervious foundations.
Impervious blanket shall be connected to core of the dam.
The material used for impervious blanket should have far
less permeability than the foundation soil.
To avoid formation of cracks, the material should not be
highly plastic.
Reference may be made to IS: 1498 for suitability of soils for
blanket.
139
IMPERVIOUS BLANKET (Cont…)
140
RELIEF WELLS
To ensure safety of the earth dam in cases where the cut-off is
partial or reliance is placed on an upstream blanket for
controlling under seepage.
141
142
143
144
METHODS OF TREATMENT OF DIFFERENT
FOUNDATION MATERIAL-OVERBURDEN &
ROCK (IS 4999 :1991 & IS 6066 :1994)
DAMS ON
SHALLOW PERVIOUS FOUNDATIONS
M -IMPERVIOUS P -PERVIOUS
SP -SEMI-PERVIOUS SM -SEMI-IMPERVIOUS
R -RANDOM, INCLUDING SP OR SM
146
DAMS ON
SHALLOW PERVIOUS FOUNDATIONS
M -IMPERVIOUS P -PERVIOUS
SP -SEMI-PERVIOUS SM -SEMI-IMPERVIOUS
R -RANDOM, INCLUDING SP OR SM
147
DAMS ON
SHALLOW PERVIOUS FOUNDATIONS
M -IMPERVIOUS P -PERVIOUS
SP -SEMI-PERVIOUS SM -SEMI-IMPERVIOUS
R -RANDOM, INCLUDING SP OR SM
148
DEEP PERVIOUS FOUNDATIONS
WITH IMPERVIOUS TOP STRATUM
M -IMPERVIOUS P -PERVIOUS
SP -SEMI-PERVIOUS SM -SEMI-IMPERVIOUS
R -RANDOM, INCLUDING SP OR SM
149
DEEP PERVIOUS FOUNDATIONS
WITH IMPERVIOUS TOP STRATUM
M -IMPERVIOUS P -PERVIOUS
SP -SEMI-PERVIOUS SM -SEMI-IMPERVIOUS
R -RANDOM, INCLUDING SP OR SM
150
DEEP PERVIOUS FOUNDATIONS
WITH IMPERVIOUS TOP STRATUM
M -IMPERVIOUS P -PERVIOUS
SP -SEMI-PERVIOUS SM -SEMI-IMPERVIOUS
R -RANDOM, INCLUDING SP OR SM
151
152
Description of Grouting Methods
The following methods are generally followed for grouting of
overburden soils:
Rising Tube
In this method, grouting is done through the casing which
is driven to the bottom of the hole.
The tube is withdrawn a short distance and grout is
injected through the open end into the cavity left by the
tube as it is raised.
In this manner the tube is lifted progressively until the
entire depth required to be grouted is treated.
153
Description of Grouting Methods
Cont…
154
Description of Grouting Methods
Cont…
Descending Stage
155
Grouting by Descending Stage
156
Description of Grouting Methods
Cont…
Grouting Through Tubes with Sleeves
In this system of grouting, a pipe, with rubber sleeves
fitted at 30 cm intervals, is installed in the borehole by
filling the annular space around the tube by a sheath of
clay cement grout.
157
Grouting Through Tubes with Sleeves
158
Grouting in Rock
CHOICE OF GROUTING MATERIALS & MIXTURES
159
Grouting in Rock
BLANKET GROUTING/CONSOLIDATION GROUTING
160
Cont…
Grouting in Rock
BLANKET GROUTING/CONSOLIDATION GROUTING
161
Grouting in Rock
CURTAIN WIDTH
The curtain width at the core contact should match the core
base, usually width in the range of 1/3 to 1/5 head is
provided.
The main curtain should extend to rock or impervious
stratum and the width should be reduced from the width at
core contact to the main curtain width, about ¼ the depth of
the pervious alluvium.
The main curtain should have two or more rows depending
upon the requirements strata. For clay cement silicate
aluminate grouting the main curtain should have a width of
1/7 of head.
162
Grouting in Rock
CURTAIN WIDTH Cont…
To safeguard the foundation against credibility hazard.
To reduce quantity of seepage.
To safeguard foundation credibility The limiting lugeon
value, excess of which given below requires grouting.
Item Rock below COT
Laminar flow 3 to 10
Turbulent flow 3 to 5
Dilation 1 to 3
Washout and hydraulic fracturing 1 to 3
Voids fill 3 to 5
163
MIX PROPORTION &
GROUTING PRESSURE
Grout Mixture
Rock grouting is usually performed with a mixture of cement
and water with or without additives.
167
Grout Mixture
Admixture
Use in small quantities the following admixtures impart
certain desirable characteristics:
168
Grout Mixture
Grout Mix Proportion
For determining the mix proportions the viscosity&
bleeding of grout, strength and economy shall be the
main consideration:
If thin grout is used and continued for too long a time, the
grouting operation may get unduly prolonged and may be
expensive.
170
Grout Mixture
Grout Mix Proportion Cont…
If openings are large and grout is thin, grout
consumption will be excessive even with low pressure.
No general rules can be stipulated manner in which the
thickening of the grout is to be carried out.
The appropriate sequence for every site may be decided
after a review of the results of initial grouting.
As a guide, the mix should be thickened if there is no
increase in the pressure after continuous grouting of about
10 minutes.
171
Grout Mixture
Grout Mix Proportion Cont…
172
Grout Mixture
Grout Mix Proportion Cont…
In case of higher water loss in any of these holes, sanded
grout (2 sand : 1cement to 1sand: 1 cement) may be
injected in sequence as per the requirement and thereafter
conventional grouting be done with thinner grout, starting
with 10:10 to 1:1 (water : cement) and vice – versa so as to
fill up the gaps.
173
Grout Mixture
Grout Mix Proportion Cont…
The grouting should be continued till refusal stage is achieved
i.e the rate of intake becomes almost negligible say 1.0
litre/min averaged over a period of 10 minutes at desired
limiting pressure up to 3 kg/ cm2 and 1.5 lirte/min for pressure
between 3 and 10 kg/cm2.
It is desirable to carry out the grouting with the mixture of
cement and water only. However if the intake is more, the
grout may be thickened by using inert materials like.
Pozzolan as or fine sand, rock powder, clay bentonite etc.
174
Grout Mixture
Grout mix for Multiple Line Grout Curtains
175
Grout Mixture Cont…
Grout mix for Multiple Line Grout Curtains
176
Grout Pressure
Control of Grout Pressure
The limiting value of pressure for each zone and depth may be
established initially from the results of trial grouting, along
with observations of upheaval. Fig-2 may be used as guide.
178
Grout Pressure
Control of Grout Pressure Cont…
179
Grout Pressure
Guide for Grouting Pressures
180
DRAINAGE MEASURES
Drainage Measures
[Internal Drainage System]
Toe drain
Blanket drain
182
Drainage Measures
[Drainage & Filters]
.
183
Drainage Measures
[Relief Wells]
Consists of a pipe (10 to 15 cm diameter)
having narrow slots placed in the Centre,
surrounded by graded filter media (45 to 90 cm
diameter) sunk near d/s toe of earth dam.
Permit the ingress of seepage water into the well
allowing it to rise to the outfall (relief) level
where the pressure gets relieved.
Ensures safety of the earth dam when the cut-off
is partial or reliance is placed on upstream
blanket for controlling seepage,
Controls the pressure developed below the d/s
toe of the dam, especially when impervious
layer of the soil at the top overlays a pervious
layer.
A system of relief wells suitably spaced reduces
the intensity of the under seepage pressure and
render it practically harmless.
184
Drainage Measures
[Drainage Hole]
185
Details of
Foundation
Drain
Gallery
186
Strengthening Measures [Dental Treatment]
187
Strengthening Measures [Dental Treatment]
188
CASE STUDIES
BHAKRA DAM
190
BHAKRA DAM
Three CLAYSTONE bands (i.e., the Upstream or Heel, the
Middle and the Downstream bands) traverse the foundation
area of 226 m high Bhakra Dam.
The D/S claystone band does not effect the stability of the
dam and the left power plant has been located on this band.
191
BHAKRA DAM
The foundation rock (sandstone) was found to have a
modulus of elasticity equal to that of the concrete used in
the dam.
192
BHAKRA DAM
The claystone band in the river portion was excavated to a
safe depth and backfill the seam with a concrete plug to act
as a strut for transferring the thrust from the dam to U/S
rock.
193
BHAKRA DAM
The most severe case occurs when the seam is completely
disintegrated and the least severe when it is intact.
The studies indicates that the stresses in the plug and the
adjoining rock decreased rather rapidly for depths of plug
down to 30 m and varied gradually thereafter.
194
BHAKRA DAM
The most severe case occurs when the seam is completely
disintegrated and the least severe when it is intact.
The problem resolves into finding out the stresses for
different depths of plug and assuming different depths of
claystone disintegration.
The studies indicates that the stresses in the plug and the
adjoining rock decreased rather rapidly for depths of plug
down to 30 m and varied gradually thereafter. i.e., the
depth of plug beyond 30 m didn’t martially contributed
to reduction of stresses.
195
BHAKRA DAM
196
BHAKRA DAM
The reservoir was filled in 1958.
In August 1962, cracks were observed in the plug galleries and
leakage increased indicating development of probable tensile
stresses within the plug.
The galleries were plugged to prevent leakage.
The cracking of the plug could be attributed possibly to the
occurrence of tensile stresses in the heel region under
reservoir-full condition, a condition which was not tested in
the photo-elastic model and the strut was designed for
compressive stresses under reservoir-empty condition.
197
BHAKRA DAM
The Middle Claystone band varies in width from 6 to 9 m
and is completely confined by the dam except were it merges
from under dam in the left abutment.
It is treated by excavating it out and backfilling with
Precooled Concrete.
The trenching depth was based on Shasta & Friant Dam
formulae.
The plug-stone contacts thoroughly grouted.
A supplementary longitudinal drainage gallery was provided
U/S of the claystone band for releasing any water pressure that
might build up U/S of the almost impervious claystone band.
198
SARDAR SAROVAR
DAM
199
SARDAR SAROVAR DAM
The Sardar Sarovar Dam is founded on Basalt rock.
The lava flows are 10-15 m thick approx.
It is treated by excavating it out and backfilling with
Precooled Concrete.
Foundation investigations revealed the presence of a reverse
fault in the deepest river portion.
The dam site is criss-crossed by a number of dolerite dyke
intrusions with result that the rock in the foundation is
fractured.
Modulus of Deformation of
Basalt : 80,000 kg/cm2
Fault-Zone material : 8000 kg/cm2
200
SARDAR SAROVAR DAM
Normal concrete-plug treatment has been provided for the fault
zone.
Excavation of trench of width 12.5 m (assumed width of
fault zone ) below the normal foundation level to a depth of
18.75 m (1.5 times the width of the fault ) on the U/S and 25
m (twice the width of the fault ) on the D/S along the fault
and backfilling with concrete.
An increasing depth of the plug from the U/S to the D/S has
been provided in view of the increasing stresses along the dam
base under the reservoir-full conditions.
201
SARDAR SAROVAR DAM
Section along the fault showing treatment of fault zone
202
SARDAR SAROVAR DAM
Sectional elevation across fault showing details of concrete plug
and grouting
203
SARDAR SAROVAR DAM
Excavation of two shafts on the U/S and the downstream ends
of the trench of depth equal to 12 m & 6 m respectively below
the trench bottom and backfilling with concrete to act as
seepage cut-offs.
Contact grouting between the side faces of the plug and the
excavated slopes of the trench.
A thin weak layer of redbole (crushed basalt with very little
clay content) is present between the two lava flows below the
foundation level of the dam on the left of the fault zone, and
two layers of weak and friable argillaceous sandstone in
between two component rock masses on the right of the fault
zone.
204
SARDAR SAROVAR DAM
The remedial measures for improving the sliding resistance
along the weak layers comprised:
A grid of longitudinal and transverse shear keys (3.0 X 2.5 m)
spaced 7.5 m and 11.5 m respectively in two directions for the
redbole layers.
A grid of similar keys (3.0 X 3.5 m) spaced 7.0 m and 11.5 m
in the longitudinal and transverse directions respectively for
the argillaceous sandstone layers.
The shear keys were constructed by excavating drifts and
backfilling them with concrete.
Longitudinal shear keys were also provided in the spillway
portion (adjacent to fault zone on the right).
205
SPILLWAY SELECTION OF
SARDAR SAROVAR DAM (Block 47)
206
SUPA DAM
207
SUPA DAM
The foundation rock at the dam site consists predominantly of
banded calcareous magnetite quartzite.
There are numerous zones of weathered and weak pockets of
varying dimensions at the heel of the dam blocks, especially in
the left-flanks blocks.
To transfer the load to better rock on the U/S of the dam, a
concrete strut of 9m thickness and 20m length was provided.
To avoid tensile cracking, a joint was provided between the
body of the dam and the strut.
208
SUPA Dam Showing Heel Strut
209
SUPA Dam Showing D/S Concrete Plug
210
CLYDE DAM
211
Dudhganga Dam
213
Rana Pratap Dam
214
Rana Pratap Dam section: Cable Anchors
for improving sliding resistance
215
Dworshak Dam
216
Dworshak Dam section Buttressing structure
for improving sliding resistance
217
The end
Thanks for your attention