EFFECTIVENESS (OEE)
1
PROCESS STEPS
2
DEFINING OEE
3
EQUIPMENT STATES STACK CHART
Productive
Time
MFG - IE 4
5
What is OEE ?
▪ Over-all Equipment Effectiveness
▪ The fraction of the total time that the tool is producing effective units at theoretically
efficient rates.
OEE FORMULA :
or
6
MFG - IE
OEE FORMULA :
▪ OEE = Availability Rate x Performance Rate x Yield
where:
Availability Rate = the fraction of total time that the equipment is in a condition to
perform its intended function.
Equipment Uptime
=
Total Time
Performance Rate = the fraction of tool uptime that the equipment is processing
actual units at theoretically efficient rates
MFG - IE 7
SAMPLE OEE COMPUTATION
TRANSACTION SUMMARY:
Productive Time : 7.53 hrs. Standby/idle: 1.94 hrs.
Evaluation time : 0.00 hrs. Set-up time: 1.59 hrs.
Unscheduled DT : 0.89 hrs. Sched PM : 0.05 hr.
MFG - IE
8
SAMPLE OEE COMPUTATION
where:
= 79.49%
MFG - IE
9
SAMPLE OEE COMPUTATION
= 1,828
252
= 7.253 hours
MFG - IE
10
SAMPLE OEE COMPUTATION
= 60.44%
USING THE SECOND FORMULA :
Theoretical Production Time for Good Units
OEE =
Total Time
where:
Theoretical Time for Effective Units = Good Outs
Max. UPH
1,828
=
252
= 7.53
hours
OEE = 7.253 hours
12 hours
= 60.44%