PROJECT PARKIRAN TINGKAT

POOL WARUNG BUNCIT


 PROJECT INFORMATION
 SCOPE OF WORK
 PROJECT DIRECTION
 SITE CONDITION
 BLOCK PLAN INFORMATION
 MOODBOARD PREFERENCE
 BUSINES PROSES RANCANG BANGUN
 DENAH TAMPAK POTONGAN
 3D MODELING
PROJECT INFORMATION
PROJECT NAME PEMBANGUNAN PARKIRAN TINGKAT
Project Location Jl. Mampang Prapatan Raya No.15
Bluebird Pool Warung Buncit
PT. Bluebird Group Tbk Pho:
021
Owner 798900
0 Fax :

SCOPE OF WORK STRUCTURE, ARCHITECTURE & MEP


Coverage Area ( Sertifikat ) Lahan 3.786M2
Coverage Area ( Bangunan ) Tapak 2.142m2

SCOPE OF WORK
STRUCTURE ARCHITECTURE
 Square Pile 40x40 cm, L Floor Hardener

= 6 s.d 10 m
Piling Works  Floor Works
  PDA, Lateral, HSPD 240
 Guard Raill  Steel
Ton test

 Cut Off Piles and Pile Head - Mechanical &


Treatment
Electrical
 Excavation -
❑ Electrical System ( Low Voltage
Fc’ 30 Mpa, Fc’ 35 Mpa Distribution )
Concrete
▪ Cable Trays & Cable Ladder Accessories & Support
 Main Structure : HWF400, 300
▪ Lighting & Small Power Fixtures & Fittings
 Steel Structure  Steel Stair
▪ Emergency System for Lighting System
 Roof
 Ordinary ▪ Lightning Protection System
 Formwork Exposed

 Reinforcement Rebar  Grade BJTD – 42


 Grade BJTP – 24
PROJECT DIRECTION

Pintu Keluar
Kuningan/Mampang (TOL
DALAM KOTA)

Site Area

Bluebird Group Pool


Warung Buncit
Batas Area

Alur Masuk Lalu


Lintas Proyek

Alur Keluar Lalu


Lintas Proyek

Jl. Mampa
ng Prapata
Site Area

n Raya
OUT

IN

Jl. Mampang Prapatan VII


HGB 1
NIB :
00659
LUAS :
710 M2

Site Area

HGB 3
HGB 2 NIB :
NIB : 00657
00658 LUAS :
LUAS : 1.480 M2
1.596 M2

Sumber : jakartasatu.jakarta.go.id
Perhitungan intensitas :
Luas lahan : m2
KDB 55% :
KLB 5.35 :
Jumlah lantai bangunan :
Lahan hijau 20% :
Kesimpulan dari RUTR Pemprov DKI : Di IJINKAN

*Parkir kendaraan bermotor ,kendaraan berat


Project Information Permanent road
 Masterplan Eksisting Concreate road
Paving block
LEGEND
a. Kantin s
b. Pos satpam t
u
c. r
CE
EN TR A N
d. Awning parkir
e. Awning parkir p
v GATE
f. Area bengkel n 0
g. Mess j k
q
h. Awning parkir m
i. Awning parkir
h
j. Genzet
k. Awning mobil listrik l

n raya
l. Gedung Baru g i
m.Public space

ang prapata
n. Awning parkir f
o. Gedung Lama
p. Smoking area

Jalan mamp
q. Kandang burung
r. Kantin
s. Awning Mojul a
t. Awning
u. Awning d
v. Pos satpam
a e
c

b
Jalan mampang prapatan VII SIDE GATE
Project Information Permanent road
 Masterplan to be Concreate road
Paving block
LEGEND
a. Kantin s
b. Pos satpam t
u
c. r
CE
EN TR A N
d. Awning parkir
e. Awning parkir p
v GATE
f. Area bengkel n 0
g. Mess j k
q
h. Awning parkir m
i. Awning parkir
h
j. Genzet
k. Awning mobil listrik l

n raya
l. Gedung Baru g i
m.Public space

ang prapata
n. Awning parkir f
o. Gedung Lama
p. Smoking area w

Jalan mamp
q. Kandang burung
r. Kantin
s. Awning Mojul a
t. Awning
u. Awning d
v. Pos satpam
w. Gedung parkir a e
c

b
Jalan mampang prapatan VII SIDE GATE
Moodboard Preference
REFERENSI BIAYA

Rp.3.922.510,- /M2

15% Rp.4.450.000,- /M2


MULAI 16-Oct-23 SELESAI 1-Jan-24
PARKIRAN TINGKAT BC STATUS

KLIEN SKO & POOL BC BARU DIMULAI

3 DARI 14
21% 4 0 DARI 4 MILESTONES
SELESAI
14 TUGAS SELESAI

KEMAJUAN KESELURUHAN

ANGGARAN PROJEK FAKTUR TERSISA


1109

971
IDR 9,689,000,000 IDR 0 IDR 9,689,000,000
JAM RENCANA JAM TERPAKAI

KEMAJUAN KESELURUHAN PROJEK


100%

100%

100%

DETAIL ENGINEERING

OWNER ESTIMATE &

GROUND BREAKING
TEKNIS
BESTEK
MEMO INTERNAL
DENAH TAMPAK
KONSEP DESIGN
PERENCANAAN

AANWIJZING
10%

KONSTRUKSI
SPK
AWARDING
NEGOSIASI
APPROVAL
SITE PLAN

POTONGAN

SOIL TEST
0%

0%

0%

0%

0%

0%

DISTRIBUSI0%

0%

0%

0%

0%

PRPO &0%

0%

0%
TENDER

KLARIFIKASI
DESIGN

BESTEK

AKTIFITAS PROJEK - JADWAL

10-Nov-23

30-Nov-23
22-Aug-23

11-Sep-23

20-Dec-23
01-Oct-23

21-Oct-23

09-Jan-24
PERENCANAAN, 16-Oct-23
SITE PLAN, 16-Oct-23
KONSEP DESIGN, 17-Oct-23
DENAH TAMPAK POTONGAN, 18-Oct-23
SOIL TEST, 23-Oct-23
DETAIL ENGINEERING DESIGN, 29-Oct-23
OWNER ESTIMATE & BESTEK, 7-Nov-23
APPROVAL, 14-Nov-23
MEMO INTERNAL, 14-Nov-23
TENDER, 23-Nov-23
DISTRIBUSI BESTEK, 23-Nov-23
AANWIJZING, 24-Nov-23
KLARIFIKASI TEKNIS, 7-Dec-23
NEGOSIASI, 10-Dec-23
AWARDING, 16-Dec-23
PRPO & SPK, 23-Dec-23
KONSTRUKSI, 1-Jan-24
GROUND BREAKING, 1-Jan-24
BULAN INI LAPORAN STATUS PROJEK: PARKIRAN TINGKAT BC

TUGAS TENGGAT BULAN INI: 4

STATUS PRIORITAS KOMPLEKSITAS

4 Le vel 1 0
1

4
Le vel 2 0

Le vel 3 4
0 0
Baru Dimulai Dalam Proses Se le sai
Rendah Se dang Tinggi
Tertunda Dibatalkan LA INNYA

TUGAS MULAI BULAN INI: 5

KOMPLEKSITAS PRIORITAS STATUS

STATUS
5
Le vel 1 0

Le vel 2 0 5
3

Le vel 3 5
0 0
Baru Dimulai Dalam Proses Se le sai
Rendah Se dang Tinggi
Tertunda Dibatalkan LA INNYA

Catatan :
Tulis catatan penting di sini saat Anda ingin mencetak.
Tulis catatan penting di sini saat Anda ingin mencetak.
Tulis catatan penting di sini saat Anda ingin mencetak.
Tulis catatan penting di sini saat Anda ingin mencetak.
Tulis catatan penting di sini saat Anda ingin mencetak.
Tulis catatan penting di sini saat Anda ingin mencetak.
Tahap 2
Kapasitas daya
tamping…Mobil

M
U KA S

A RE L U
K
A RE L U
K
U KA S
M

Tahap 1
Kapasitas
daya tampung
76
Mobil/lantai
K
A RE L U
U KA S
M
R
KELUA

MASU
K
GROUND FL.
1 FL.
2 FL.
Armatur 84 Titik/lantai
TERIMA KASIH