Infrastructure and Construction Works of

Sedra Phase 3,4,5 and Warefa Single Family Units


Monthly Progress Report # 01
1-25 April, 2024

Date of Issue : 01/April/2024


1
Infrastructure and Construction Works of
Sedra Phase 3,4,5 and Warefa Single Family Units

Contents

1 - Project Overview / Scope of Work / Executive Summary 8 - HSE


2 - Design / Engineering Drawing Status 9 - Mobilization
3 - Design / Engineering Material Status 10 - Work Progress
4 - Procurement / Contract Status 11 - List of Outstanding Items
5 - Resource Chart Table ( Manpower / Equipment) 12 - Progress Photos
6 - QA/QC 13- Schedule Update/Look Ahead
7 – Risk Register
Monthly Report # 05
Period Ending 01 April 2024
2
Infrastructure and Construction Works of
Sedra Phase 3,4,5 and Warefa Single Family Units

1 - Project Overview / Scope of Work / Executive Summary

Monthly Report # 05
Period Ending 01 April 2024
3
Section 1
Project Overview / Scope of Work / Executive Summary

Project Name: Infrastructure and Construction Works of Sedra Phase 3,4,5 and Warefa
Single Family Units

Saudi Arabia, KSA.

Project Description:

PROJECT TEAM:
• End User
• Employer ROSHN
• Consultant / Client Representative East Consulting Engineering Center
• Design / Builder / Contractor CHINA HARBOUR ENGINEERING CO. LTD. (MIDDLE EAST)
• Design / Build Team

4
Section 1
Project Overview/Scope of Work / Executive Summary

NOTE:
5
Section 1
Project Overview / Scope of Work / Executive Summary

6
Section 1
Project Overview / Scope of Work / Executive Summary
Summary: Progress and Achievements

PLANNING & SCHEDULE MANAGEMENT


The Baseline Schedule is in approval stage; first submission is made on DATE and second submission is
made on DATE and third submission is made on DATE . The baseline schedule will be revised and
resubmitted as per comments of Engineer dated 21.09.2015 and ref.

BUDGET AND COST PLANNING


The preliminary BOQ prepared and input to baseline schedule according to combination of Phase 3,4 & 5
and . After completion and approval of all design works, the detailed BOQ will be submitted again.

DESIGN MANAGEMENT
Design is in progress and submission of drawings are ongoing.

DRAWINGS MANAGEMENT
In progress for the main project works.

CONSTRUCTION MANAGEMENT
Soil investigation works at is completed and approved by Engineer dated DATE .

7
Section 1
Project Overview / Scope of Work / Executive Summary
Summary: Progress and Achievements

CONTRACT& LEGAL

LOCATIONS / SITES

8
Section 1
Project Overview / Scope of Work / Executive Summary
Summary: Progress and Achievements

LOCATIONS / SITES

9
Section 1
Project Overview / Scope of Work / Executive Summary
Summary: Progress and Achievements

DOCUMENTS MANAGEMENT PLAN


In progress.

PROCUREMENT
The procurement for the project and mobilization is in progress.

10
Infrastructure and Construction Works of
Sedra Phase 3,4,5 and Warefa Single Family Units

2 - Design / Engineering Drawing Status

Monthly Report # 05
Period Ending 01 April 2024
11
Section 2
Design / Engineering Drawing Status
Summary Status of DESIGN Drawings

12
Section 2
Design / Engineering Drawing Status
Summary Status of DESIGN Drawings

13
Section 2
Design / Engineering Drawing Status
Summary Status of DESIGN Drawings

14
Section 2
Design / Engineering Drawing Status
Summary Status of CONCEPT & PRELIMINARY DESIGN Drawings

1. Roads, Landscape and Infrastructure Design are ongoing and will be finalized based on soil
investigation report.

15
Section 2
Design / Engineering Drawing Status
Summary Status of IFC Drawings :

Not started.

16
Section 2
Design / Engineering Drawing Status
Summary Status of SHOP DRAWINGS :

Not started.

17
Infrastructure and Construction Works of
Sedra Phase 3,4,5 and Warefa Single Family Units

3 - Design / Engineering Material Status

Monthly Report # 05
Period Ending 01 April 2024
18
Section 3
Design / Engineering (Materials Status)
Summary Status of MATERIALS SUBMITTALS:

19
Section 3
Design / Engineering (Long Lead Items)

STRUCTURAL (For information)

No Description

1 Precast - Super Structure

2 Steel Ladders w/ Cage

3 Space Frame Roofing System

4 Miscellaneous Metal Works

5 Structural Steel

6 Roof System

Schedule for Long lead items have been submitted on date and accepted dated dste. Upon approval of the baseline
schedule material procurement updates will be tracked in the reports.

20
Section 3
Design / Engineering (Long Lead Items)

ARCHITECTURAL (For information)


No Description
1 Metal Handrails
2 Wooden Kitchen Cabinets & Counter Tops .
3 Roof System and Wet Areas
4 Hollow Metal Doors, Frames
5 Aluminum Windows & Doors
6 Wooden Doors, Frames
7 Hardware for Wooden and Metal Doors
8 Steel Gates
9 Porcelain,Ceramic Tiles & Skirting
10 Marble / Granite
11 Suspended Plaster Board & Acoustic Ceiling
12 Non-Slip Epoxy Flooring
13 Vinyl Sheet Flooring
14 Gypsum Ceiling and Panels
15 Internal & External Signage
16 Toilet Accessories
17 GRC Fiber Dome & Sky Light
18 Manholes with Covers

Schedule for Long lead items have been submitted on gate and accepted dated date. Upon approval of the baseline
schedule material procurement updates will be tracked in the reports.

21
Section 3
Design / Engineering (Long Lead Items)

MECHANICAL (For Information)

No Description

1 Medical Equipment

2 Workshop Equipment

3 HVAC System Equipment

4 Swimming Pool Equipment

5 Potable Water System Equipment

6 Sanitary Fixtures

7 Liquified Natural Gas System (LPG)

8 Water Transfer Pumps & Overhead GRP Tanks

9 Fire Fighting System Equipment

10 STP

11 RO

Schedule for Long lead items have been submitted on date and accepted dated date. Upon approval of the baseline
schedule material procurement updates will be tracked in the reports.

22
Section 3
Design / Engineering (Long Lead Items)

ELECTRICAL (For information)


No Description
1 Control Panel for HVAC System
2 Lighting Panel Board
3 LV Cables
4 Package Substation
5 Lighting Fixtures
6 MATV System
7 Addressable Fire Alarm System
8 IP Camera CCTV System
9 Public Address System
10 Access Control System
11 IP Telephone System
12 Low Current System
13 Data & Intercomm Systems
14 UPS system

Schedule for Long lead items have been submitted on 10.09.2015 and accepted dated 20.09.2015. Upon approval of
the baseline schedule material procurement updates will be tracked in the reports.

23
Section 3
Design / Engineering (Materials Register)

Schedule for Long lead items have been submitted on DATE for approval. Engineer accepted on date.

24
Section 3
Design / Engineering (Materials Register)

Materials Register: Structural

25
Section 3
Design / Engineering (Materials Register)

Materials Register: C&A

26
Section 3
Design / Engineering (Materials Register)

Materials Register: Electrical

27
Section 3
Design / Engineering (Materials Register)

Materials Register: Mechanical

28
Section 3
Design / Engineering Status
Summary Status of METHOD STATEMENTS:

29
Section 3
Design / Engineering Status (Method Statement – Bldgs)

Method Statement Submittal Register : Civil

30
Section 3
Design / Engineering Status (Method Statement – Bldgs)

Method Statement Submittal Register : Civil

31
Section 3
Design / Engineering Status (Method Statement – Bldgs)

Method Statement Submittal Register: Architectural

32
Section 3
Design / Engineering Status (Method Statement – Bldgs)

Method Statement Submittal Register: Architectural

33
Section 3
Design / Engineering Status (Method Statement – Bldgs)

Method Statement Submittal Register: Mechanical (Buildings)

34
Section 3
Design / Engineering Status (Method Statement – Bldgs)

Method Statement Submittal Register: Mechanical (Buildings)

35
Section 3
Design / Engineering Status (Method Statement – Bldgs)

Method Statement Submittal Register: Electrical (Buildings)

36
Section 3
Design / Engineering Status (Method Statement – Bldgs)

Method Statement Submittal Register: Electrical (Buildings)

37
Section 3
Design / Engineering Status (Method Statement – Bldgs)

Method Statement Submittal Register: Plumbing (Buildings)

The method of statement list are included in the approved with B-code QA/QC document. Tracking will be followed
according to this list.

No method statement has been submitted in this month

38
Section 3
Design / Engineering Status (Method Statement – Bldgs)

Method Statement Submittal Register: Fire Fighting (Buildings)

The method of statement list are included in the approved with B-code QA/QC document. Tracking will be followed
according to this list.

No method statement has been submitted in this month

39
Section 3
Design / Engineering Status (Method Statement – Bldgs)

Method Statement Submittal Register: HVAC (Buildings)


The method of statement list are included in the approved with B-code QA/QC document. Tracking will be followed
according to this list.

No method statement has been submitted in this month

40
Section 3
Design / Engineering Status (Method Statement – Bldgs)

Method Statement Submittal Register: Irrigation (Buildings)


The method of statement list are included in the approved with B-code QA/QC document. Tracking will be followed
according to this list.

No method statement has been submitted in this month

IRRIGATION (Buildings)
No Description Status

NOTE:
The method statement register was submitted and approved with “B-code”. A revision of the register is now in
progress and in accordance with Consultant`s comments.

41
Infrastructure and Construction Works of
Sedra Phase 3,4,5 and Warefa Single Family Units

4 - Procurement / Contract Status

Monthly Report # 05
Period Ending 01 April 2024
42
Section 4
Procurement / Contracts Status

Summary Status of MATERIALS

43
Section 4
Procurement / Contracts Status

Summary Status of SUBCONTRACTORS

44
Infrastructure and Construction Works of
Sedra Phase 3,4,5 and Warefa Single Family Units

5 - Resource Chart Table ( Manpower / Equipment)

Monthly Report # 05
Period Ending 01 April 2024
45
Section 5
Resource Chart Manpower & Equipment - (Current)

Resource figures as of 25th of April, 2024.

Manpower & Equipment(For information)

275 269

225

175
Total Qty.

125

75

25
0
Manpower Equipment
September-15 269 0

46
Section 5
Manpower Histogram
(Baseline Vs Actual)

47
Section 5
Equipment Histogram
(Baseline Vs Actual)

Revised Baseline schedule has been submitted on 10/Sept/2024. It has been under review by Engineer.

48
Infrastructure and Construction Works of
Sedra Phase 3,4,5 and Warefa Single Family Units

6 - QA/QC

Monthly Report # 05
Period Ending 01 April 2024
49
Section 6
QA / QC

02210 - SPECIFICATION FOR SUBSURFACE INVESTIGATION site work completed. Draft report is submitted to
Consultant on 14th of September.

50
Infrastructure and Construction Works of
Sedra Phase 3,4,5 and Warefa Single Family Units

7 – Risk Register

Monthly Report # 05
Period Ending 01 April 2024
51
Section 7
RISK REGISTER

RISKS

Impact Type
Mitigation /
Risk
Code Number Risk Name Risk Description Enhancement
Initiator Cost Time Quality Other
Plan

Project
CONTRACT. 01 Manageme - TBD TBD - -
nt

Project
CONTRACT. 01 Manageme - TBD TBD - -
nt

ISSUES

52
Infrastructure and Construction Works of
Sedra Phase 3,4,5 and Warefa Single Family Units

8-HSE

Monthly Report # 05
Period Ending 01 April 2024
53
Section 8
HSE Report

MONTHLY SAFETY REPORT


Health & Safety MONTH OF April 2024
Department

54
Section 8
Safety

No incidents/accidents have been reported in this month.

55
Infrastructure and Construction Works of
Sedra Phase 3,4,5 and Warefa Single Family Units

9 - Mobilization

Monthly Report # 05
Period Ending 01 April 2024
56
Section 9
Mobilization Plan (Site camps)

Summary of the works have been carried out at Mobilization

57
Section 9
Mobilization Plan (Site camps)

1000-person camp is planned for Phase 3,4 & 5 site.

58
Infrastructure and Construction Works of
Sedra Phase 3,4,5 and Warefa Single Family Units

10 - Work Progress

Monthly Report # 05
Period Ending 01 April 2024
59
Section 10
Work Progress (Civil & Architectural)

60
Section 10
Work Progress (Infrastructure / Roads)

Nothing has been reported in this month.

61
Section 10
Work Progress (MEP)

Nothing has been reported in this month.

62
Infrastructure and Construction Works of
Sedra Phase 3,4,5 and Warefa Single Family Units

11 – Contractual Issues & Outstanding Items

Monthly Report # 05
Period Ending 01 April 2024
63
Section 11
List of Outstanding Items with Roshn/Consultant

64
Infrastructure and Construction Works of
Sedra Phase 3,4,5 and Warefa Single Family Units

12 - Progress Photos

Monthly Report # 05
Period Ending 01 April 2024
65
Section 12
Progress Photos

Camp Area – Site Levelling

66
Section 12
Progress Photos

Mobilization

67
Section 12
Progress Photos

Mobilization – WC & Shower Units Brickwork

68
Section 12
Progress Photos
Mobilization – Labor Bathroom- Brickwork

69
Section 12
Progress Photos
Mobilization – Fence Erection

70
Section 12
Progress Photos

Mobilization – Warehouse and Open Storage Area Grading

71
Section 12
Progress Photos
Site – Warehouse and Open Storage Area Grading

72
Infrastructure and Construction Works of
Sedra Phase 3,4,5 and Warefa Single Family Units

13 - Schedule Update / Look Ahead

Monthly Report # 05
Period Ending 01 April 2024
73
Section 13
Schedule Update
(Summary)

Not submitted in this month.(After approval of the baseline schedule)

74
Section 13
Schedule Update
(Progressing Activities)

Not submitted in this month. (After approval of the baseline schedule)

75
Section 13
Schedule Update
(2-Weeks Look Ahead Schedule)

Not submitted in this month .(After approval of the baseline schedule)

76
Section 13
Schedule Update
(Longest Path)

Not submitted in this month .(After approval of the baseline schedule)

77
Infrastructure and Construction Works of
Sedra Phase 3,4,5 and Warefa Single Family Units

THANK YOU
Monthly Report # 05
Period Ending 01 April 2024
78