Professional Documents
Culture Documents
MONTHLY REPORT TO EAST Con
MONTHLY REPORT TO EAST Con
Contents
Monthly Report # 05
Period Ending 01 April 2024
3
Section 1
Project Overview / Scope of Work / Executive Summary
Project Name: Infrastructure and Construction Works of Sedra Phase 3,4,5 and Warefa
Single Family Units
Project Description:
PROJECT TEAM:
• End User
• Employer ROSHN
• Consultant / Client Representative East Consulting Engineering Center
• Design / Builder / Contractor CHINA HARBOUR ENGINEERING CO. LTD. (MIDDLE EAST)
• Design / Build Team
4
Section 1
Project Overview/Scope of Work / Executive Summary
NOTE:
5
Section 1
Project Overview / Scope of Work / Executive Summary
6
Section 1
Project Overview / Scope of Work / Executive Summary
Summary: Progress and Achievements
DESIGN MANAGEMENT
Design is in progress and submission of drawings are ongoing.
DRAWINGS MANAGEMENT
In progress for the main project works.
CONSTRUCTION MANAGEMENT
Soil investigation works at is completed and approved by Engineer dated DATE .
7
Section 1
Project Overview / Scope of Work / Executive Summary
Summary: Progress and Achievements
CONTRACT& LEGAL
LOCATIONS / SITES
8
Section 1
Project Overview / Scope of Work / Executive Summary
Summary: Progress and Achievements
LOCATIONS / SITES
9
Section 1
Project Overview / Scope of Work / Executive Summary
Summary: Progress and Achievements
PROCUREMENT
The procurement for the project and mobilization is in progress.
10
Infrastructure and Construction Works of
Sedra Phase 3,4,5 and Warefa Single Family Units
Monthly Report # 05
Period Ending 01 April 2024
11
Section 2
Design / Engineering Drawing Status
Summary Status of DESIGN Drawings
12
Section 2
Design / Engineering Drawing Status
Summary Status of DESIGN Drawings
13
Section 2
Design / Engineering Drawing Status
Summary Status of DESIGN Drawings
14
Section 2
Design / Engineering Drawing Status
Summary Status of CONCEPT & PRELIMINARY DESIGN Drawings
1. Roads, Landscape and Infrastructure Design are ongoing and will be finalized based on soil
investigation report.
15
Section 2
Design / Engineering Drawing Status
Summary Status of IFC Drawings :
Not started.
16
Section 2
Design / Engineering Drawing Status
Summary Status of SHOP DRAWINGS :
Not started.
17
Infrastructure and Construction Works of
Sedra Phase 3,4,5 and Warefa Single Family Units
Monthly Report # 05
Period Ending 01 April 2024
18
Section 3
Design / Engineering (Materials Status)
Summary Status of MATERIALS SUBMITTALS:
19
Section 3
Design / Engineering (Long Lead Items)
No Description
5 Structural Steel
6 Roof System
Schedule for Long lead items have been submitted on date and accepted dated dste. Upon approval of the baseline
schedule material procurement updates will be tracked in the reports.
20
Section 3
Design / Engineering (Long Lead Items)
Schedule for Long lead items have been submitted on gate and accepted dated date. Upon approval of the baseline
schedule material procurement updates will be tracked in the reports.
21
Section 3
Design / Engineering (Long Lead Items)
No Description
1 Medical Equipment
2 Workshop Equipment
6 Sanitary Fixtures
10 STP
11 RO
Schedule for Long lead items have been submitted on date and accepted dated date. Upon approval of the baseline
schedule material procurement updates will be tracked in the reports.
22
Section 3
Design / Engineering (Long Lead Items)
Schedule for Long lead items have been submitted on 10.09.2015 and accepted dated 20.09.2015. Upon approval of
the baseline schedule material procurement updates will be tracked in the reports.
23
Section 3
Design / Engineering (Materials Register)
Schedule for Long lead items have been submitted on DATE for approval. Engineer accepted on date.
24
Section 3
Design / Engineering (Materials Register)
25
Section 3
Design / Engineering (Materials Register)
26
Section 3
Design / Engineering (Materials Register)
27
Section 3
Design / Engineering (Materials Register)
28
Section 3
Design / Engineering Status
Summary Status of METHOD STATEMENTS:
29
Section 3
Design / Engineering Status (Method Statement – Bldgs)
30
Section 3
Design / Engineering Status (Method Statement – Bldgs)
31
Section 3
Design / Engineering Status (Method Statement – Bldgs)
32
Section 3
Design / Engineering Status (Method Statement – Bldgs)
33
Section 3
Design / Engineering Status (Method Statement – Bldgs)
34
Section 3
Design / Engineering Status (Method Statement – Bldgs)
35
Section 3
Design / Engineering Status (Method Statement – Bldgs)
36
Section 3
Design / Engineering Status (Method Statement – Bldgs)
37
Section 3
Design / Engineering Status (Method Statement – Bldgs)
The method of statement list are included in the approved with B-code QA/QC document. Tracking will be followed
according to this list.
38
Section 3
Design / Engineering Status (Method Statement – Bldgs)
The method of statement list are included in the approved with B-code QA/QC document. Tracking will be followed
according to this list.
39
Section 3
Design / Engineering Status (Method Statement – Bldgs)
40
Section 3
Design / Engineering Status (Method Statement – Bldgs)
IRRIGATION (Buildings)
No Description Status
NOTE:
The method statement register was submitted and approved with “B-code”. A revision of the register is now in
progress and in accordance with Consultant`s comments.
41
Infrastructure and Construction Works of
Sedra Phase 3,4,5 and Warefa Single Family Units
Monthly Report # 05
Period Ending 01 April 2024
42
Section 4
Procurement / Contracts Status
43
Section 4
Procurement / Contracts Status
44
Infrastructure and Construction Works of
Sedra Phase 3,4,5 and Warefa Single Family Units
Monthly Report # 05
Period Ending 01 April 2024
45
Section 5
Resource Chart Manpower & Equipment - (Current)
275 269
225
175
Total Qty.
125
75
25
0
Manpower Equipment
September-15 269 0
46
Section 5
Manpower Histogram
(Baseline Vs Actual)
47
Section 5
Equipment Histogram
(Baseline Vs Actual)
Revised Baseline schedule has been submitted on 10/Sept/2024. It has been under review by Engineer.
48
Infrastructure and Construction Works of
Sedra Phase 3,4,5 and Warefa Single Family Units
6 - QA/QC
Monthly Report # 05
Period Ending 01 April 2024
49
Section 6
QA / QC
02210 - SPECIFICATION FOR SUBSURFACE INVESTIGATION site work completed. Draft report is submitted to
Consultant on 14th of September.
50
Infrastructure and Construction Works of
Sedra Phase 3,4,5 and Warefa Single Family Units
7 – Risk Register
Monthly Report # 05
Period Ending 01 April 2024
51
Section 7
RISK REGISTER
RISKS
Impact Type
Mitigation /
Risk
Code Number Risk Name Risk Description Enhancement
Initiator Cost Time Quality Other
Plan
Project
CONTRACT. 01 Manageme - TBD TBD - -
nt
Project
CONTRACT. 01 Manageme - TBD TBD - -
nt
ISSUES
52
Infrastructure and Construction Works of
Sedra Phase 3,4,5 and Warefa Single Family Units
8-HSE
Monthly Report # 05
Period Ending 01 April 2024
53
Section 8
HSE Report
54
Section 8
Safety
55
Infrastructure and Construction Works of
Sedra Phase 3,4,5 and Warefa Single Family Units
9 - Mobilization
Monthly Report # 05
Period Ending 01 April 2024
56
Section 9
Mobilization Plan (Site camps)
57
Section 9
Mobilization Plan (Site camps)
58
Infrastructure and Construction Works of
Sedra Phase 3,4,5 and Warefa Single Family Units
10 - Work Progress
Monthly Report # 05
Period Ending 01 April 2024
59
Section 10
Work Progress (Civil & Architectural)
60
Section 10
Work Progress (Infrastructure / Roads)
61
Section 10
Work Progress (MEP)
62
Infrastructure and Construction Works of
Sedra Phase 3,4,5 and Warefa Single Family Units
Monthly Report # 05
Period Ending 01 April 2024
63
Section 11
List of Outstanding Items with Roshn/Consultant
64
Infrastructure and Construction Works of
Sedra Phase 3,4,5 and Warefa Single Family Units
12 - Progress Photos
Monthly Report # 05
Period Ending 01 April 2024
65
Section 12
Progress Photos
66
Section 12
Progress Photos
Mobilization
67
Section 12
Progress Photos
68
Section 12
Progress Photos
Mobilization – Labor Bathroom- Brickwork
69
Section 12
Progress Photos
Mobilization – Fence Erection
70
Section 12
Progress Photos
71
Section 12
Progress Photos
Site – Warehouse and Open Storage Area Grading
72
Infrastructure and Construction Works of
Sedra Phase 3,4,5 and Warefa Single Family Units
Monthly Report # 05
Period Ending 01 April 2024
73
Section 13
Schedule Update
(Summary)
74
Section 13
Schedule Update
(Progressing Activities)
75
Section 13
Schedule Update
(2-Weeks Look Ahead Schedule)
76
Section 13
Schedule Update
(Longest Path)
77
Infrastructure and Construction Works of
Sedra Phase 3,4,5 and Warefa Single Family Units
THANK YOU
Monthly Report # 05
Period Ending 01 April 2024
78