P&E Dept Profile
P&E Dept Profile
&
WORKS UNDERTAKEN
ORGANIZATION SET UP
(As on March 2019)
1 132kV line Bairabi to W.Phaileng via Mamit NEC 5495.00 Jun 2020
7 33kV line Kau Tlabung SHP to Thenhlum DoNER 782.00 Dec 2019
NEC &
8 Tuiriza & Tuiching MHP (100kW each) 376.07 Oct 2019
MNRE
CENTRAL SCHEMES IMPLEMENTED
1. SAUBHAGYA (Pradhan Mantri Sahaj Bijli Har Ghar Yojana)
Sanctioned Amount : Rs 65.28 crore
Fund already received : Rs 30.53 crore
Scope : Providing electricity to 25755 households within 2018.
SUB-STATION:
i) 132/33 kV W.Phaileng (New) : 2x12.5 MVA.
ii) 132/33 kV Marpara (New) : 2x12.5 MVA.
iii) 132/33 kV Lungsen (New) : 2x12.5 MVA.
iv) 132/33 kV Lunglei (Ext./Aug.) : 4x8.33 MVA.
v) 33/11 kV S. Bungtlang (New) : 2x3.15 MVA.