JHA: Job Hazard Analysis


JSA: Job Safety Analysis
JRA: Job Risk Assessment
WHY ?
Rev 4 – May 03

WHY IS JOB SAFETY ANALYSIS NECESSARY?

• Risks cause accidents


• Activity (company, contractors)
• Size means exposure
• Regulations & Company Policy
GENERAL SAFETY PRINCIPALS
Rev 4 – May 03

• Avoid risks
• Assess the risks which cannot be avoided
• Reduce risk from the origine
• Replace hazardous by non- or less
hazardous
• Give priority to collective protections
before PPE’s
• …
Job Safety Analysis
Rev 4 – May 03

R1 – Analysis can be done during operations

E.G. Risk assessment at work places

Safety audit,

Improving working environment


Job Safety Analysis
Rev 4 – May 03

R2 - Analysis can be done before operations

DESIGN of work scope, procedures …

Preparing CO-ACTIVITY of several companies

or persons on same job


SCOPE
Rev 4 – May 03

 PREPARATION stage of NON-ROUTINE WORKS


which appear to pose a significant threat.
- technical hazards
- co-ordination
eg: SIMULTANEOUS OPS

 REVIEW of existing procedures


Job Safety Analysis
Rev 4 – May 03

Job Safety Analysis must be used to


communicate between operators
about:
 RISK
 SAFETY MEASURES
Job Safety Analysis
Rev 4 – May 03

The JSA is very helpful to keep in mind all the risk and precautions
associated to a risky operation.
… and the Pre Job Meeting is the right time to remind all that.
EXAMPLE
Rev 4 – May 03

Risk
NEEDS
Rev 4 – May 03

 METHOD to cover all possibilities


 PROMPT LISTS to facilitate

 TEAM WORK to share knowledge

ALSO:  INSPECT SITE CAREFULLY to take


particular conditions into account
 Use audits and drills analysis
report
Rev 4 – May 03

METHOD
RISKS ANALYSIS
Rev 4 – May 03

OBJECTIVES :

 Identify Hazards
 Assess Risks

 Define preventive and protective measures


Design phase, Permit to Work, SIMOPS

 Prepare recovery in case of incident


DESCRIPTION OF ACTIVITIES
Rev 4 – May 03

Observe and to describe activities

 Observe

 See safety rules

 Question the workers

 Identify the differences between procedures


and real practices
 Identify downgraded phases
ASSESS RISKS
Rev 4 – May 03

Evaluate risks

Definition:

Risks means the combination of

 the likelihood

 the potential consequences of the hazardous event


Rev 4 – May 03

Evaluate risks

WAYS OF DOING

THE JOB

CHOSEN BY THE

WORKERS

DIFFERENTLY

THAN EXPECTED
Job Safety Analysis
Rev 4 – May 03

Evaluate risks

Risk is linked with exposure frequency


 
( L) LIKELIHOOD OF OCCURRENCE
V.L OW LOW MED HIGH V.HIGH
NEGLIGIBLE LOW LOW LOW LOW MED
SEVERITY
HAZARD

MODERATE LOW LOW LOW MED HIGH


(S)

SERIOUS LOW LOW MED HIGH HIGH


MAJOR LOW MED HIGH HIGH HIGH
CATASTROPHIC MED HIGH HIGH HIGH HIGH

(L) LIKELIHOOD OF OCCURRENCE


Very Low Between 1 & 10 years

Low Less than 1 year

Medium Less than 1 month

High Less than 1 week

Very High Daily


Job Safety Analysis
Rev 4 – May 03

Evaluate risks

Imagine most probable results


( L) LIKELIHOOD OF OCCURRENCE
V.L OW LOW MED HIGH V.HIGH
NEGLIGIBLE LOW LOW LOW LOW MED
SEVERITY
HAZARD

MODERATE LOW LOW LOW MED HIGH


(S)

SERIOUS LOW LOW MED HIGH HIGH


MAJOR LOW MED HIGH HIGH HIGH
CATASTROPHIC MED HIGH HIGH HIGH HIGH

(S) HAZARD SEVERITY


NEGLIGIBLE Minor injury

MODERATE Lost time injury

SERIOUS Permanent disability

MAJOR Fatality

CATASTROPHIC Multiple fatalities and any other injuries


Job Safety Analysis
Rev 4 – May 03

Evaluate risks

Risk Rating
( L) LIKELIHOOD OF OCCURRENCE
V.L OW LOW MED HIGH V.HIGH
NEGLIGIBLE LOW LOW LOW LOW MED
SEVERITY
HAZARD

MODERATE LOW LOW LOW MED HIGH


(S)

SERIOUS LOW LOW MED HIGH HIGH


MAJOR LOW MED HIGH HIGH HIGH
CATASTROPHIC MED HIGH HIGH HIGH HIGH

( R ) RISK RATING
LOW No immediate action required. Proceed with care
Hazard to be investigated in conjunction with line
MEDIUM
manager / supervisor with a view to reducing the risk
Task must not be undertaken.
HIGH Immediate action must be taken to eliminate the risk
or substantially reduce the risk.
SAFETY MEASURES
Rev 4 – May 03

Define safety measures to be enforced

 Determine preventive and protective measures

 Prepare recovery in case of incident


SAFETY MEASURES
Rev 4 – May 03

Define safety measures to be enforced

HOW TO CHOOSE SUITABLE SOLUTIONS ?

EFFICIENCY
SIMPLICITY
LONG LASTING
FEW CONSTRAINTS FOR THE WORKER
RISK NOT TRANSFERRED
LEGAL COMPLIANCE
CAN BE APPLIED TO OTHER SITES
DELIVERY TIME
EXAMPLE
Rev 4 – May 03

Select jobs to be assessed


Job Safety Analysis
EXAMPLE
Rev 4 – May 03

Observe and to describe activities

Job Safety Analysis


EXAMPLE
Rev 4 – May 03

Identify hazards
Job Safety Analysis
EXAMPLE
Rev 4 – May 03

Evaluate risks
Job Safety Analysis
EXAMPLE
Rev 4 – May 03

Define safety measures to be enforced

Job Safety Analysis


COMMUNICATION
Rev 4 – May 03

Use & communicate JSA during Meeting!

A documented JSA Databases, used as PJM Tool, will constitute a feed back:
 For the others Crews in time off, who have not participated to this operation

 By revising JSA (if change in procedure or new identified risk appears),


in order to advide others crews.

 For the others Rigs, sharing the experience of each one.


PLAN:
By Risk Assessment

DO:
 By anticipation (with PJM
REVIEW: documented by JSA)
By revising JSA
(Post Job Meeting)  By Rules of Arts & Procedure

CHECK

JSA “Feed back for the others”


UNDERSTANDING
Rev 4 – May 03

COMMUNICATION IS A 2- WAY PROCESS

ASK
CONTRACTORS / PERSONNEL
TO REPEAT
THE RISK IDENTIFIED
AND THE SAFETY PRECAUTIONS
REVIEW
Rev 4 – May 03

COMMUNICATION IS A 2- WAY PROCESS


ASK
CONTRACTORS / PERSONNEL
TO ASSESS THE EFFICIENCY
OF THE PROPOSED MEASURES
VS THE RISK ANALYSIS.
It will ensure that
WORKERS
HAVE UNDERSTOOD
CONCLUSIONS
Rev 4 – May 03

 All relevant partners, companies, contractors are involved in the Job


Safety Analysis
 The Job Safety Analysis is based on a structured method (energies)
and on personnel experience to focus on major risks.

 Risk Assessment always includes a thorough inspection of the site

 Risk Assessment is used during the pre-job meeting

 Risk Assessment is to be re-used to repeat the operation, update


procedures, train the green hands, make safety specs for the
subcontractors...
Rev 4 – May 03

You might also like