Professional Documents
Culture Documents
Sectional
Sectional
Sectional
COMPLETION/P
ARTIAL
COMPLETION
DIPLOMA OF QUANTITY
SURVEYING
MISS BINTULHUDA BINTI
ZAINODIN
INTRODUCTION
● Large project takes a long time to finish,
employer need to wait longer.
● Some building contract allows employer to
occupy the completed parts of the works before
the completion of whole works.
● Relevant parts must be made known in advance
by the employer during tendering stage or during
progress of the work.
Relevant contractual provisions
Effects of
C.C.M.G.D Sectional L.A.D
Completion.
D.L.P
PARTIAL COMPLETION
PAM Form Clause 42.1
● The employer takes early possession of a section or sections of the
works with the agreement of the contractor while the work is in
progress
● The provision allows for any part of the completed works to be
handed over to the employer before practical completion
● Consent from the contractor is required.
● The contractor’s consent is not to be unreasonably withheld i.e. the
contractor is bound to give his consent to the government’s request
for partial completion
● Without such consent – the employer will be breach of his obligation
to give the contractor complete possession of site until completion
Effects of partial completion
Clause 42.1(b)
● Section is deemed to have reached practical completion
but no formal CPC is issued
● D.L.P starts immediately for that section
● CPC to be issued only once on the completion of the
whole works
Effects of partial completion
C.C.M.G.D
Clause 42.1(c)
● CCMGD to be issued :
a) On expiry of DLP for the section
b) Upon making good defects by the contractor for that
section
Effects of partial completion
L.A.D
Clause 42.1(d)