PM PRACTICE SUMS

Practice Sum 1
TASK PRECEDENCE NORMAL CRASH NORMAL COST ($) CRASH COST ($)
From the data provided TIME TIME
below draw the network (WKS) (WKS)
diagram and determine A - 4 4 10,000 10000
how will you crash the
project when you are asked B - 4 3 11,500 12000
to crash by
C - 5 4 12,000 16000
• 2 weeks
D A 7 6 20,000 21000
• Maximum possible
E B 6 4 24,000 28,000
If the deadline of the
project is 24 weeks and the F B 8 6 17,000 20,000
penalty to be paid per
week of delay is $1,500 G C 10 6 80,000 105,000
how much would you crash H D 9 7 30,000 33,000
the project by
I E,F 7 5 20,000 30,000
J H,I,G 6 6 15,000 15,000
Practice Sum 2 TASK PRECEDENCE NORMAL
TIME
CRASH NORMAL CRASH
TIME COST ($) COST
(WKS) (WKS) ($)
From the data provided below draw the A - 4 3 10,000 12,000
network diagram and determine how will
you crash the project when you are asked B - 3 2 12,000 13,000
to crash by Maximum possible. C - 5 3 15,000 20,000
If the client decides to provide a reward, D A 7 4 17,000 23,000
by how much will you crash the project if
the reward earned per week of crashing is E B 6 5 14,000 16,000
1. $1,500 F B 8 5 42,000 48,000
2. $3,000 G C 6 5 20,000 23,000
3. $4,000
H D 8 6 30,000 30,500
I E,F 7 6 25,000 30,000
J G 7 3 21,000 28,000
K H,I,J 5 2 16,000 20,000