Professional Documents
Culture Documents
Final DAK - Contract II AKK Project Security Challenges
Final DAK - Contract II AKK Project Security Challenges
3
Part
I: Project Status
Connects Dabat and Tsegede woreda with a 57 km DB - DBST surfacing DC4
Geometric standard road Project
• BOP - Ajire Town 43+200 and EOP 99+140 (Ketema Nigus)
• Powercon PLC JV with TLC and the Subcontractor TONSA engaged Contract
amount:- 1,158,659,797.00 ETB including 15% VAT
Project Status as of end of May 2023 :- 63.79% Physical Progress (36.36KM)
Project Commenced on 21st of September 2018
• Contract period :-1095 Calendar Days
• Total Requested EOT:- 1206 Calendar Days (Ends on January 8th -2025)
• Approved EOT :- 706 Calander Days (including interim EOT till August 27th 2023)
• 505 calendar days (excluding consequential delays associated thereof ), was a
recorded total cessation period due to security- apparent disorder
• Disorder days requested EOT 1- 98 days, EOT -2 181 days, EOT-3 216 days EOT – 4 74
days ( total disruption requested dates 569 days as August 19th 2023
Part I: Project Status and Idle resources
No Equipment Type Site Availability in Number
1 Dozer 5
2 Grader 2
3 Excavator 13
4 Wagen Drill 2
5 Roller 2
6 Loader 3
7 McCloskey Crusher (3 unit) 1
8 Dump Trucks 5
9 Water truck 2
10 Fuel Truck 2
11 Generator 6
12 Mixer 7
Part II: Project Security Challenges
Part II: Project Security Challenges Continued…
Sample Security challenge on 2015 E.C
Disruption at crusher site due to ROW payment delay (from
September – end of Oct 2023 ( 61 days )
Project cessation - Security challenge:- (Jan 2nd – Feb 18th 2023
I Cr and June 6, 2023 until now)
2015
n Calander days
us Consumption
ef her
R
fe
ct
iv
O
W; Disruption due ROW payment delay: road blockage and
61;
e 17
r
u
ct
ssa
tio
n
Disruption due to Government disbanding rebels:-
io du
n
Lawlessness and effect on work execution and supply challenge
Dis e
P rup to
e tion Se
ri due cu
o to rit
d
;
1
RO
W,
31,
y ;
13
starting from April 2023 (Lot I closed for > 2 weeks)
Crusher ROW 9% Cessation due5;to Security
3 37
Disruption due to ROW Ineffective Construction Period
7
;
3
%
Ineffective Construction Period:- was 137 days (38% of C.
8
%
days)
7
Part II: Project Security Challenges continued…
Contractor Main challenges
1. Security/Disorder Direct Nature:-
Killing of Project Staffs
Attack on Contractor’s Staff,
Harassment and intimidation,
Kidnapping of project staff
continuous robbery and looting of properties
Effect :- Project Cessation, and stoppage of work
Security/Disorder Indirect Effect
Inability to mobilize/demobilize resources,
Lessors declination to lease and transporters declination to serve,
Key staffs decline to go to site
Huge cost of reorganization and remobilization after each disruption 8
Part II: Project Security Challenges continued…
9
Part II: Project Security Challenges continued…
10
Part III: A. Incident occurrences, and
B. Incident continuity Causes
11
Part III: Incident occurrences
Notable Incidents on execution of project works:-
Killing of contractor staff (Death of Loader operator on cold blood murder)
Attack on Project staffs including trial of assassination of PM, PA and other
Kidnaping of project staffs and Intimidation
Continues Bullet Attack on small vehicles, Dump trucks and Operators
Attack on guards, Contractor’s and Engineer’s office which costed 5 human life
Bullet shooting incidents on site visit on presence of ARE and PM
Killing of policemen on different occasions
Engagement of cross fire and attack on deployed special forces
12
Part III: A. Incident occurrences cont’d….
Attack on Project staff using sharp material
Repetitive Road Blockage and robbery (3 incident occurrences in one Month
including an attack on employer’s representative staff on May 2023)
Life threatening incident in near and cross by conflict within the local peoples
Threatening Subcontractor project manager and construction Engineer
Attack on Forman while doing works and later left the contractor due to threat
Incident occurrences on every Saturday and half day project closure
Attack on meeting gathering including the presence of woreda administrator and
zonal higher officials (death of rebel)
13
Part III: A. Incident occurrence cont’d….
Prevailing restrictions, Sporadic and unpredictable armed engagement between
government forces and rebels (on both April 2023 and recently since November 11th
2023)
Forceful usage of contractors property and threatening the contractor for legal act
Continuous looting of contractor’s property from project site camp (Fuel, cements,
reinforcements, Mixers, radio communication devices, Equipment parts, tools and
materials including plywood formworks and woods,
Hinderance and forbidding of demobilizing resources which in turn affect on
project’s resources balancing.
14
PART III: Incidents occurrences cont’d….
Project full suspension recorded Periods (more than 505 days)
Kidnaping of 2 contractor’s Staff and 2 Policemen, and bullet attack on
13 peoples and death of 6 persons
From February 12-17 2020 and Feb 25 – May 23 2020 (62 days)