Professional Documents
Culture Documents
Managment PTW Presentation For Rev System Draft
Managment PTW Presentation For Rev System Draft
Managment PTW Presentation For Rev System Draft
• Construction Area - One PTW Coordinator (with back-to-back) + PTW Officer/Administrator (with back-to-back)
• Commissioning Area -One PTW Coordinator (with back-to-back) + PTW Officer/Administrator (with back-to-
back)
• Dedicated PTW Offices - one per each Construction and Commissioning area.
• Offices will be open for permit verification and registration (Proposed Timings are 06:30 to 11:15 Hrs) and
signing session (Afternoon 16:30 to 17:15)
• Permit forms will be made available from the PTW offices and respective contractor PTW Coordinators
/Administrator will collect, keep and control their issue.
•
Signing Session of Permits/Meetings
• Enerflex Area PTW offices are Open for Contractors from 06:30 to 11:15 Hrs and on Signing Session
(time to be agreed).
• Permit requestors visit their respective Area PTW offices during this period to undergo permit review
and registration.
• There will be only 1 (ONE) Signing Session Meeting for the Construction area which is proposed to
happen from 16:30 Hrs to 17:15 Hrs at Offsite SITE OFFICE
•
ENERLEX PTW STRUCTURE CONTRACTOR
PTW STRUCTURE
Signatories
IA
IA(Enerflex)
(Enerflex) ENERFLEX
PTW Contractor
Coordinator PTW
Coordinator
AA
AA(Enerflex)
(Enerflex)
Affected
Affected
Parties
Parties
PA
PA(Main/Sub
(Main/SubCont)
Cont)
HOW THE SYSTEM PROPOSED TO
WORK
Step 1
PA ENERFLEX PTW Coordinator reviews and inspects the request for a permit and relevant
documentation.
The review process is complete, It OK for the permit to be raised
ENERFLEX PTW Office now will collect the permit (registering takes place by each
Contractor PTW office)
No signatures at this stage.
Permit requestor and Performing Authority shall not sign in advance permit PA section
HOW THE SYSTEM PROPOSED TO WORK
contd…
Step 2
PA/Permit Requestor or Contractor PTW Coordinator /Administrator takes the permit to the
respective AA) to discuss the task and to review any required certificates, documentation, and
controls to be implemented.
PA
Review process complete with AA.
Step 3
PC forwards the Permit to the respective AA on the field for his review via Contractor
PTW Coordinator/Permit requestor
The permit is with AA. (for critical activities)
PC
No signatures at this stage.
HOW THE SYSTEM PROPOSED TO WORK contd…
Step 4
AA checks the worksite and ensures all the precautions can be implemented and agrees to make
regular checks at the work site to ensure permit requirements are met. AA reviews any conflicts with
previously raised permits/works.
Once the AA is satisfied, permit will be addressed to the IA review and approval at the Signing Session.
Any permits not accepted by AA shall be returned to IA at the signing session for rectification or
cancellation.
No signatures at this stage.
HOW THE SYSTEM PROPOSED TO WORK contd…
Step 5
IA reviews the Permit / Supporting documents at the daily Signing Session
subject to AA review being completed.
If Affected Parties are involved, they sign in at the signing session following the
AAA signature of the IA.
HOW THE SYSTEM PROPOSED TO WORK contd…
Step 6
AA at his carefulness signs the permit either at the Signing Session or at the site on the following
day.
If AA decides to sign a permit just before the work commencement and his personal site visit and
verification of the contractor’s preparedness, he will withhold the permit and sign it at site on the
AA following day.
Once signed, a permit is handed over to the PC, and PA comes to Permit Office and Sign the permit
HOW THE SYSTEM PROPOSED TO WORK
contd…
Step 7
PC collects the permit from ENERFLEX AA (if signed at the signing session).
PC confirms understanding and agreement to implement all required controls as per the permit
IA conditions.
PC transfers the permit to PA and arranges for any required isolations and gas tests if required by
permit conditions.
No signatures at this stage.
HOW THE SYSTEM PROPOSED TO WORK Contd…
Step 8
PA accepts and signs the Permit from PC, before commencing the work conducts TBT and pre-
task briefing of the crew on the hazards and control measures to be adopted.
Step 9
AA or his delegate visits the site before work commencement to ensure all the permit requirements
are met by PA.
AA The permit will become live only when the day’s endorsement is done by all (AA,& PA)
PC retains Copy # 2 and PC updated the PTW database for the Issued and Approved Permit
HOW THE SYSTEM PROPOSED TO WORK
Contd…
Step 10
Once the work is finished / permit validity expires / permit is suspended for any reason, the PA must
make the worksite safe or initiate the revalidation process for the permit.
PA PA Signs the Permit and Hands over the permit to PC (Permit office at the end of the shift)
If the permit is suspended for any reason PA MUST IMMEDIATELY inform the PTW Office and
respective IA and AA
HOW THE SYSTEM PROPOSED TO WORK
Contd…
Step 11
The AA visits the site on completion of the task to verify the site is left in a safe
condition.
AA
AA will close the Permit by signing it.
PA & and AA visit the work area and if all is okay PA collect the permit and hands it to PC
In case the condition does not meet requirements PA keeps
the permit till control measures are in place(if any hazardous work-related and site visit is required)
ENERFLEX/
PTW SIGNATORY JOB POSITION
ENERFLEX / CONTRACTOR
PTW SIGNATORY JOB POSITION
CONTRACTOR
Approving
ENERFLEX Authority (IA) ENERFLEX
Approving Enerflex Area Manager Construction Manager
ENERFLEX Authority (IA) Area Manager-Delegate
to Field Supervisor
Enerflex Field
Enerflex Discipline ENERFLEX Discipline
Area Authority(AA)
Superintendent Superintendent
ENERFLEX Area Authority (AA)
delegated to Field
Supervisor
Main Contractor
Discipline Supervisor/ Main Contractor
Performing MAIN CONTRACTOR Performing
Delegated to Charge Discipline Supervisor/
MAIN CONTRACTOR Authority (PA) Authority (PA)
Hand Foremen
Proposal
Present
• IAs; AAs – Refresher training and introduction to PTW Rev. – Max 1 hours
• PA’s – Max 2 Hour custom refresher training and introduction to PTW Rev.
• Newcomers – 2-hour full PTW/TRA Training on Rev.
• Contractor PTW Coordinators* – Full refresher training + 2-hour Workshop with Enerflex PTW Coordinator
• GENERAL NOTE:
• The PTW courses can be modified in consultation with senior management to suit particular site needs
and requirements.
Other Points To Emphasis
• Always try to take the permit for the minimum number of days required for the task with
minimum buffer days (Max 07 days) as it is observed in many cases the permits are
issued for 7 days only even if task can be finished in 2 to 3days.
• IF The Task is Finished before attaining the max validity period, return the permit to
Area PTW Office Immediately
• Remember there will be a limitation on the number of permits, that can be “SAFELY
ISSUED AND HANDLED IN EACH AREA” (Presently the system is under monitoring to
implement the limitations )
•
• Take utmost care While filling up and handling Work permits & Certificates. “
Overwriting or using correction fluid invalidates any permit or certificate resulting in “
IMMEDIATE CANCELLATION” (any mistakes or errors has to be crossed out with a
SINGLE LINE and INITIALLED by the IA& AA)