Project Charter
Project Management Plan
Project Scope Baseline
» Scope Statement
» WBS
» WBS Dictionary
» Sponsor Acceptance
Project Schedule Management
» Project Schedule Management Plan
» Project Gantt Chart
» Project Network Schedule Diagram
2 of 94
Project Charter
• PROJECT GOALS
• DELIVERABLES
• SCOPE DEFINITION
• PROJECT MILESTONES
• ASSUMPTIONS, CONSTRAINTS & DEPENDENCIES
• PROJECT STAKEHOLDERS
• PROJECT AUTHORIZATION
3 of 94
Project Charter
Project Name: Construction of a Hospital Project Number: 007
Date: 01 May 2023 Revision Number: 1.0
1. PROJECT GOALS
The business need for this project is to provide healthcare services to the local community. The hospital will be a modern facility that
meets the healthcare needs of the community.
2. DELIVERABLES
3. SCOPE DEFINITION
3. SCOPE DEFINITION
4. PROJECT MILESTONES
Assumptions:
• Availability of sufficient funding for the project
• Availability of qualified and skilled labor for the construction and installation work
• Compliance with all regulatory requirements
Project Charter
Project Name: Construction of a Hospital Project Number: 007
Date: 01 May 2023 Revision Number: 1.0
Constraints:
• Time constraints due to the need for the hospital to be operational within the planned timeline
• Budget constraints due to the need to stay within the allocated budget
Dependencies:
• Availability of necessary medical equipment and fixtures for installation
• Availability of regulatory approvals and licenses
6. PROJECT STAKEHOLDERS
The project stakeholders include the hospital administration, the medical staff, the patients, the local community,
and the regulatory authorities..
7. PROJECT AUTHORIZATION
Scope Baseline
•Purpose
•Scope Statement
•Work Breakdown Structure (WBS)
•WBS Dictionary
•Sponsor Acceptance
Scope baseline
(logo) (PNEC - MEM)
1.Product Scope Description: The General Hospital construction project aims to create a modern,
state-of-the-art hospital facility that can provide high-quality medical care to the local community.
The hospital will have the capacity to accommodate 200 patients and will offer a wide range of
medical services, including emergency care, outpatient services, and inpatient care.
2. Product Acceptance Criteria: The hospital will be accepted as complete when it meets the
following requirements:
• All construction work is finished and the facility is fully operational
• The hospital is equipped with all necessary medical equipment and supplies
• All required licenses and permits are obtained from regulatory bodies
• The hospital meets all applicable safety and environmental regulations
3. Project Deliverables: The following are the deliverables that will result from the project:
• Fully constructed and operational hospital facility
• Medical equipment and supplies
• Regulatory licenses and permits
Project Scope Statement
(logo) (PNEC - MEM)
4. Project Exclusions: The following work is not included in the project and is outside of the
scope:
• Acquisition of land for the hospital
• Staff hiring and training
• Ongoing maintenance and operations of the hospital after construction is complete
6. Project Assumptions: The following assumptions are being made by the project team and
stakeholders:
• The land for the hospital has already been acquired
• The necessary permits and licenses can be obtained in a timely manner
• The project team has the necessary skills and experience to complete the project within
the specified time and budget
WBS
(logo) (PNEC - MEM)
Project Schedule Management Plan Document Project. #: 007 Date: 01 May 2023
Description Construction of a Hospital – SMP Revision #: 1.0 Page: 1 of 6
1. Project Schedule Overview
• The project schedule will cover the entire duration of the project from site
selection to the completion of installation of medical equipment, fixtures, and furniture.
• The total duration of the project is 28 months.
• The project will be divided into three major phases: site selection, design and
construction, and installation of medical equipment, fixtures, and furniture.
2. Site Selection Phase
• Duration: 1 month
• Activities:
• Conduct site surveys
• Analyze site data and make recommendations
• Finalize site selection and acquire necessary approvals
3. Design and Construction Phase
• Duration: 24 months
• Activities:
• Develop detailed design plans
• Obtain necessary permits and approvals
• Begin construction
• Conduct quality control checks and inspections
• Manage contractor and subcontractor schedules
Project Schedule Management Plan
(logo) (PNEC - MEM)
Project Schedule Management Plan Document Project. #: 007 Date: 01 May 2023
Description Construction of a Hospital – SMP Revision #: 1.0 Page: 1 of 6
Project Schedule Management Plan Document Project. #: 007 Date: 01 May 2023
Description Construction of a Hospital – SMP Revision #: 1.0 Page: 1 of 6
Project Schedule Management Plan Document Project. #: 007 Date: 01 May 2023
Description Construction of a Hospital – SMP Revision #: 1.0 Page: 1 of 6