Professional Documents
Culture Documents
Smart Grid Demonstration Project - Dynamic Line Rating (DLR)
Smart Grid Demonstration Project - Dynamic Line Rating (DLR)
– Temperature
– Solar radiation
Oncor Electric Delivery Company LLC Justin Johnson ERCOT ROS Presentation 06/25/2010 3
How Weather Conditions Affect Ratings (Illustrative Only)
Ambient Temperature:
– 2oC fluctuation +/- 2% capacity,
– 10oC drop in ambient + 11% capacity
Solar Radiation:
– Cloud shadowing +/- a few percent,
– Total eclipse + 18% capacity
Oncor Electric Delivery Company LLC Justin Johnson ERCOT ROS Presentation 06/25/2010 4
What to Monitor?
Dead-end Dead-end
Oncor Electric Delivery Company LLC Justin Johnson ERCOT ROS Presentation 06/25/2010 5
Tension Monitoring - Dynamic Line Rating
Dead-end Dead-end
Tension Equalizes
Oncor Electric Delivery Company LLC Justin Johnson ERCOT ROS Presentation 06/25/2010 6
Dynamic Line Rating Concepts
(Illustrative Only)
Know true line capacity in real time
Improve system reliability
Optimize grid utilization
De
sig
n
I so
Dynamic Line Rating
th
er
m
Oncor Electric Delivery Company LLC Justin Johnson ERCOT ROS Presentation 06/25/2010 7
Impact On Transmission Grid Operations
Example Of Safely Managed Contingency
Dynamic
Rating
Static
Rating
Actual
Load
The operator would have been forced to move the grid off its optimum dispatch
Oncor Electric Delivery Company LLC Justin Johnson ERCOT ROS Presentation 06/25/2010 8
LOCATION OF INSTRUMENTED CIRCUITS
Oncor Electric Delivery Company LLC Justin Johnson ERCOT ROS Presentation 06/25/2010 9
DLR Smart Grid Demonstration
Oncor Electric Delivery Company LLC Justin Johnson ERCOT ROS Presentation 06/25/2010 10
PROJECT OBJECTIVES
Operational Objectives
Relieve congestion and transmission
constraints
Gain operational knowledge of DLRs for
wide scale deployment
Ensure that safety code clearances are not
impacted
Demonstrate that multiple monitoring units
can be integrated into operations
Identify/quantify other operational limits that
may impact ability to raise ratings
Oncor Electric Delivery Company LLC Justin Johnson ERCOT ROS Presentation 06/25/2010 11
PROJECT OBJECTIVES
Demonstration Objectives
Extrapolate the impact of DLRs
on the study’s transfer path to
entire ERCOT region
Determine a methodology to
release day-ahead ratings
Develop user friendly tools for
the operator to manage
improved WASA
Oncor Electric Delivery Company LLC Justin Johnson ERCOT ROS Presentation 06/25/2010 12
PROJECT OBJECTIVES
Economic Objectives
Quantify economic value of
released transmission capacity to
market
Estimate the savings associated
with deferral of rebuilding,
reconductoring, or building new
circuits
Quantify the total costs of
implementing this type of DLR
Oncor Electric Delivery Company LLC Justin Johnson ERCOT ROS Presentation 06/25/2010 13
Integrated Dynamic Line Rating Systems
• Tension-based Dynamic
Line Rating System for
overhead transmission
lines
• Tension resolves all
environmental factors
for accurate results
• Best way to capture
spatial variability of
wind, sun, air
temperature
• Captures as built, as
aged condition of line
• Communicates with
utility’s Energy
Management System
Oncor Electric Delivery Company LLC Justin Johnson ERCOT ROS Presentation 06/25/2010 14
Real Time Rating - Loadcell Monitors Tension
Oncor Electric Delivery Company LLC Justin Johnson ERCOT ROS Presentation 06/25/2010 15
Real Time Rating – Communications Package
Solar powered
Oncor Electric Delivery Company LLC Justin Johnson ERCOT ROS Presentation 06/25/2010 16
Integrated Dynamic Line Rating Systems
Transmission Line
License free
Spread Spectrum Radio
CATMasterTM
Base Station Substation
Existing SCADA protocol
over substation RTU channel
(RS232/485)
Control Center
IntelliCATTM
for Windows
ICCP or MODBUS protocol
Oncor Electric Delivery Company LLC Justin Johnson ERCOT ROS Presentation 06/25/2010 17
MAJOR PARTICIPANTS
• Oncor
Purchase DLR equipment and manage project
• The Valley Group, a Nexans company
Provide DLR equipment
• Siemens Energy, Inc.
Integrate DLR technology into Oncor’s TMS system
• Chapman Construction Company
Install equipment on designated circuits
• Southwest Research Institute
Perform independent analysis
Oncor Electric Delivery Company LLC Justin Johnson ERCOT ROS Presentation 06/25/2010 18
PROJECT TIMELINE
Design/Initial
Procurement
Project Studies
Initial Device
Installation
Fine-tune Initial
Device Output
Terminal Upgrades
Reporting (Quarterly
to DOE)
Remaining Device
Installation
Final Report
Submitted to DOE
Oncor Electric Delivery Company LLC Justin Johnson ERCOT ROS Presentation 06/25/2010 19
Summary
• Target Completion is 2nd Quarter 2013
• Provides two years of summer peak data
• Will provide a “roadmap” for other utilities to follow - study will be
public
• Success Factors include increasing transmission capacity and
removing existing commercial constraints to DLR technology
• All eight circuits should be instrumented by end of this year
Oncor Electric Delivery Company LLC Justin Johnson ERCOT ROS Presentation 06/25/2010 20