Kajian Keekonomian Usaha Kontraktor Tambang Batubara
Kajian Keekonomian Usaha Kontraktor Tambang Batubara
SHOVEL TRUCK
TAHAPAN USAHA TAMBANG
EKSPLORASI
STUDI
AMDAL
KELAYAKAN
TDK
ARSIP LAYAK
YA
DEVELOPMENT
EKSPLOITASI
MINING FLOW PIT to PORT
Waste Dumping Top Soil Spreading
Re-vegetation
Coal Crushing
35 Km
Coal Transport
To Port Stockyard
4
LANDCLEARING DAN TOPSOIL REMOVAL
Original
Area
Land Clearing
Topsoil Removal
Topsoil
Disposal
OVERBURDEN REMOVAL
DRILLING
RIPPING
LOADING
DOZING
BLASTING
OB
HAULING
SUPPORT
GRADER
DUMPING DISPOSAL
WATER TRUCK
COAL
HANDLING
COAL
LOADING
COAL
HAULING
TRUCK
ROM
SCALE
STOCKPILE
COAL WINNING
CRUSHER
HOPPER
CRUSHING
PLANT
LOADING BARGING TO
TO BARGE OVERSEAS
TRANSHIPMENT
RESIKO DALAM USAHA TAMBANG :
RESIKO KECELAKAAN
Tabrakan
Slip /Tergelincir
Slip /Tergelincir
RESIKO KECELAKAAN
Stockpile terbakar
Drilling Machine
Bulldozers
Hydraulic Excavators
Backhoe
Shovel
Wheel Loader
Dump Truck :
Rigid DumpTruck
Articulated Dump Truck
Motor Grader
Compactor
.
SIFAT MATERIAL
BANK LOOSE
COMPACTED
CONVERSION FACTOR OF MATERIAL
CLAY SAND
COAL
Fe-ORE
PRODUKTIVITAS ALAT
• Fungsi dari :
• Kapasitas Alat (Machine)
• Cycle time (Machine)
• Sifat material (kekerasan, berat jenis) (Material)
• Kondisi lapangan (Environment)
• Skill operator (Manpower)
PRODUKTIVITAS ALAT MUAT
Prod’tas = C x bf x 3600 x je
cm
= 1,163 bcm/jam
PRODUKTIVITAS ALAT ANGKUT
• Produkttivitas = C x 60 x je
cmt
= 232.56 lcm/jam
= 186.04 bcm/jam.
PERFORMANCE ALAT
AVAILABILITY HYRARCHY
S
Standby
R
Repair
Working
(W + S) W Production
PA = UA = Prod’ty =
(W + R + S) (W + S) W
DEFINITION
W = Working
R = Repair
S = Standby
Production x (W + S) x W
Production = N x (W + R + S) x
W (W + R + S) (W + S)
N = Production = Production x 1 x 1
Prod’ty xMOHH x UA x PA Prod’ty MOHH x UA PA
= W x 1 x 1
MOHH x UA PA
W x 1
MOHH x UA PA
= Running Eq.
PA
CALCULATION
1,000,000 Bcm
W= 100 Bcm/Hr
= 10,000 hrs
10,000 hr
Running Eq. = 720 hr x 70%
= 19,84
19,84
Active Eq. = 85%
= 23,34 24
RE-CHECK
Office
Workshop
Base Camp
HA
UL
ING
PORT
Biaya Tambang
Tunnel
(THE FUTURE)
CAPITAL EXPENDITURES
OPERATING EXPENSES
PA dan UA
Contoh :
Alat angkut HD785 , PA = 85%
Available hrs = 85% x 366*24 = 7,466 jam
Lost time :
hujan 1,087 jam
licin 275 jam
libur 120 jam
makan 270 jam
moving 90 jam
» MIRR = 12.1%
Biaya aktivitas tambang :
(contoh)