This document provides details of ongoing development projects, including the construction of hydropower projects and installation of diesel generators. It lists 3 hydropower projects experiencing delays or cost increases: a 2 MW project in Dahitar is being revised to add 2 more MW; a 1.5 MW project in Budalas is delayed as work on the channel has yet to start and turbine generator sets are delayed; and a 0.2 MW project in Hisper is delayed due to issues procuring turbine generator sets. It also notes a diesel generator tender was completed but costs were too high so the scheme is being revised. Compensation costs for a 2 MW project in Dahitar are being revised upwards to cover additional affected structures.
This document provides details of ongoing development projects, including the construction of hydropower projects and installation of diesel generators. It lists 3 hydropower projects experiencing delays or cost increases: a 2 MW project in Dahitar is being revised to add 2 more MW; a 1.5 MW project in Budalas is delayed as work on the channel has yet to start and turbine generator sets are delayed; and a 0.2 MW project in Hisper is delayed due to issues procuring turbine generator sets. It also notes a diesel generator tender was completed but costs were too high so the scheme is being revised. Compensation costs for a 2 MW project in Dahitar are being revised upwards to cover additional affected structures.
This document provides details of ongoing development projects, including the construction of hydropower projects and installation of diesel generators. It lists 3 hydropower projects experiencing delays or cost increases: a 2 MW project in Dahitar is being revised to add 2 more MW; a 1.5 MW project in Budalas is delayed as work on the channel has yet to start and turbine generator sets are delayed; and a 0.2 MW project in Hisper is delayed due to issues procuring turbine generator sets. It also notes a diesel generator tender was completed but costs were too high so the scheme is being revised. Compensation costs for a 2 MW project in Dahitar are being revised upwards to cover additional affected structures.
This document provides details of ongoing development projects, including the construction of hydropower projects and installation of diesel generators. It lists 3 hydropower projects experiencing delays or cost increases: a 2 MW project in Dahitar is being revised to add 2 more MW; a 1.5 MW project in Budalas is delayed as work on the channel has yet to start and turbine generator sets are delayed; and a 0.2 MW project in Hisper is delayed due to issues procuring turbine generator sets. It also notes a diesel generator tender was completed but costs were too high so the scheme is being revised. Compensation costs for a 2 MW project in Dahitar are being revised upwards to cover additional affected structures.
Name of Project Alloc Release Issues/Remarks for Revision No Approval Cost June 2023 Forwd
Const. of 02 MW 02 MW is operational, scheme is
27.01.201 0.25 188 HPP Dahiter 4 356.830 356.578 0.252 2 0 under revision for additional 02 Nagar, Gilgit. MW
1. 90% Penstock Pipe fixed.
2. Power House complete Upto roof level. Construction of 1.5 113.05 10.00 3- Forebay cutting work is complete. 191 MW HPP Budalas. 13/4/2018 247.101 134.043 0 8 0 4. Work on channel not yet started 5.Tender of T/G Set and 30% mobilization advance paid, however TG sets delayed due to LC issue
Civil Work & E/M Work almost 80%
Construction of complete . 192 0.200 MW HPP 16/4/2019 95.073 93.962 1.111 1.111 0 Hisper. T/G Sets is delayed due to LC issue. Scheme is submitted for revision. Supply and Tender of D/G set complete however Installation of 01MW 193 DG set for 31/12/2021 0 50.00 50.00 0 due to high tender rates scheme has 50.000 Askurdass Nagar. submitted for revision COMPENSATION OF DAMAGES 02 MW DAHITAR
S.No. Item Cost as per Original PC-I Revised Cost Remarks
Additional cost will cover
structures within 350 ft range 1 Land Compensation 6.00 million 31.500 million on both sides of penstock pipe