DETAIL OF ONGOING DEVELOPMENT PROJECTS.

ADP Date of Approved Exp Upto Thru


Name of Project Alloc Release Issues/Remarks for Revision
No Approval Cost June 2023 Forwd

Const. of 02 MW 02 MW is operational, scheme is


27.01.201 0.25
188 HPP Dahiter 4
356.830 356.578 0.252
2 0 under revision for additional 02
Nagar, Gilgit. MW

1. 90% Penstock Pipe fixed.


2. Power House complete Upto roof
level.
Construction of 1.5 113.05 10.00 3- Forebay cutting work is complete.
191 MW HPP Budalas. 13/4/2018 247.101 134.043 0
8 0 4. Work on channel not yet started
5.Tender of T/G Set and 30%
mobilization advance paid, however TG
sets delayed due to LC issue

Civil Work & E/M Work almost 80%


Construction of
complete .
192 0.200 MW HPP 16/4/2019 95.073 93.962 1.111 1.111 0
Hisper. T/G Sets is delayed due to LC issue.
Scheme is submitted for revision.
Supply and Tender of D/G set complete however
Installation of 01MW
193 DG set for 31/12/2021 0 50.00 50.00 0 due to high tender rates scheme has
50.000
Askurdass Nagar. submitted for revision
COMPENSATION OF DAMAGES 02 MW DAHITAR

S.No. Item Cost as per Original PC-I Revised Cost Remarks

Additional cost will cover


structures within 350 ft range
1 Land Compensation 6.00 million 31.500 million
on both sides of penstock
pipe